Study: Extended Interconnection Queue Times Plague Wind, Solar
In a report likely to be used by interests on all sides of the U.S. power grid picture, big energy data and analytics firm Enverus says developers of wind, solar, and stationary battery projects can expect queue times of 4 to 9 years before they can be interconnected into the various regional power grids. The waiting period for interconnection depends on an array of policy and economic variables, but Enverus finds that developers can gauge expectations based in large part on their project's geographic location.
Ryan Luther, research director at Enverus Intelligence Research (EIR), said in the report's Executive Summary, 'The surge in investment and development has overwhelmed interconnection queues, with a record number of projects seeking grid connections. This has exceeded grid operators' processing capacity, causing significant delays and project suspensions.'
Enverus identifies regional power grids in New England - operated by independent system operator ISO-NE - and the Texas grid operated by ERCOT.
Enverus Chart depicting average time in interconnection queues by regional U.S. grid for 2024. Enverus
By contrast, the longest queue times were identified in the CAISO power grid in California and NYISO grid which serves New York. Neither of those latter findings should come as any real surprise given the heavy-handed regulatory environments in those two states. The significantly shorter time on the ERCOT grid may come as a surprise to many given that so much criticism has been leveled at the Texas grid manager since February 2021, when Winter Storm Uri caused massive, days-long blackouts resulting in the deaths of more than 300 Texans.
EIR compiled its findings by analyzing timelines for projects which became operational during the 2022-2024 period, using its proprietary advanced analytics platform, PRISM. IRA Incentives Have Lengthened Queue Delays
In its release, EIR notes that generous tax credits contained in the 2022 Inflation Reduction Act, along with Biden-era EPA's enhanced requirements designed to shut down coal-fired power plants have combined to boost demand for wind, solar, and battery projects across the country. But that reality has had an unintended consequence.
'The surge in investment and development has overwhelmed interconnection queues, with a record number of projects seeking grid connections,' the company says in a release, adding, "This has exceeded grid operators' processing capacity, causing significant delays and project suspensions. Understanding project suspensions and success rates is critical, as these factors vary by independent system operators (ISO), technology type and project stage.'
EIR emphasizes its analysts' finding that about 90% of these proposed projects never progress beyond the interconnection queue, noting that, 'Based on our gradient-boosting machine learning model, we predict that only ~10% of projects will successfully come online in the next three years.' Obviously, these lengthy delays and bottlenecks in the interconnection process raise the coast of capital and result in a high percentage of proposed projects being cancelled.
Citing interconnection suspensions late in the development cycle as a major impediment to ultimate project success rates, as depicted in the chart below, EIR says, 'NYISO, SPP, PJM and ISONE have more suspensions later in the project lifecycle, with interconnection agreement suspension rates ranging from 46% to 79%, compared to around 20% in ERCOT, CAISO and MISO. Consequently, projects in these markets show minimal improvement in completion probability until reaching construction.'
Enverus chart depicting Average Time in Queue for 2022-24 Wind, Solar, and Battery Projects by ISO ... More Region. Enverus
'Congestion, competition, aging infrastructure and interconnection bottlenecks are the biggest obstacles in the way of reaching our goal of siting projects, maximizing the production of renewable energy generators and delivering power where it's needed the most,' says Silvia Alborghetti, director of Business Development at zhero. 'But the information we need for project siting requires lots of resources and time to gather.' The Bottom Line on Interconnection Queue Times
These findings by Enverus serve to emphasize both some unintended consequences created by the IRA tax incentives and subsidy programs, as well as the fact that the need to streamline permitting processes applies to all sources of energy. It also highlights the complexity of the interplay between federal, regional, and state policies.
The EIR study also emphasizes the enduring truth that time really is money, and the fact that taxpayers are forced to foot so much of the money being allocated to projects that never reach fruition due to these extended interconnection queue times becomes especially galling to many Americans. This really is no way to run a railroad, or more to the point, a power grid.

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles

Wall Street Journal
25 minutes ago
- Wall Street Journal
U.S. Stocks Fall as Trump Renews Trade Tensions - What's News
P.M. Edition for July 7. President Trump extended the deadline on so-called reciprocal tariffs to Aug. 1 while announcing 25% tariffs on goods from Japan and South Korea. Several more nations received similar notifications. Plus, heavy rain continues in Texas, where the death toll from the flash floods has risen to 90. And President Trump is meeting Israeli Prime Minister Benjamin Netanyahu at the White House. WSJ national security correspondent Michael Gordon discusses how a changed Middle East could be ripe for Trump's dealmaking diplomacy. Alex Ossola hosts. Sign up for the WSJ's free What's News newsletter.
Yahoo
30 minutes ago
- Yahoo
GameSquare Holdings, Inc. Announces Proposed Public Offering of Common Stock
FRISCO, TX / / July 7, 2025 / GameSquare Holdings, Inc. (Nasdaq:GAME) (the "Company" or "GameSquare") a next-generation media company with roots in gaming and creator entertainment, today announced that it is commencing an underwritten public offering of shares of its common stock (or common stock equivalents). The offering is subject to market conditions, and there can be no assurance as to whether or when the offering may be completed, or as to the actual size or terms of the offering. Lucid Capital Markets is acting as the sole book-running manager for the offering. The offering is being made pursuant to a shelf registration statement filed with the Securities and Exchange Commission ("SEC") on March 4, 2025, and declared effective by the SEC on June 4, 2025. A preliminary prospectus supplement and accompanying prospectus relating to the offering will be filed with the SEC and will be available on the SEC's website at Copies of the preliminary prospectus supplement and accompanying prospectus relating to the offering, when available, may also be obtained by contacting Lucid Capital Markets, LLC, 570 Lexington Avenue, 40th Floor, New York, NY 10022. This press release shall not constitute an offer to sell or the solicitation of an offer to buy any securities nor will there be any sale of these securities in any state or other jurisdiction in which such offer, solicitation or sale would be unlawful prior to registration or qualification under the securities laws of any such state or other jurisdiction. About GameSquare Holdings, Inc. GameSquare's mission is to revolutionize the way brands and game publishers connect with hard-to-reach Gen Z, Gen Alpha, and Millennial audiences. Our next generation media, entertainment, and technology capabilities drive compelling outcomes for creators and maximize our brand partners' return on investment. Through our purpose-built platform, we provide award winning marketing and creative services, offer leading data and analytics solutions, and world-class production through our GameSquare Experiences teams. With one of the largest gaming media networks in North America, as verified by Comscore, we are reshaping the landscape of digital media and immersive entertainment. Forward-Looking Statements: This news release contains "forward-looking information" and "forward-looking statements" (collectively, "forward-looking statements") within the meaning of the applicable securities legislation. All statements, other than statements of historical fact, are forward-looking statements and are based on expectations, estimates and projections as at the date of this news release. Any statement that involves discussions with respect to predictions, expectations, beliefs, plans, projections, objectives, assumptions, future events or performance (often but not always using phrases such as "expects", or "does not expect", "is expected", "anticipates" or "does not anticipate", "plans", "budget", "scheduled", "forecasts", "estimates", "believes" or "intends" or variations of such words and phrases or stating that certain actions, events or results "may" or "could", "would", "might" or "will" be taken to occur or be achieved) are not statements of historical fact and may be forward-looking statements. In this news release, forward-looking statements relate, among other things, to: the Company's future performance, revenue, growth and profitability; and the Company's ability to execute on its current and future business plans. These forward-looking statements are provided only to provide information currently available to us and are not intended to serve as and must not be relied on by any investor as, a guarantee, assurance or definitive statement of fact or probability. Forward-looking statements are necessarily based upon a number of estimates and assumptions which include, but are not limited to: the Company's ability to grow its business and being able to execute on its business plans, the success of Company's vendors and partners in their provision of services to the Company, the Company being able to recognize and capitalize on opportunities and the Company continuing to attract qualified personnel to supports its development requirements. These assumptions, while considered reasonable, are subject to known and unknown risks, uncertainties, and other factors which may cause the actual results and future events to differ materially from those expressed or implied by such forward-looking statements. Such factors include, but are not limited to: the Company's ability to achieve its objectives, the Company successfully executing its growth strategy, the ability of the Company to obtain future financings or complete offerings on acceptable terms, failure to leverage the Company's portfolio across entertainment and media platforms, dependence on the Company's key personnel and general business, economic, competitive, political and social uncertainties. These risk factors are not intended to represent a complete list of the factors that could affect the Company which are discussed in the Company's most recent MD&A. There can be no assurance that forward-looking statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on the forward-looking statements and information contained in this news release. GameSquare assumes no obligation to update the forward-looking statements of beliefs, opinions, projections, or other factors, should they change, except as required by law. GameSquare Corporate Contact Lou Schwartz, PresidentPhone: (216) 464-6400Email: ir@ GameSquare Investor Relations Andrew BergerPhone: (216) 464-6400Email: ir@ GameSquare Media Relations Chelsey Northern / The UntoldPhone: (254) 855-4028Email: pr@ SOURCE: GameSquare Holdings, Inc. View the original press release on ACCESS Newswire Melden Sie sich an, um Ihr Portfolio aufzurufen.
Yahoo
39 minutes ago
- Yahoo
Exxon signals lower oil, gas prices could hit second-quarter profit
By Sheila Dang HOUSTON (Reuters) -Exxon Mobil signaled on Monday that lower oil and gas prices could cut its second-quarter earnings by about $1.5 billion from the previous quarter's level. The earnings snapshot from the largest U.S. oil producer is closely watched for clues on how the broader oil sector will fare when companies begin releasing quarterly results in a few weeks. Benchmark Brent crude prices averaged $66.71 per barrel during the April to June quarter, an 11% decline from the previous quarter, as more crude supply from the OPEC+ group of producers weighed on prices. U.S. natural gas prices declined 9% from the first quarter. Exxon said in the regulatory filing that it will release the final quarterly results on Aug. 1. Wall Street expects Exxon to report adjusted earnings of $1.53 per share for the second quarter, according to estimates compiled by LSEG. The company had posted $6.8 billion in upstream earnings for the first quarter. Its total profit in that quarter was $7.71 billion.