Hi-tech protection for birds at risk from SA's wind turbine farms

Hi-tech protection for birds at risk from SA's wind turbine farms

Daily Maverick20-05-2025
What has been described as 'South Africa's first automated bird protection system' has gone live at Red Rocket's Brandvalley and Rietkloof wind farms, using AI-powered detection and turbine shutdowns to protect vulnerable species.
An automated bird protection system has been installed at Red Rocket's wind farms between the Western Cape and Northern Cape provinces in South Africa with advanced shutdown-on-demand functionality.
The system has been fully installed and is active at the 144MW Brandvalley and 144MW Rietkloof Wind Farms, which announced the commencement of commercial operations in April and are the first two projects under Round 5 of the Renewable Energy Independent Power Producer Procurement Programme (REIPPPP) to take on this technology.
Developed in partnership with international avian monitoring specialists Bioseco, the system uses advanced detection and shutdown-on-demand technology to prevent bird collisions with turbine blades – a persistent and controversial issue in wind energy development.
The system employs a suite of optical sensors and intelligent software to continuously monitor the airspace around selected turbines in bird-sensitive areas.
When a bird is detected approaching the danger zone, the system first deploys visual and audio deterrents. If the bird continues on a collision course, it automatically triggers a temporary shutdown of the turbine, allowing the bird to pass safely.
How it works is that modern camera-based systems, like the Bioseco Bird Protection System (BPS), mount six to eight stereovision modules on each turbine tower. The cameras monitor birds in real time, 360 degrees around the turbine.
Red Rocket's environmental and social manager, Ashleigh von der Heyden, and Sustainable Investments director Magdalena Michalowska Logan explained.
They said the system was configured to detect various sizes of bird species based on the wingspan of the species.
And when a bird (or flock) under conservation concern enters the 'danger zone', the system can initiate different tiers of mitigation, starting with non-harmful deterrent mechanisms, then moving on to automated turbine shutdown.
In case of automatic shutdown, Von Der Heyden and Logan said the relevant turbine received a 'stop command' and feathered its blades until the bird/birds had cleared the zone, after which it automatically restarted.
Depending on the turbine technology, they said it would typically take about 40 seconds to shut down the turbine.
This, in turn, was considered when sizing the trigger zone, along with bird species that would initiate such a command to shut the turbine down.
What they sought to ensure, according to Von Der Heyden and Logan, was that species of conservation concern were effectively protected through the implementation of tailored, fit-for-purpose mitigation measures – whether technological, operational or human-led across all their wind farm operations.
'This represents a huge leap forward over the current traditional, manually operated methods,' said Red Rocket CEO Matteo Brambilla in a media release.
Bioseco's commercial manager, Magda Bielawska, echoed the sentiment: 'Our mission is not only to protect birds, but to enhance wind-energy production through intelligent environmental integration.'
Why bird collisions matter
Wind energy's rapid expansion in South Africa – driven by the REIPPPP – has brought both environmental benefits and new challenges.
While wind farms help reduce fossil fuel dependence and curb greenhouse gas emissions, they can also pose significant risks to bird populations.
A 2017 report by BirdLife South Africa, reviewing the first operational wind farms under REIPPPP, found that diurnal raptors accounted for 36% of recorded fatalities, with songbirds making up 26%. Notably, threatened species such as the blue crane, Verreaux's eagle, martial eagle and black harrier were among those killed by turbine collisions.
The mean fatality rate was estimated at 4.1 birds per turbine per year, placing South Africa within the range observed in North America and Europe, but with particular concern for local species that may be more vulnerable due to their limited ranges or conservation status.
The report's authors stressed that, while the data were preliminary and based on a limited number of sites and years, a precautionary approach was warranted:
'The best mitigation technique is clearly the avoidance of any fatalities, however, this is not always possible and the importance of continuous monitoring during operation is therefore of utmost importance.'
Bird collisions at wind farms in SA
Daily Maverick previously reported that birds from at least 200 species have had fatal collisions with wind turbines in South Africa, and that almost every wind farm in the country has recorded fatalities of threatened and priority species.
In earlier rounds of renewable energy development under the REIPPPP, avian protection relied primarily on manual observation and/or human-led shutdown-on-demand protocols.
Von Der Heyden and Logan said these methods remained a valuable tool in a broader mitigation strategy and continue to be used where appropriate at their wind farms.
But they said that the industry had evolved significantly, as had scientific understanding, regulatory guidance and stakeholder expectations.
'The deployment of the Bioseco system is not intended to replace traditional methods, but to complement them – enhancing real-time responsiveness and contributing valuable data to support long-term monitoring outcomes,' they said.
The teams assess each project individually to determine the most appropriate combination of mitigation measures based on the species present, site conditions and the best available science.
BirdLife South Africa (BLSA) has been looking at an estimated rate of around 3-4 birds killed per turbine per year (across all species) with more than 1,400 turbines operating in 2023.
According to BLSA, one wind farm reported almost 50 birds killed per turbine per year, mostly swifts (ie not threatened).
Against this backdrop, BLSA welcomed the implementation of shutdown on demand at wind farms and believed most facilities in South Africa should adopt this strategy, either using technology or observers.
Samantha Ralston-Paton, the birds and renewable energy project manager at BLSA, said this was an important tool to help address bird collisions.
BLSA will soon publish a handbook on Shutdown on Demand (both technology-led and observer-led) to help developers, bird specialists and decision-makers implement shutdown on demand effectively.
'Not a silver bullet'
But, Ralston-Paton warned, shutdown on demand was not a silver bullet. 'It should never replace careful site selection and avoidance of areas where there is a high risk of bird collisions (eg near eagle nests),' she said.
The effectiveness of technology-led shutdown on demand will be influenced by the technology used, site, and species — ie the topography, number and location of devices installed, size of the target species and detection range.
Red Rocket acknowledged that the technology was not a comprehensive answer, but said that it performed a mitigation and monitoring function that superseded humans' capabilities and was not as weather dependent as human-based monitoring.
'This technology is promising for the ecological benefit of bird species that live in and around wind turbine facilities,' Von Der Heyden and Logan said.
Being the first technology in South Africa used solely for mitigating bird strikes, they said the technology would be monitored by independent bird specialists and the Red Rocket Team.
Previously, Ralston-Paton said that when it came to birds, the issue was not so much the impact of individual wind farms, but the cumulative effect of multiple wind farms, added to existing pressures on many bird species.
She used the example of the black harrier, which is classified as endangered. The actual number of black harriers lost thus far may not seem huge, but increasing the fatality rate by just 3-5 birds a year would accelerate its path to extinction, Ralston-Paton said.
'The population is already really small, with around 1,200 mature individuals,' she said.
The South African National Biodiversity Institute (Sanbi) says the proliferation of wind farms in the core black harrier breeding areas of the Western Cape coast to the Northern Cape, as well as in the newly discovered summer range in Lesotho, meant that harriers may be affected at both ends of their migratory cycle.
They said that this was an unknown threat, but that the species was high on the collision-sensitivity list of the Birds and Wind Energy Specialist Group.
'It is important to keep in mind that without mitigation, impacts could be ongoing for the 20-year lifespan of a wind farm, and we have plans to increase the number of turbines in SA (and therefore risk to birds) significantly over the next 10 years,' Ralston-Paton said.
Von Der Heyden and Logan said that they recognised that the bird species most at risk of turbine collisions were typically long-lived, slow to reproduce and wide-ranging. This meant that even a small number of fatalities could have significant population-level impacts, as mentioned by BLSA.
To address this, they apply a multi-layered mitigation approach that includes meticulous turbine micro-siting, advanced bird tracking technologies and adaptive shutdown-on-demand protocols that respond in real time to site-specific and seasonal conditions.
'These efforts are complemented by transparent data sharing and the appointment of independent avifaunal specialists to provide ongoing oversight,' Von Der Heyden and Logan said.
As for what Red Rocket learnt from this deployment, Von Der Heyden and Logan said they found that the automation system reduced downtime while improving protection.
'Manual spotters often shut down turbines for up to a 10-minute block. The camera-based, per turbine approach at Brandvalley and Rietkloof should see a reduction in unnecessary stops while still mitigating potential bird collisions, translating into both conservation and production gains,' they said.
They were calibrating the system to minimise downtime, and since it was a first in South Africa, Red Rocket said they would monitor the system soon to better understand the reduction of downtime for turbines. DM
Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Political interference nearly crippled South Africa's energy landscape
Political interference nearly crippled South Africa's energy landscape

IOL News

time06-08-2025

  • IOL News

Political interference nearly crippled South Africa's energy landscape

Former Eskom chief executive Brian Molefe. Image: Jacques Naude / Independent Newspapers As South Africa marks a decade of wind energy generation under the Renewable Energy Independent Power Producer Procurement Programme (REIPPPP), it must also reckon with a period when political interference nearly brought that progress to a halt. At the centre of that disruption stands former Eskom CEO Brian Molefe. Molefe's refusal to sign key renewable energy agreements delayed investment, deepened load shedding, and destabilised the sector. The resulting uncertainty cost the country billions and led to significant job losses, consequences that are still felt in the energy landscape today. Molefe was appointed CEO of Eskom in 2015, after a tenure at Transnet that would later come under scrutiny for enabling large-scale procurement irregularities. In August of that year, he and then-President Jacob Zuma celebrated the first unit of the Medupi coal-fired power station reaching commercial operation. The event was presented as a turning point. Zuma announced that load shedding was over, and the energy crisis resolved. That statement was not only premature, it was deliberately misleading. Medupi had already been delayed by four years and had exceeded its original budget by tens of billions of rand. The final unit would only come online in 2021. These delays placed immense pressure on older coal-fired power stations that needed scheduled maintenance. Without this planned downtime, system stability declined. Load shedding remained a necessary and increasingly frequent tool to prevent system collapse. Rather than use this milestone to support a balanced and diversified electricity mix, Molefe used it to justify delaying the signing of REIPPPP Bid Window 4 power purchase agreements. His reasons ranged from the claim that Medupi's output would suffice, to arguments about the tariffs being too high. Behind these justifications was a clear agenda: stall the growth of private-sector-led renewable energy. The impact of that decision was immediate. Local and international investors paused or withdrew. Project developers halted work. Manufacturing facilities scaled down. One of the most visible casualties was DCD Wind, which closed its newly launched wind tower manufacturing plant in the Coega Industrial Development Zone. Construction companies, including established South African firms like CONCO, were forced to shut down. Thousands of jobs were lost, and the momentum that had been building in the renewable sector was lost. Video Player is loading. Play Video Play Unmute Current Time 0:00 / Duration -:- Loaded : 0% Stream Type LIVE Seek to live, currently behind live LIVE Remaining Time - 0:00 This is a modal window. Beginning of dialog window. Escape will cancel and close the window. Text Color White Black Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Background Color Black White Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Transparent Window Color Black White Red Green Blue Yellow Magenta Cyan Transparency Transparent Semi-Transparent Opaque Font Size 50% 75% 100% 125% 150% 175% 200% 300% 400% Text Edge Style None Raised Depressed Uniform Dropshadow Font Family Proportional Sans-Serif Monospace Sans-Serif Proportional Serif Monospace Serif Casual Script Small Caps Reset restore all settings to the default values Done Close Modal Dialog End of dialog window. Advertisement Next Stay Close ✕ Ad loading Molefe's actions were part of a broader campaign to disrupt institutional reform in the energy space. He did not act alone. His efforts were supported by Zuma, the Gupta network, former Minister of Public Enterprises Lynne Brown, and two successive energy ministers, Mmamoloko Kubayi and David Mahlobo. It was only after Zuma's recall in February 2018 that political space opened for intervention. Within weeks, incoming Energy Minister Jeff Radebe approved the signing of the long-delayed Bid Window 4 agreements. On 4 April 2018, 27 projects were given the green light, unlocking R56 billion in investment. Why did this level of resistance to renewables exist at a time when the country was in the midst of a worsening electricity crisis? The answer lies in a political battle that continues to define South Africa's energy decisions. It is a struggle between competing factions within the ANC, between those who support transparency and decentralisation, and those who rely on state-owned institutions to control procurement, influence contracts, and preserve patronage. These centralist actors have long promoted mega-projects, including large coal and nuclear builds, as the default strategy for energy security. Such projects are consistently framed as job creators. The implication is that decentralised, private-sector-led electricity generation threatens employment, especially in the coal value chain. This narrative has been reinforced by unions and political allies, even as evidence shows that renewable energy procurement has supported broad-based investment, skills development, and regional economic growth. The Medupi and Kusile projects have made the risk of state-led mega projects clear. Both have suffered cost overruns, delays, and ongoing technical failures. These outcomes have weakened Eskom, undermined supply stability, and exposed public finances to inflated risk. Yet the same centralist arguments persist. Although the Zuma-Molefe axis is no longer in power, resistance to reform continues. In recent months, pressure against independent power generation and market liberalisation has increased again. This reflects a deeper reluctance to relinquish control of an energy sector that has long served as a channel for influence and enrichment. South Africa remains in a fragile position. There is no shortage of technical expertise, investor appetite, or policy guidance. What has been missing, repeatedly, is political alignment and the will to put the country's energy needs above personal or factional interests. If this dynamic does not shift, the country risks repeating the very failures that stalled progress a decade ago. Only a stable, rules-based environment that protects procurement integrity and regulatory independence will allow South Africa to rebuild a credible, reliable electricity future. Thomas Garner holds a Mechanical Engineering degree from the University of Pretoria and an MBA from the University of Stellenbosch Business School. Image: Supplied

Scatec clinches preferred bidder status for R13bn solar cluster in Free State
Scatec clinches preferred bidder status for R13bn solar cluster in Free State

IOL News

time24-07-2025

  • IOL News

Scatec clinches preferred bidder status for R13bn solar cluster in Free State

The project, known as the Kroonstad PV cluster, is expected to operate under 20-year Power Purchase Agreements (PPAs), ensuring a steady supply of sustainable energy once completed. Image: Supplied Norway-based renewable energy group, Scatec ASA, has been awarded preferred bidder status for a R13 billion solar cluster project in in the Free State province, which will add a total of 846MW to the electricity grid. In a statement on Wednesday, Scatec confirmed it had been awarded preferred bidder status in the seventh round of the Renewable Energy Independent Power Producer Procurement Programme (REIPPPP). The project, known as the Kroonstad PV cluster, is expected to operate under 20-year Power Purchase Agreements (PPAs), ensuring a steady supply of sustainable energy once completed. This latest development follows the Department of Electricity and Energy's strategic re-allocation of energy capacity from onshore wind to solar photovoltaic (PV) solutions. The cluster will comprise three solar power plants, Oslaagte Solar 2 (293MW), Oslaagte Solar 3 (293MW), and Leeuwspruit Solar (260MW). The estimated total project cost for the solar cluster project is R13bn ($735 million). The projects will be financed with up to 90% non-recourse project debt and the remaining by equity from the owners. Scatec CEO, Terje Pilskog, said South Africa was one of the group's core markets with the latest award the largest megawatt award to date in the country. 'It excites me to announce another important milestone for Scatec in South Africa and for the country's renewable energy transition. The Kroonstad PV Cluster represents a significant addition to Scatec's growing renewable energy footprint in Sub-Saharan Africa," Pilskog said. "Being selected once again under the REIPPPP reaffirms our role as a trusted partner and a leading developer in the region. We commend the government's continued commitment to enabling clean, secure, and affordable energy." Scatec will own 50.90% of the equity in the project with Stanlib's infrastructure fund (through its renewable energy platform, Greenstreet), along with Redstreet owning 46.50% and a Community Trust holding 2.6%. Scatec will provide engineering, procurement, and construction (EPC), operations and maintenance, and asset management services to the project. Financial close is expected in 2026. "We are now looking forward to reaching financial close and start construction of the PV cluster during 2026,' said Alberto Gambacorta, Scatec's executive vice-president and general manager for Sub-Saharan Africa. The group in December announced it had officially started producing and supplying electricity to the national grid from the three Kenhardt plants in the Northern Cape. The Kenhardt project, one of the world's first and largest hybrid solar and battery storage facilities, has an installed solar capacity of 540MW and a battery storage capacity of 225MW/1 140MWh. Scatec said the project delivers 150MW of dispatchable power from 5am to 9.30pm year-round to the national grid under a 20-year Power Purchase Agreement with Eskom. The group is also in an advanced stage of the three Grootfontein solar projects won as part of the Department of Mineral Resources' fifth bidding round of its REIPPPP in 2021. The solar power plants will be the first Scatec assets located in the Western Cape province of the country and have a total capacity of 273MW solar power. Once operational the projects will deliver much needed renewable energy under a 20-year Power Purchase Agreement. The three solar plants will lead to a combined abatement of 630 000 tons of CO2 emissions annually. BUSINESS REPORT

As wind energy gains momentum, lack of grid infrastructure remains a bottleneck
As wind energy gains momentum, lack of grid infrastructure remains a bottleneck

IOL News

time02-07-2025

  • IOL News

As wind energy gains momentum, lack of grid infrastructure remains a bottleneck

Wind turbines lined up at Rietkloof Wind Farm. Interest in wind energy has gained significant momentum in South Africa, says the author. Image: Supplied Interest in wind energy has gained significant momentum in South Africa, driven by recent policy reforms and growing private sector demand, opening up new opportunities for investment. Private sector projects like Discovery Green in the Western Cape, Seriti Green in Mpumalanga, and Red Rocket in the Overberg are set to add nearly 700 MW of privately financed, wheeled wind power to South Africa's energy mix, which will significantly bolster the country's renewable energy capacity. However, the lack of grid infrastructure could prove to be a stumbling block in unlocking this potential, as there is a current shortage of transmission capacity to connect these new wind projects to the national grid. Unlocking opportunity Wind power was under-represented in the latest government procurement rounds, as they focused heavily on solar. However, there remains a massive opportunity for wind power to contribute meaningfully to South Africa's energy mix and large-scale, privately financed projects are emerging to take advantage. Among them is the Overberg wind farm, developed by Red Rocket in the Western Cape. With a planned capacity of 380 MW and the first 242 MW phase reaching financial close in early 2025, it will be South Africa's largest privately driven wind project once complete. The project is backed by a 20-year power purchase agreement with Richards Bay Minerals and will deliver power through a wheeling arrangement on Eskom's grid. Also contributing to this shift are the Discovery Green and Seriti Green wind farms. Discovery Green's 150 MW wind project in the Western Cape is designed to supply corporate customers directly via wheeling agreements. Meanwhile, Seriti Green's 155 MW Ummbila Emoyeni wind farm in Mpumalanga will provide around 75% of Seriti Resources' coal operations' energy needs. Together, these three projects will inject 685 MW of new wind capacity into the national grid. Wheeling strategies are key in delivering this wind power to customers, allowing Independent Power Producers (IPPs) to directly deliver energy generated to their customers. However, to fully realise the potential of this private-sector momentum, significant investment in transmission infrastructure will be needed to unlock grid access in renewable-rich regions. The stumbling block to success As wind power and wheeling are gaining traction, they are exposing a critical bottleneck: ageing and limited grid capacity. South Africa currently has a shortfall of around 14 000 km of transmission lines, and just 4 000 km has been shortlisted for upgrades, although no contracts have been issued. This is a key barrier to further adoption, not only of wind power but of any renewable energy solutions. The International Energy Agency's recent report, Building the Future Transmission Grid, highlights that this is not a uniquely South African problem. Demand for new transmission is surging globally, and grid infrastructure is struggling to keep pace with renewable deployment. According to the report, by mid‑2024 there were around 1 650 GW of wind and solar projects around the world stalled waiting for grid connection. These projects face indefinite delays unless grid expansion accelerates, but there are two major challenges: rising costs and long lead times for key equipment. For South Africa, this means that despite a wealth of projects and interest, wheeling and full grid integration are constrained without urgent transmission upgrades, which will take time and require significant investment. Accelerating and modernising South Africa's grid To unlock the full potential of renewable energy projects, fast-tracking grid capacity expansion is critical. For South Africa, this includes streamlining bureaucracy in transmission tenders, enabling projects to move quickly from planning to construction. The IEA report supports this requirement, highlighting that coordinated demand visibility, simplified permitting, and reformed procurement processes are essential to accelerate progress. Alongside expansion, investing in modernisation and smart grid technologies can optimise existing infrastructure. Digital systems such as real-time monitoring, dynamic line rating, and automation help relieve bottlenecks and delay the need for costly large-scale grid buildouts. To further strengthen the grid, South Africa should secure supply chain resilience by pursuing long-term contracts and bulk purchasing of key components like cables and transformers to combat global shortages and rising prices. Additionally, developing a skilled local grid workforce is vital. The IEA projects a global shortfall of 1.5 million grid-sector workers by 2030. South Africa needs to invest in training engineers, line workers, and technicians to manage and maintain its expanding transmission network effectively. Modernisation is the key Wind energy in South Africa is gaining traction not just through government tenders, but increasingly through private wheeling, letting IPPs connect directly to buyers across the country. However, without rapid expansion of transmission lines, smart grid integration, and streamlined policy, both wheeling and the green energy transition will not be able to reach their full potential. A new concept of wireless electricity transmission could also be an alternative. A coordinated approach to the problem is critical. We need to accelerate transmission expansion, harness smart technologies, secure supply chains, and build workforce capacity. South Africa has the natural resources along with corporate appetite for renewable energy and the capability to drive the energy transition forward. What we need is the infrastructure to make this possible. Viren Sookhun, MD at Oxyon People Solutions Image: Supplied