Urban immobility: Why the Mumbai Metro is failing to take off
The 21-year-old graphic designer eagerly hopped on to the swanky coaches of the metro, hoping to travel 15 km in the city's western suburbs in air-conditioned bliss.
But mid-way in the journey, she found that not only did she have to change from one metro line to the other, she had to exit the station and navigate dense traffic to do so.
The two metro lines did not intersect. There was no interchange station.
For 23 minutes of air-conditioned metro travel, Dave had to walk a total of 20 minutes – to get to the metro station and to switch lines. Tired of the exertion, she gave up on metro travel and went back to commuting by bus.
She is not the only one. Data shows Mumbai commuters are staying away from the metro network, belying hopes that it would take the load off local trains and ease traffic on the roads.
Lines 2A and 7 between Andheri and Dahisar, for instance, have only reached 2.05 lakh ridership per day – 25% of the projected ridership, data till mid-June shows.
The latest addition to the network – the Aqualine which connects Aarey Colony in the north to Worli in central Mumbai – has only 45,000 daily passengers, till mid-June, a tenth of estimated daily ridership,
The total daily ridership on all four metro lines is less than seven lakh, against an estimate of 18.84 lakh.
The Mumbai metro network is being built at a staggering cost of more than Rs 90,000 crore, which is escalating with every year of construction delays. Its failure to attract riders, experts say, reflects a wider crisis in India's urban transport landscape – the focus of this three-part series.
Connectivity trouble
Mumbai currently has four metro lines run by three operators. Not only do they lack seamless interconnectivity, the lines don't even share common ticketing.
Every morning that Sahil Gupta, an engineer, takes the metro to work, he goes through three rounds of security checks, ticket scans and baggage scans.
An autorickshaw from home takes him to Malad station in the western suburbs where he boards metro line 2A, alighting at DN Nagar. Here, he exits the station, takes a foot overbridge to line 1. He repeats ticketing and security before travelling to Marol, where he crosses the road, and goes through the same drill again before boarding his third and final metro line 3 to get to the airport.
'The system is complicated,' Gupta said. 'I have to buy three tickets and go through three scans.'
An official from the Mumbai Metropolitan Region Development Authority defended the system, saying it was natural for each metro operator to undertake their own security checks.
In June, the National Common Mobility Card came into use in Maharashtra. The contactless card is meant to streamline travel across all modes of public transport in India. However, in Mumbai, it only works on metros and buses.
A MMRDA official said the monorail has a closed-loop ticketing system, which means it requires dedicated cards and will not accept interoperable cards used on other modes of transport. The common mobility card is not integrated with the suburban railway system.
Last mile chaos
Mitesh Tomani, a 24-year-old college student, said he struggles every day to look for an auto or a bus from Aarey-JVLR metro station to his college, SDA Bocconi Asia Center, in Hiranandani Gardens.
Tomani first takes a bus from his home in Worli to Acharya Atre Chowk metro station, then he hops on to line 3, known as the Aqualine, and travels till the last station in Aarey colony. From there, if he is lucky to find a bus or an auto rickshaw he travels further for about 4 km to his college. The entire journey takes over an hour and costs Rs 250.
'The metro makes the ride comfortable,' he said. 'But little thought has been put towards what passengers can do once they step out of the metro.'
There are four buses from the bus stop near Aarey metro station towards Hiranandani where his college is. Most days, he gets tired of waiting for a bus on the desolate stretch. 'The frequency of buses is poor,' he explained.
He ends up spending Rs 70-Rs 100 on an autorickshaw ride one way. 'Even for that I have to wait,' Tomani said. 'Not many autorickshaws pass through this road. The metro station is new.'
Transport experts say this is a common experience, which they attributed to a lack of planning.
'There are bus stands and dedicated lanes for autorickshaw outside railway stations, but nothing similar can be found outside metro stations,' said AV Shenoy, co-founder of the Mumbai Mobility Forum, a think-tank that focuses on public transport.
He pointed out that Mumbai had different operators for local trains, BEST bus and metros, all of which work in isolation. 'Ideally new bus routes should be started around the new metro stations,' he said.
For instance, for most of its length, metro line 7 runs parallel to the Western Express Highway. When passengers exit the metro stations, they emerge on the highway where moving traffic makes it impossible for auto rickshaws to halt for long. Even bus stops are not located close to the metro stations.
'There is little thought put into how people will get to the metro station or leave it,' said transportation analyst Sudhir Badami.
Back in 2008, the state government had formed the Unified Mumbai Metropolitan Transport Authority to bring all modes of public transport under one umbrella. But Shenoy said the chaos outside metro stations showed that the authority had failed to do its job.
A former official of the Mumbai Metropolitan Region Development Authority, which operates metro lines 2A and 7, claimed that the agency had actually attempted to ensure that it was integrated with other modes of transport.
'For some stations, we tried to create a space for buses to stop and autos to ply,' he said, requesting anonymity since he was no longer authorised to speak to the media. But for the efforts to succeed, he said, 'BEST has to ensure they create [bus] stops near metro stations and auto-unions must create a service of share-autos from there.'
The MMRDA is now working on connecting some of its metro stations to local railway stations.
Metro users, however, point out that the problem isn't limited to the lack of last-mile connectivity. Exiting metro stations itself can be a hazard – there is no safe pedestrian space outside.
A survey by the Walking Project, a citizen initiative in Mumbai, found that at least four metro stations on line 2A had no footpath at the exits.
'Lack of holistic planning forces ridership to the lower side,' said Walking Project's programme manager Vedant Mhatre. 'London has much wider footpath access to stations.'
Steep cost
The Mumbai metro network has been under construction for over a decade.
The first metro line connecting Versova and Ghatkopar in the western suburbs was inaugurated in 2014. The per kilometre cost of building it was Rs 206 crore in 2012, according to data from the Mumbai Metropolitan Region Development Authority.
By the time the MMRDA began building metro line 7 and 2A, the cost had escalated to Rs 359 crore per kilometre.
'At one-tenth the cost, buses would have ferried the same number of people,' said transport expert Badami, who has been advocating a bus rapid transport system as the solution for Mumbai's traffic woes.
Eighty-two percent of Mumbai's population lives within 5 km of their workplace, according to a 2008 survey by the Mumbai Urban Transport Project. 'That leaves 18% who would ride a metro for long-distance travel,' Badami said.
However, he noted that 'with 50% of the population residing in slums, not everyone can afford metro fare'.
It costs Rs 10 to travel 40 km by local trains. On the metro, the cost is Rs 80 for the same distance.
Transport expert Shenoy questioned the utility of the Mumbai metro in its current form. It is too expensive for Mumbai's working class, he said, who continue to take the local trains. And those who can afford the metro are unlikely to use it because of the lack of convenience. 'Why would they walk so much?' he asked.
The Maharashtra government plans to eventually build 14 metro lines over 337 km with 225 stations in the Mumbai metropolitan region.
Many believe this ambition is not matched by action.
'The metro is not being built for how people would like to use it,' said urban activist Zoru Bhathena. 'It is being built for the sake of it.'
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Time of India
2 hours ago
- Time of India
Forest department approves Udaipur dam project after securing land near Sariska
Jaipur: The state Forest Department has granted the long-pending No Objection Certificate (NOC) for the Devas III and IV dam project in Udaipur, nearly two years after withholding it due to the unavailability of suitable compensatory land. The clearance followed the identification of 174.1106 hectares of non-forest land near the Sariska Tiger Reserve in Alwar district, fulfilling the department's requirement that the land be adjacent to a tiger reserve or wildlife sanctuary. The Rs 1,691-crore project, aimed at securing Udaipur's future drinking water supply, is proposed on an equivalent area of forest land in the district. As per forest conservation norms, any diversion of forest land for non-forest use must be offset by providing equal non-forest land for afforestation. However, such land was not available near the project site, leading to prolonged delays. A forest official said, "Initially, the Forest Department had objected even after the Udaipur administration identified alternative land within the district. In a revised demand, the department insisted on land located near a protected area. Following this, the Alwar district administration identified land in the Kalad–Pratapgarh forest block adjoining the Sariska Tiger Reserve. by Taboola by Taboola Sponsored Links Sponsored Links Promoted Links Promoted Links You May Like Learn More - How Watching Videos Can Boost Your Income TheDaddest Undo A total of 340.32 hectares was surveyed, and 174.1106 hectares have been reserved for afforestation. " The process was expedited after the Udaipur administration corresponded with the Alwar Collector, emphasising that the project was a priority for the ruling govt. "After completing the documentation, the revenue proposal has been sent to the state govt for final approval. Once cleared, the land will be transferred to the Forest Department, which will formally issue the NOC. The Water Resources Department had already issued work orders for construction in October 2023. With the NOC expected shortly, physical work on the dam and tunnel is set to begin," the official added.


Indian Express
2 hours ago
- Indian Express
Tension after crowd forcefully opens Dadar Kabutarkhana to feed pigeons
Over a hundred members of the Jain community took to the streets Wednesday morning, forcefully opened the Dadar Kabutarkhana and offered grains to pigeons at a time when the Brihanmumbai Municipal Corporation (BMC)'s closure of such feeding spots has ruffled feathers across quarters in the city. Anticipating the agitation and protest, BMC Tuesday sought police assistance in taking action against those who would be found feeding pigeons at public spaces. The protest comes a day after Maharashtra's Chief Minister Devendra Fadnavis directed BMC to permit the feeding of pigeons in a controlled manner. Over the weekend, BMC shut the 92-year-old feeding spot in Dadar and lodged FIRs, much to the chagrin of animal rights activists and members of the Jain community for whom feeding pigeons holds religious significance. Tensions flared in Dadar where hundreds of Jain community members flocked to the Kabutarkhana. Some of them climbed atop the bamboo structure, and pulled down the tarpaulin sheets over the site, which the BMC had installed over the weekend. Following the partial removal of the cover, the crowd, led by women, climbed inside the feeding ground and offered grains to the pigeons even as the police attempted to control the protesters. Tucked in the bustling neighbourhood near Dadar railway station, Dadar Kabutarkhana — established in 1933 — is maintained by the Dadar Kabutarkhana Trust. According to members of the trust, over 980 pigeons had died in the vicinity over the past 3 days. 'It was to offer prayers, that a peace gathering had initially been planned on Wednesday. However, after our meeting with the Chief Minister where he spoke in favour of us, we had called off the gathering. Even as we had conveyed a message of the cancellation throughout the night, some members perhaps did not receive the message and gathered at the site on Wednesday morning,' said Sandeep Doshi from the Dadar Kabutarkhana Trust. He maintained that the extreme reactions were triggered by members outside of the Jain community, who had also gathered on Wednesday. 'Some other members from other communities also gathered and the extreme action was taken by them. While some things happened in the heat of the moment, we did not break anything, did not fight with the police nor the administration,' added Doshi. Even as the Mumbai Police had on Wednesday morning said that it was in the process of filing an FIR, officials said that no FIR was filed until Wednesday. 'We can file an FIR only on the basis of complaints filed by BMC, as the High Court had directed the BMC to take action on the matter,' an official from Mumbai Police told The Indian Express. Meanwhile, the BMC had not filed any complaints until Wednesday evening. Dadar Kabutarkhana is among the 44 feeding spots the civic body has initiated action against for pigeon feeding. Between July 13 and August 3, at least 141 people have been fined for feeding pigeons with the civic body collecting over Rs. 68,700 in penalties. Mumbai is home to at least 51 such Kabutarkhanas with the Maharashtra Government on July 3 calling for the closure of these feeding sites owing to concerns of public health hazards. However, BMC's stance on the closure of Kabutar Khanas gained further momentum after the Bombay High Court order issued on July 30, directing the civic body to lodge FIRs against those who 'illegally' and in a 'defiant' manner feed pigeons at Dadar West, among other feeding areas in Mumbai, despite the policy prohibiting the feeding. Amid the civic body shutting pigeon feeding across the city, members of the Jain community Monday staged a 'Shantidoot Yatra' from Colaba to the Gateway of India, appealing for the reversal of the decision. Meanwhile, as the protest subdued by Wednesday afternoon, the area continued to wear a tense look with the Mumbai police deploying its personnel while also later pressing in barricades. With the tarpaulin sheets and plastic cover partially removed, several pigeons returned into the central feeding spot while many continued to flutter around the grade-II heritage structure. As members of the Dadar Kabutarkhana trust maintained that the forceful opening was triggered by members outside of the community, the incident triggered reactions across the political spectrum. In the aftermath of the incident, Maharashtra cabinet minister Mangal Prabhat Lodha backed the Dadar Kabutarkhana Trust. He said, 'The Kabutarkhana trust had no role to play in this incident with the members maintaining that the incident was triggered by members of another community. Some people came here and the Jain community and monks had no role to play in the matter.' Earlier on August 4, Lodha had written to the civic chief, Bhushan Gagrani, calling for alternate feeding spots in the city. Meanwhile, Manisha Kayande, Shiv Sena UBT leader who had raised the issue of illegal Kabutarkhanas in council in July, said, 'Members of the Jain community tore the sheets which had been laid over the feeding site. This is a complete contempt of the High Court. This is no religious subject but in fact, a subject of medical science and concerns birds and animals. However, now, voices of people who have suffered ailments due to the pigeons have been completely stifled. How is this appropriate and who will help them?' 'There has been news today that some animal lovers and particularly members of the Jain community have done destruction at the Dadar Kabutarkhana. This is not true. As per the decision taken on Tuesday, people had only come there to feed birds by opening the tarpaulin,' Sandeep Bhandari, president of BJP's Jain cell said on Wednesday. Earlier on Tuesday, CM Fadnavis had directed BMC to facilitate feeding of pigeons in public spaces in a controlled manner to ensure that the birds do not starve. Even as the civic body maintained that the sites would remain closed until the Bombay High Court hearing on August 7, officials said BMC was exploring the options of feeding for staggered durations, following Fadnavis's directives.


Time of India
3 hours ago
- Time of India
Nashik civic body to fell 800 trees to make space for 2 new sewage treatment plants
Nashik: The civic body is constructing two new sewage treatment plants at Panchak and Chehedi as part of the Rs 1,475 crore Godavari river purification project. The initiative, aimed to be completed before the upcoming Simhastha Kumbh Mela, scheduled between 2026 and 2028, necessitates the chopping of 800 trees. Tired of too many ads? go ad free now According to Nashik Municipal Corporation (NMC) officials, the existing trees are hindering the construction of the new STPs at these locations. The tree authority of the NMC has granted permission to fell the trees on the condition that new trees are planted equivalent to the total age of the removed trees. Consequently, a total of 8,210 trees will be planted in Nashik to replace the 800 trees to be cut down at Panchak and Chehedi. "NMC commissioner Manisha Khatri has issued two separate orders for the plantation of 8,210 trees in the city in lieu of chopping 800 trees at Chehedi and Panchak for the construction of the two STPs," NMC officials said. The new trees will be planted and maintained for seven years by a private agency, with planting scheduled before the removal of the existing trees. Additionally, the agency is required to submit survival reports of the planted trees to the garden department every six months, said the civic officials. The STP at Chehedi will have a capacity of 64 million litres per day (MLD), while the Panchak STP will have a capacity of 75 MLD. These two new STPs are part of the broader project to construct four new STPs in the city. A private agency has been finalised, and a work order has been issued. Currently, Nashik's 11 STPs collectively have a treatment capacity of 392 MLD.