Explainer: How City Rail Link will redraw Auckland's train lines

Explainer: How City Rail Link will redraw Auckland's train lines

1News2 days ago
A new map shows how Auckland's train lines will be redrawn when the City Rail Link opens in 2026, but an exact opening date for the project remains elusive.
Questions remain about the $5.5 billion project after Auckland Transport (AT) revealed a finalised rapid rail and bus network diagram yesterday, showing how train lines would change with the new 3.5km CRL tunnel and two underground stations.
Speaking at a media conference, AT chief executive Dean Kimpton wouldn't give an opening date more specific than sometime in 2026, but which was a "commitment".
The three new rail lines will carry geographic names and two-letter codes. (Source: 1News/Justin Hu)
"A dollar for every time that question is asked," he said, adding, "we don't want to promise a date until we're ready, but you can be sure, when we know, you will know."
ADVERTISEMENT
Construction work was still finishing on the new CRL stations along with KiwiRail track rebuild work across rail lines, Kimpton said, while 165 new staff were being trained up.
Next year's expected completion will also come after five years of disruption to Auckland trains due to planned efforts to renew rail foundations and other major track issues.
The first test train travels through Auckland's City Rail Link at Karanga-a-Hape station. (Source: City Rail Link)
When will we know the opening date?
So, when will Aucklanders know a date for the opening of the city's biggest infrastructure project? "We won't be in a position to confirm anything until next year," Kimpton said.
While officials were previously known to have been targeting early 2026, bosses have been reluctant to give a specific date in public, sticking to a broad timeframe instead.
Dean Kimpton speaks to media in August 2025. (Source: 1News/Justin Hu)
ADVERTISEMENT
An AT retail leasing document from earlier this year indicated an opening between February and April 2026, but comments from officials at a council meeting two months ago suggested the new system would probably be opening closer to autumn.
Covid-era lockdown delays were blamed after a publicised opening was delayed two years from 2024, with the budget also ballooning to over $5 billion.
KiwiRail programme director Bobby Fischer said 1600 test runs had been made through the tunnels already. "There's a significant amount of testing that goes on, before it will be open to the public, just to make sure it is safe and ready to go."
KiwiRail programme director Bobby Fischer (Source: 1News)
Where will the new lines go via the CRL?
Existing train lines — Eastern, Western, Southern and Onehunga — will give way to new cross-city routes that route through the underground CRL tunnels and no longer terminate at the downtown Britomart station, which has been re-named to Waitematā.
A new station in the midtown area, Te Waihorotiu, will be close to the Sky Tower, Civic Centre and the universities. The other new underground station, Karanga-a-Hape, will be located just off Karangahape Road, towards the south of the city centre.
ADVERTISEMENT
A render of a train platform at the future Karanga-a-Hape station. (Source: City Rail Link)
A fully rebuilt Mt Eden station, renamed Maungwhau, in Eden Terrace on the city fringe, is also opening along with the other CRL stations.
'East-West line'
The biggest line change will merge existing Eastern and Western lines into a single "East-West line", allowing direct travel from Swanson to Manukau without changing trains.
The route will sweep from West Auckland stations through the central isthmus, pass through the CRL, then continue via Ōrākei to Ōtāhuhu, before terminating in Manukau.
"You could be shopping at Lynn Mall, and if they don't have what you want, jump on an East-West train straight to Sylvia Park to see if they do," Kimpton said.
Train at Ōrākei station, Auckland in 2017 (file image) (Source: istock.com)
ADVERTISEMENT
Trains from the west will no longer reverse out of Newmarket station to reach the city, saving commuters nearly 10 minutes. But the more direct CRL route into the city means they'll now skip Grafton — near Auckland Hospital — and Newmarket itself. This means some passengers will need to change trains when they don't have to today.
'South-City line'
Those currently using the Southern line will see changes too, with the new "South-City line" looping around the underground stations before returning south to terminate at Ōtāhuhu. Passengers will likely want to check the destination boards, as some trains will go clockwise and others go counter-clockwise around city stations.
Interior of an Auckland passenger train (file image). (Source: Unsplash/Nguyen)
Three new rural stations south of Papakura also remain under construction.
The third line, the "Onehunga-West line", will connect Henderson and Onehunga without going through the city centre. It will run less frequently than the other two main lines, and initially will only operate between Henderson and Maungawhau outside of rush hour.
How often will the trains run?
ADVERTISEMENT
During rush hour, most lines will see trains at least every eight minutes or better — up from ten minutes today — with shorter intervals where multiple lines overlap, such as inside the CRL tunnels, where gaps between trains are as short as every four minutes.
The new map. (Source: Supplied)
Exceptions include the half-hourly Onehunga line and some "counterpeak" trains on the western section of the new East-West line, which will become slightly less frequent than they are now, affecting people travelling in the opposite direction to peak commuter flows.
For example, heading out of the CBD towards the western suburbs in the morning rush hour, or vice versa, heading from the west towards the city in the afternoon peak.
Outside of rush hour, trains will run every 15 minutes during the day and at weekends, compared to the existing 20-minute intervals. After 8pm, rail lines will remain every 30 minutes, with officials pointing to a need for continued rail maintenance windows at night.
A finalised timetable was expected in the next few months, officials said.
What are the new lines called?
ADVERTISEMENT
The three new rail lines will carry geographic names and two-letter codes.
AT said the letter codes — "E-W' for East-West, "O-W" for Onehunga-West, and "S-C" for South-City — will be prominently displayed on maps and station signage.
A floor print-out of the new Auckland network map. (Source: 1News/Justin Hu)
Several different ideas were considered in the process for naming the new train lines, including the geographic names, a simple numbering system — similar to the ones used in Sydney or New York — and two which would have incorporated te reo.
Under one suggestion, lines would have been named after native New Zealand birds, while another would have used bilingual colour coding, with English shorthand codes followed by te reo names, such as "Kākāriki/Green Line" or "Whero/Red Line".
An internal briefing showing other naming conventions considered for Auckland's train lines. (Source: The Research Agency/Auckland Transport)
Kimpton said the final line names were chosen after research.
'A lot of thought has been put into the names, and I've sat in on some of the customer workshops where we've tested naming,' he said.
"There were quite a few options put up, but we felt that East-West, South-City, Onehunga-West were naming conventions, along with the colours that best communicated intuitively what line people were on, or what line they needed to catch."
Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

'A bit like Star Trek': Politicians take City Rail Link test run
'A bit like Star Trek': Politicians take City Rail Link test run

1News

time3 hours ago

  • 1News

'A bit like Star Trek': Politicians take City Rail Link test run

There's been another milestone in Auckland's City Rail Link with people from outside the project allowed on an underground test run for the first time. Prime Minister Christopher Luxon was aboard along with senior ministers, city leaders and other officials. The train journey started at the revamped Maungawhau Station and headed into a tunnel to arrive at Waitematā or Britomart Station. "We were just saying it's a bit like Star Trek, warp speed up there the way the tunnel is lit," Luxon said after standing with the driver. City Rail Link's first test train. (Source: ADVERTISEMENT Auckland Mayor Wayne Brown stayed seated and chatting with the Finance Minister during the trip and maybe didn't see the warp speed lighting. "We don't really see exactly what we've got here just yet, but it's good, this is a good step in the direction," he told RNZ. In a speech before getting on the train, Brown said getting to today had not been cheap or easy, with Auckland enduring a decade of construction that has been tough. He warned future projects needed to be done better and faster and could not be done on what costs were now. There have been more than 1600 test train runs in the new City Rail Link tunnels so far. Vince Ahkuoi was the driver. "I haven't driven a train that is that important, I don't think," he said. ADVERTISEMENT Today showed just how far the City Rail Link had come, another driver Grant Dowie said. He said test trains had run more than 5000km since February and 50 drivers had been trained. "And if you think that the tunnel is only 3.5km long, to get over 5000km of test running we've been running backwards and forwards multiple times," he told RNZ. He said the VIP test train on Friday showed that testing had done its job, but there was still much more to do. "We started at walking pace, and then we went to 3km [an hour] and then we went to 10km and then we went to 25 and then 40," he said. Prime Minister Christopher Luxon at the City Rail Link's first test train. (Source: Trains now run at 70km/h and a key test was making sure the trains actually fit. ADVERTISEMENT "I know it's a silly thing but in other parts of the world there have been situations where they've built a tunnel and then the trains didn't fit," Dowie said. "I know people are thinking 'well why aren't we opening the tunnel' but it's a journey that we have to go through to make sure it's safe before we open." City Rail Link officials are hailing Friday's VIP test run as a milestone but say there is still a long way to go before the public can have its turn. CRL chief executive Patrick Brockie said testing and commissioning was the most complex part of the $5.5 billion project. "There is still a lot of work to do before we know when exactly passengers will ride," he said. Several politicians attended City Rail Link's first test train. (Source: Another on the train, Finance Minister Nicola Willis was happy with what she saw. "The feeling I have is it looks like when you're overseas and you go in a proper underground subway and that's an experience many New Zealanders have had and now they can have it here in Auckland," she said.

Ministers And Mayor Ride CRL Train Under Auckland
Ministers And Mayor Ride CRL Train Under Auckland

Scoop

time9 hours ago

  • Scoop

Ministers And Mayor Ride CRL Train Under Auckland

Press Release – City Rail Link The train travelled beneath the city centre through the twin 3.45 kilometre-long tunnels, starting at the new Maungawhau Station and passing through Karanga-a-Hape and Te Waihorotiu underground Stations and Waitemat Station (Britomart) before … Auckland's City Rail Link (CRL) celebrated an exciting milestone today, welcoming Prime Minister Christopher Luxon, Auckland Mayor Wayne Brown, Government Ministers, civic leaders and project partners as passengers on the transformational railway under the central city. 'The Government and Auckland Council are joint funders of the $5.5 billion project, and we're delighted to have been able to show off the progress we are making and offer a preview of the benefits thousands of Aucklanders will enjoy when CRL opens next year,' says City Rail Link Ltd's Chief Executive, Patrick Brockie. The train travelled beneath the city centre through the twin 3.45 kilometre-long tunnels, starting at the new Maungawhau Station and passing through Karanga-a-Hape and Te Waihorotiu underground Stations and Waitematā Station (Britomart) before returning to Maungawhau. Mr Brockie says with heavy construction complete, work is focused on commissioning and testing all the tunnel and station systems necessary to operate the CRL safely. 'While the finish line is getting closer, there is still a lot of work to be done before the CRL can open to passengers in 2026,' he says. The trip was organised under strict safety protocols as part of the CRL's rigorous train testing phase. Since the first test train ran in February this year, more than 1,600 individual test train journeys have already taken place inside the tunnels and Mr Brockie says there is a lot more to do to ensure the CRL and future train services are safe and reliable. 'We know from lessons learned overseas, this is our most challenging and complex phase and getting this right for Aucklanders is our utmost priority.' All project partners are working together to complete and open the CRL as quickly as possible to deliver the largest ever change to Auckland's public transport network. 'We can't wait to show more people just how transformational City Rail Link will be for Auckland's wider rail network. It allows for a rethink of our train lines giving customers more choice in how they travel and ways get to where they're going faster,' says Auckland Transport Chief Executive Dean Kimpton. 'There's still a long 'to-do list' before we can open in 2026 and together with our partners, we are working hard to be ready for day one. We're hiring front line staff, procuring new trains, updating bus routes, improving streets, paths and bus stops around our new stations and removing level crossings from our rail network,' says Dean Kimpton. KiwiRail Chief Executive Peter Reidy says KiwiRail continues to deliver significant upgrades to the metro network to support the increased services City Rail Link will bring. 'In Auckland we are carrying out work which would normally take a decade but is being delivered in three to four years. 'While working closely with our partners to ensure rigorous testing and commissioning of the City Rail Link, KiwiRail is also modernising our older rail assets so they can support significantly more trains and passengers. 'We have delivered large new infrastructure projects to support this – Pukekohe to Papakura electrification, Third Main Line and Wiri to Quay Park, Western Power Feed – and continue at pace with the final stages of our Rail Network Rebuild and constructing three new stations in southern Auckland.' CRL is New Zealand's first underground railway.

Prime Minister and VIPs take historic trip on Auckland's $5.5 billion City Rail Link
Prime Minister and VIPs take historic trip on Auckland's $5.5 billion City Rail Link

NZ Herald

time11 hours ago

  • NZ Herald

Prime Minister and VIPs take historic trip on Auckland's $5.5 billion City Rail Link

Luxon said the project was 'a major, major feat' that would spur another $12b of investment in other economic activity in the city. On the return trip from Waitematā, he described the trip as a bit like Star Trek, the way the tunnels were lit, saying he had spent a lot of time on subway trains travelling to work while living in New York and London. Train driver Vince Ah Kuoi said it was cool to be in the driver's seat for the first passenger train. Photo / Bernard Orsman 'A lot less smelly armpits here than what I observed in Tokyo and London, in particular,' he said. Asked about his first impression, Brown said, 'It's a ride in a train. It was normal and natural, which is what we want. We don't want excitement. We just want to know if this goes quickly? We have proved it is very quick to get from here to there. That is what it is supposed to do, and that is what it is doing.' Finance Minister Nicola Willis was along for the ride. Photo / Michael Craig In a speech before the train ride, Brown said the CRL was a great milestone for Auckland, long overdue and reaching this point had not been easy or cheap. 'Auckland has endured 10 years of disruptive been tough on the city and local businesses who have also suffered big shocks from Covid and economic downturns.' Vince Ah Kuoi, one of two train drivers on the trip, said it was cool being asked to drive the first passenger train. Ah Kuoi - who has been driving trains in Auckland for 18 years - said the CRL was the biggest, grandest, newest piece of rail in that time. Prime Minister Christopher Luxon (left), NZ First leader Winston Peters (centre) and Auckland Mayor Wayne Brown exchange greeting before an historic passenger ride this morning on the City Rail Link. Photo / Michael Craig Pat Brockie, chief executive of City Rail Link Ltd, said that with the heavy construction work finished, work is focused on commissioning and testing all the tunnel and station systems to operate the CRL safely. While Brockie said the finish line is getting closer and there was still a lot of work to be done before the CRL can open to passengers, he would not give any indication of when the CRL will open next year. The City Rail Link was first planned in 2008, but construction did not begin until 2016 under a 50/50 agreement between Auckland Council and the Government. At the time of spades in the ground, the cost was estimated at between $2.8b and $3.4b. In 2019, the cost ballooned to $4.4b, and $5.5b in 2023. When it opens next year, trains will run every four or five minutes at peak times through the central city, with a peak capacity of 19,000 passengers per hour – about a 50% increase from the current 12,000 passengers per hour. Sign up to The Daily H, a free newsletter curated by our editors and delivered straight to your inbox every weekday.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store