Under Trump's emergency order, this pipeline through the Great Lakes wetlands could get fast-tracked
The Army Corps of Engineers, citing a recent national energy emergency order by President Trump, has expedited a permit review for a new miles-long section of an oil and gas pipeline that would bore deep into protected wetlands bordering Canada and the United States.
The pipeline request from Enbridge Energy, a Canadian company, would cut beneath the Straits of Mackinac—the connecting waterway between Lakes Michigan and Huron—to install a tunnel 12 times as wide as above-ground existing pipelines. Tribal groups that had been cooperating with the Corps' environmental impact statement for the project pulled out when they learned of the emergency review. The Corps announced April 15 that the project, known as Line 5, fits under Trump's January order.
The project is part of a 645-mile pipeline between Superior, Wisconsin, and Sarnia, Ontario, that transports about 22 million gallons of oil and natural gas liquids daily, according to the company website.
The Corps' decision to expedite consideration came days before a sweeping change by the U.S. Department of Interior to hasten energy reviews. The federal agency said beginning April 23 that energy-related projects and, specifically, environmental impact reviews of such projects will move with unprecedented speed and with truncated public comment. Energy, under Trump's order, refers to fossil fuels such as oil, gas, and coal, along with geothermal, nuclear and hydropower.
The Corps operates within the Defense Department, not the Interior Department. While the Interior policies do not apply to Line 5, they are likely to accelerate fossil fuel projects in the coming months. New emergency procedures from both departments in response to Trump's executive order are 'really ploughing new ground,' said Dave Scott, a senior attorney at the Environment Law & Policy Center, a legal advocacy group.
'There is a massive and real risk that the public won't be able to engage meaningfully with decisions that government agencies like the Corps are making that have significant impacts on the environment,' Scott said.
The Interior Department announced last week it was pursuing what it called an ' alternative National Environmental Policy Act,' to allow for sharply compressed timelines for projects that 'strengthen domestic energy supply.' Projects that require an environmental assessment, which the department said now takes a year to complete, will be reviewed within 14 days. Projects in need of an environmental impact statement, which the department said can result in two years of study, will be reviewed in 'roughly 28 days,' according to its announcement.
Scott also noted a second executive order, Unleashing American Energy, further erodes environmental protections for new projects. It directs the Council on Environmental Quality to consider rescinding National Environmental Policy Act regulations, which are the rules that require federal agencies to consider environmental impact when issuing permits.
Environmental groups have questioned the need and the rationale behind the pipeline change.
'We know that there is no national energy emergency,' said Julie Goodwin, senior attorney at Earthjustice, the country's biggest public interest environmental firm. The U.S. produces more crude oil than any other country, ever, and has for the past six years. The emergency process 'is really a gift to the fossil fuel industry,' Goodwin said.
At issue is Enbridge's replacement of two 20-inch diameter pipelines now buried close to shore and resting or supported on the lakebed. Instead, it wants to dig a 3.6-mile-long tunnel, with a 21-foot diameter, into the Straits' lakebed.
The Corps is still developing an environmental impact statement for the Straits project, which it acknowledges will 'permanently impact 1.52 acres of wetlands, including 1.01 acres within the Corps' responsibility under Section 404 of the Clean Water Act.' The statement is expected in June.
'The Detroit District has not yet determined the length of the public comment period for its Line 5 Tunnel,' the Corps said in an email. The standard comment period is 60 days, but the Corps' new policy for emergency reviews is 15 days.
The Interior Department announcement last week may indicate a new public comment timeline in store for energy-related projects. In some cases, public comment at Interior would depend largely on the decision of department officials. Proposals found to have 'no significant impact' during an internal department assessment will have a report issued on a public website, the announcement said, and no public comment is required.
For projects 'likely to have significant environmental impact,' a department official 'can determine the duration of the written comment period based on the nature of the action and the urgency of the emergency response, and the Department anticipates that most comment periods will be approximately 10 days,' Interior's announcement said.
Regarding the pipeline project before the Corps, seven local tribes described the shortened environmental impact statement (EIS) process as 'unacceptable.'
A letter was sent in March to the Corps and signed by representatives from the Bay Mills Indian Community, Little River Band of Ottawa Indians, Sault Ste. Marie Tribe of Chippewa Indians, Grand Traverse Band of Ottawa and Chippewa Indians, Match-E-Be-Nash-She-Wish Band of Pottawatomi, and Nottawaseppi Huron Band of the Potawatomi.
'Tribal Nations are no longer willing to expend their time and resources as Cooperating Agencies just so their participation may be used by the Corps to lend credibility to a flawed EIS process and document,' the letter said. The Corps 'has disregarded its commitments to cooperating agencies and its obligations under the National Environmental Policy Act by fully aligning itself with the applicant [Enbridge] at every step.'
The emergency review process 'is really rewriting and bypassing critical and important laws for an unneeded pipeline,' said Beth Wallace, director of climate and energy at the National Wildlife Federation, the nonprofit conservation education and advocacy group.
Enbridge has said the existing pipes, which date back to 1953, need replacement to prevent a possible oil spill. Burying the new pipeline section as much as 100 feet below the lakebed would 'eliminate the chance of a pipeline incident in the Straits,' according to the project website.
'Line 5 is critical energy infrastructure,' Enbridge said in an email to Inside Climate News. The tunnel project is 'designed to make a safe pipeline safer while also ensuring the continued safe, secure, and affordable delivery of essential energy to the Great Lakes region.' On its website, the company called its supply to Michigan 'vital' and said that 'Line 5 supplies 65% of propane demand in the Upper Peninsula, and 55% of Michigan's statewide propane needs.'
Tribal groups, citizens, and environmentalists have called for decommissioning the pipeline out of concern for risks to freshwater sources and local ecosystems. The Great Lakes are the largest freshwater system on the planet, providing clean drinking water to more than 40 million people in the U.S. and Canada.
'Enbridge's own pipelines have capacity to pick up product and move it to the same exact refineries and facilities,' said Wallace of the National Wildlife Federation. Investing further in fossil fuel infrastructure also runs counter to Michigan's plan to reach 100 percent carbon neutrality by 2050, she added.
An economic analysis by PLG Consulting, a Chicago-based logistics firm, examined how shutting down Line 5 could impact energy markets. 'Surging output' has made North America energy independent and 'there is no risk of supply shortages,' the PLG report from October 2023 found. There are a 'multitude' of alternative supply sources from both domestic and international sources that could fill in for Line 5. Even today, no refinery relies entirely on Line 5 for its crude oil supply, the PLG report said.
Enbridge is still waiting on several federal and state permits before it can begin construction. The state of Michigan issued environmental permits for the tunnel project in 2021 but those will expire next year. Enbridge re-applied earlier this year to renew the permits.
The Michigan Public Service Commission approved the tunnel project in 2023 although Enbridge still needs the permitting decision from the Army Corps.
The activist group Oil and Water Don't Mix is also urging citizens to demand that Gov. Gretchen Whitmer deny the pipeline permit to protect the Great Lakes. 'The state of Michigan has the opportunity to shut down Line 5,' Earthjustice's Goodwin said. 'And that's what should happen.'
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Wall Street Journal
11 minutes ago
- Wall Street Journal
10-Year Treasury Yield Heads Toward Largest Decline Since April 14
1316 ET — The yield on the 10-year U.S. Treasury note is headed toward its biggest one-day decline since April 14 after a pair of lackluster reports on the U.S. economy. Yields, which fall when bond prices rise, began sliding early in the session after the ADP's National Employment report showed that 37,000 jobs were created in May, the slowest pace of private-sector hiring in two years. Economists polled by The Wall Street Journal projected hiring would increase by 110,000 new jobs. Yields extended their decline after an ISM services report, which suggested that activity among service firms fell unexpectedly in May. The survey's index for new orders and inventories both sank into contraction, with respondents reporting difficulty in planning due to uncertain tariff policies. The 10-year yield recently traded near 4.36%, down from 4.46% Tuesday. ( 0841 ET – An ominous sign from the U.S. labor market triggers a rush to Treasury bonds, driving yields sharply lower. ADP says only 37,000 jobs were created by private employers in May, the lowest since March 2023. Economists surveyed by WSJ expected 110,000. ADP revises the April figure to 60,000 from 62,000 and says hiring is losing momentum while pay growth remained at robust levels. The report may reflect businesses reluctance to hire amid tariffs uncertainty. Trump cites the report to call on the Fed to lower rates. Friday, payrolls are expected to slow a little from April. The 10-year is at 4.419% and the two-year at 3.931%. ( @ptrevisani)


CNET
11 minutes ago
- CNET
EcoFlow Has Slashed Prices by Up to 55% Ahead of Father's Day
If you enjoy summer travel, outdoor adventures, or live in an area where the weather can disrupt the power supply, a portable power station or power bank is the perfect way to ensure your devices stay charged. Today's power stations and power banks are more compact and lightweight than ever, making them even easier to transport for almost everyone. Right now, EcoFlow is offering multiple deals that can help you save on various devices, with savings of up to 55% when you purchase directly from their website. Amazon also has several EcoFlow deals, just be aware that their offers might vary. EcoFlow's disaster preparedness deals are live until June 8 and include bundles that can power larger appliances and even medical devices for a long time, as well as solar panels to charge the included power station. The EcoFlow Delta 3 bundle features the power station and a 220W solar panel, all for $999. If only the power station is needed, you can get it for just $699 and save $100 over its original asking price. Other bundle options include the EcoFlow Delta 2 portable power station and a 500-watt solar panel for $1,499, a total of $1,200 in savings. This power station has a 6144Wh capacity that can power devices inside your home as needed. It's also built to efficiently store solar energy that the panel converts to stay charged even in the most trying conditions. EcoFlow has also partnered with Costco to offer the River 3 Plus combo, which includes two power banks, for just $279. The portable power station has a 286Wh capacity suitable for camping needs, and the bundle comes with a 15W wireless power bank and a 30W cable power bank. EcoFlow is also running a Father's Day and summer travel sale from June 9 until June 15. We'll keep you updated when the deals are live for more opportunities to save. To take better advantage of these deals, check out our article that explains how to choose the best portable power station for your needs. Why this deal matters EcoFlow is behind some of our favorite portable power stations, and their solar panels only add value -- ensuring that you can keep them charged, even when there's no outlet. The brand is offering several deals via its own website, in partnership with Costco, and through its official Amazon storefront. Keep in mind that some deals expire on June 8, and others start on June 9 and end on June 15 if you purchase through EcoFlow's website. Still, now is the perfect opportunity to purchase a portable power station, as there are options for many budgets.
Yahoo
12 minutes ago
- Yahoo
Gold Turns Higher on Increased Uncertainty
Gold prices gain as comments from President Trump instill some new economic worries heading into the summer. Trump posted on his Truth Social account that China's President Xi was "extremely hard to make a deal with," and also demanded Fed Chair Jerome Powell lower interest rates.