Consumer court orders BDA to refund Rs 8 lakh for delay in handing over flat

Consumer court orders BDA to refund Rs 8 lakh for delay in handing over flat

Time of India5 hours ago

Bengaluru: The IV Addl District Consumer Disputes Redressal Commission has ordered Bangalore Development Authority (BDA) to refund Rs 8.03 lakh, with 18% interest, to a Marathahalli resident here, who waited for nine years for possession of a flat that BDA had promised to deliver in a year's time.
On March 21, 2025, the Commission ordered BDA to refund Rs 8.03 lakh, along with an interest of 18% from the date the first payment was made, Rs 1 lakh for service deficiency, Rs 25,000 for mental agony, and another Rs 10,000 in litigation costs.
The complainant, Suryaprakash H R, 70, had booked a 1BHK flat at Gunjur village under the housing scheme for Economically Weaker Sections (EWS) on March 7, 2014, making an initial payment of Rs 1.12 lakh.
According to Suryaprakash, BDA had allotted him a 1BHK flat in Gunjur through draw of lots, and On December 3, 2014, he was told to pay the remaining amount of Rs 7.87 lakh within six months. To fulfil this, Suryaprakash took out a housing loan of Rs 8 lakh, which was released to BDA in four instalments.
However, thereafter, BDA neither issued a firm date for registration, nor did it respond to the complainant's repeated inquiries.
by Taboola
by Taboola
Sponsored Links
Sponsored Links
Promoted Links
Promoted Links
You May Like
임플란트, 지금 시작하세요 [자세히 보기]
임플란트
더 알아보기
Undo
Worse still, the allotment-related file could not be traced at the BDA office by its officials.
Construction halted midway
When Suryaprakash visited the project site in 2016, he found only the first and second floors had been built, with no further progress.
On December 22, 2016, he wrote to the chief minister, who in turn directed the BDA commissioner to act. A letter from BDA's chief engineer confirmed that construction had been entrusted to Deepak Cable India Ltd.,
but due to non-completion, the contract was cancelled and re-tendered.
As the delays dragged on, Suryaprakash and other EWS allottees staged a hunger strike in front of the Gunjur BDA project.
On January 5, 2019, they submitted a joint representation to BDA and again approached the CM on June 15, 2019. The CMO yet again forwarded the complaint to the BDA commissioner, but work remained incomplete.
Frustrated with his runs from pillar to post, on Jan 28, 2023, Suryaprakash issued a legal notice to BDA, followed by a representation to the deputy CM on October 26, 2023.
The BDA deputy secretary replied on April 3, 2024, acknowledging receipt of Rs 4.73 lakh, but alleging that Rs 3.13 lakh was due.
Suryaprakash countered the claim, saying he had already paid 95% of the sale amount.
On June 13, 2024, he finally filed a consumer complaint, seeking a full refund.
Unjustified act
The BDA's legal counsel contested the claim, saying Rs 1.16 lakh was still due, and that possession was withheld because of that.
The Consumer Disputes Redressal Commission observed that the elderly complainant was a valid allottee who had paid 95% of the flat cost by August 2015. Rejecting BDA's claim that possession was withheld due to the pending amount, the consumer court observed that it did not justify the delay, and ruled that BDA had failed to provide proper civic amenities, parking facility, and sanitary connections at the Gunjur project, making the residential units uninhabitable.

Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

A Lithium startup is building a US battery plant that will skirt Trump's tariffs
A Lithium startup is building a US battery plant that will skirt Trump's tariffs

Time of India

time14 minutes ago

  • Time of India

A Lithium startup is building a US battery plant that will skirt Trump's tariffs

US startup Pure Lithium Corp. is working on a testing facility to build a new type of lithium battery that's completely manufactured domestically. The company has developed a lithium metal battery that Chief Executive Officer Emilie Bodoin says will displace lithium-ion batteries. Pure Lithium has spent the last four years doing research and development on the technology, which could be used in electric vehicles, utility-scale energy storage and other applications. 'We're working as hard as we can to build a prototype pilot facility,' Bodoin said Tuesday in a Bloomberg Television interview. She added that the company is expanding its lithium production process and is integrating that into a manufacturing plant, 'and as soon as we get it up and running we're going to start getting these batteries out into the hands of US customers that need it.' by Taboola by Taboola Sponsored Links Sponsored Links Promoted Links Promoted Links You May Like Florida: These Companies Are Overcharging You for Auto Insurance OTTO Insurance Read More Undo The Boston-based company's move to build a pilot plant comes as President Donald Trump 's administration sets the stage for tariffs on imports of key battery components from China. Pure Lithium says it extracts lithium from brine to manufacture a battery free of graphite, nickel, cobalt and manganese, allowing it to be produced without any inputs from China. The company received a letter of interest from the US Export-Import Bank in April for financing of as much as $300 million. Live Events

BharatNet Phase-III: Polycab wins ₹6,447.54-crore deal for Karnataka, Goa and Puducherry circle
BharatNet Phase-III: Polycab wins ₹6,447.54-crore deal for Karnataka, Goa and Puducherry circle

Time of India

time15 minutes ago

  • Time of India

BharatNet Phase-III: Polycab wins ₹6,447.54-crore deal for Karnataka, Goa and Puducherry circle

NEW DELHI: State-controlled Bharat Sanchar Nigam Limited ( BSNL ) has awarded a ₹6,447.54-crore deal to homegrown electrical wires and optical cable manufacturer Polycab to construct and maintain a middle-mile network under the BharatNet Phase-III programme in Karnataka, Goa and Puducherry telecom circle. '...Polycab India Limited has executed an agreement with BSNL as the Project Implementation Agency for Design, Supply, Construction, installation, upgradation, operation and maintenance of middle mile network of Bharat Net in Karnataka, Goa and Puducherry Telecom Circle against Package No. 4 amounting ₹6,447.54 crores (inclusive of GST),' Polycab said in a regulatory filing in aftermarket hours Tuesday. The deal value comprises a capital expenditure (capex) of ₹3,741.92-crore and operating expenditure (opex) of ₹2,245.15-crore, and an opex of ₹460.47-crore for the existing network, as per the filing. BharatNet , a rural telecom connectivity project, is aimed at providing non-discriminatory access to broadband connectivity to all telecom operators (telcos). BSNL has previously awarded contracts to Polycab, ITI Limited, Sterlite Technologies (STL), Telecommunications Consultants of India Limited (TCIL), and Pratap Technocrats, among others, under multiple packages of the BharatNet Phase-III programme. ETTelecom reported on August 7, 2024, that the Telecommunications Consultants of India Limited (TCIL), ITI Limited, indigenous optical fiber cable (OFC) makers HFCL, STL, Polycab, and Pratap Technocrats, are among the bidders for the third phase of the Centre's ambitious BharatNet programme. Indigenous OFC makers Polycab, STL and HFCL presented solo bids while as many as 18 bidders, including G R Infraprojects, Vindhya Telelinks, Pace Digitek Infra Private Limited, Rail Vikas Nigam Limited (RVNL), Bharat Electronics Limited, Megha Engineering, and others, took the consortium route. A total of 21 bidders put in their bids under the BharatNet 3 program for Madhya Pradesh, Rajasthan, Uttar Pradesh (East), Uttar Pradesh (West), Karnataka, Uttarakhand, Bihar, Himachal Pradesh, West Bengal, Jammu & Kashmir, North East Region – I and North East Region – II, and others. In early 2024, the Centre rolled out the BharatNet III programme with an outlay of Rs 65,000-crore. The last date to submit bids was August 6, 2024. The tender is part of the Prime Minister Narendra Modi-led government's Rs 1.39 lakh crore BharatNet programme which aims to provide last-mile broadband connectivity, and upgrade the existing 164,000 gram panchayats, as well as, connect 47,000 gram panchayats under the new model.

'RIP Captain. You will be missed' Air India bids final salute to Captain Sumeet Sabharwal
'RIP Captain. You will be missed' Air India bids final salute to Captain Sumeet Sabharwal

Time of India

time15 minutes ago

  • Time of India

'RIP Captain. You will be missed' Air India bids final salute to Captain Sumeet Sabharwal

Following Air India's plane crash in Ahmedabad last week, Air India on Tuesday bid its final salute to 56-year-old veteran pilot Captain Sumeet Sabharwal . Company's Head of Flight Operations, along with Tata Group 's HR Head and Communications Head joined Captain Sabharwal's family to offer condolences. "With profound grief and heavy hearts, we bid farewell to Captain Sabharwal - an exceptional aviator, a dedicated professional, and a beloved member of the Air India family," the airline said. The last rites of Captain Sabharwal were performed in Mumbai on Tuesday hours after Sabharwal's mortal remains were brought to Mumbai from Ahmedabad. Play Video Pause Skip Backward Skip Forward Unmute Current Time 0:00 / Duration 0:00 Loaded : 0% 0:00 Stream Type LIVE Seek to live, currently behind live LIVE Remaining Time - 0:00 1x Playback Rate Chapters Chapters Descriptions descriptions off , selected Captions captions settings , opens captions settings dialog captions off , selected Audio Track default , selected Picture-in-Picture Fullscreen This is a modal window. Beginning of dialog window. Escape will cancel and close the window. Text Color White Black Red Green Blue Yellow Magenta Cyan Opacity Opaque Semi-Transparent Text Background Color Black White Red Green Blue Yellow Magenta Cyan Opacity Opaque Semi-Transparent Transparent Caption Area Background Color Black White Red Green Blue Yellow Magenta Cyan Opacity Transparent Semi-Transparent Opaque Font Size 50% 75% 100% 125% 150% 175% 200% 300% 400% Text Edge Style None Raised Depressed Uniform Drop shadow Font Family Proportional Sans-Serif Monospace Sans-Serif Proportional Serif Monospace Serif Casual Script Small Caps Reset restore all settings to the default values Done Close Modal Dialog End of dialog window. by Taboola by Taboola Sponsored Links Sponsored Links Promoted Links Promoted Links You May Like O novo dispositivo que ajuda a reduzir o formigamento e os choques noturnos nos pés. aartedoherbalismo Undo Air India bid the final farewell to Captain Sabharwal saying: — airindia (@airindia) Live Events Businessman Niranjan Hiranandani and local MLA Dilip Lande also visited Sabharwal's residence to pay respects to him. With an experience of more than 8,200 flying hours, Captain Sabharwal was was commanding the ill-fated Air India flight AI-171 carrying 242 passangers and crew members that crashed in Ahmedabad on June 12.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into the world of global news and events? Download our app today from your preferred app store and start exploring.
app-storeplay-store