State regulators order Peoples Gas to finish pipeline replacement by 2035
After a yearlong review, state regulators Thursday gave Peoples Gas the green light to resume its long-running, multibillion-dollar pipeline replacement program, but with a narrowed focus, accelerated timeline and greater accountability.
The order, unanimously approved by the Illinois Commerce Commission, directs the utility to retire the remaining 1,000 miles of aging leak-prone cast iron and ductile pipes running under Chicago by 2035.
A safety monitor will oversee and report on Peoples' progress annually beginning in 2027, with the threat of civil penalties if the company 'fails to comply with the completion deadline,' according to the order.
But the ICC did not sign off on a broader $7.2 billion proposal by Peoples to modernize its entire system by 2040, which included upgrading to medium pressure and moving gas meters outside homes. Instead, the utility will need to prioritize the pipeline replacement and justify the work in its annual rate hearings to recover the costs.
Abe Scarr, director of Illinois PIRG, a nonprofit consumer advocacy organization, hailed the decision as a victory for Peoples Gas customers that will help hold down future rate hikes associated with an infrastructure program that had expanded far beyond its initial mission.
'By refocusing Peoples Gas on cost-effective investments to mitigate safety risks, the ICC has directed Peoples Gas to run a program that costs less, makes us safer, and facilitates the transition to cleaner energy,' Scarr said in a news release.
Consumer groups have long argued that the utility should focus on repairing and replacing the most vulnerable leak-prone pipes, while Peoples has incorporated a broader system upgrade that has taken years longer and cost billions more than originally projected.
In the wake of the decision Thursday, Peoples Gas suggested the ICC order to speed up the process and focus entirely on pipeline replacement may prove more expensive and disruptive in the long run.
'This direction given by the Commission, compared to the prior approach, may necessitate additional cost and more construction sites disrupting streets across city neighborhoods,' Peoples Gas said in a statement.
Peoples Gas has a subterranean network of some 4,600 miles of pipes under the city, including significant stretches of original cast and ductile iron — some dating back to the 1800s — which pose a risk of gas leaks that could lead to an explosion.
Launched in 2011, the Safety (formerly System) Modernization Program to replace the aging iron pipes was projected at inception to cost $2.6 billion and take 20 years to finish. Plagued from the outset by delays and budget overruns, the program has already cost $3.3 billion and is just 38% complete, according to the utility.
About 1,078 miles of the leak-prone cast and ductile iron pipes remain, Peoples Gas spokesperson David Schwartz said Thursday.
Initially funded by a 10-year legislative rider enabling the utility to automatically pass the costs along to customers, the pipeline program was paused by the ICC last year for an investigation to determine the best path forward after the surcharge expired at the end of 2023.
In November, two Illinois Commerce Commission administrative law judges issued a proposed order recommending Peoples Gas resume and finish the work — including the upgrade to medium pressure and meter relocation — by 2035, at a projected additional cost of $7.2 billion.
The recommended plan, which was based on the preferred option suggested by Peoples Gas during the review process, would have put the total price tag of the program at $10.5 billion, with the utility's 891,000 Chicago customers bearing the cost through their monthly bills.
Some consumer advocates believe the actual price would have been even higher.
In October, the Citizens Utility Board released a Groundwork Data report it commissioned warning that completing the pipeline replacement program would actually cost another $12.8 billion, topping the utility's projections by more than $5 billion.
The report concluded Peoples Gas would need to impose record-breaking 7% annual rate increases over the next 15 years to cover that cost, effectively doubling delivery charges for its customers.
The long-running replacement program was driven by pressure from the administration of former President Barack Obama to hold utilities across the U.S. accountable for aging pipeline systems following a 2010 explosion in San Bruno, California, that killed eight people, injured 58 and destroyed 38 homes.
But consumer advocates have argued for years that gas pipelines may be obsolete by the time Peoples completes the systemwide infrastructure upgrade, as the shift to electrification and renewable energy sources, such as wind and solar, gain traction.
The new ICC order directs Peoples to retire all old cast iron and ductile pipe under 36 inches in diameter by 2035. During the review process, Peoples said that larger cast iron pipe in the system has a longer remaining life than smaller diameter pipe.
While the order didn't preclude other system improvements, finding that 'moving from a low-pressure to a medium-pressure system can offer improvements in safety and operational efficiency,' it nonetheless directs Peoples to focus on getting the old iron pipes out, and also 'declined to prioritize' meter relocation work.
After years of budget overruns, delays and expanding scope, Scarr is hopeful that the refocused pipeline program will finally get the job done for Peoples Gas customers and the city.
'It should be less expensive for customers and get better outcomes,' Scarr told the Tribune.
rchannick@chicagotribune.com

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles
Yahoo
a day ago
- Yahoo
Why Harmony Gold Mining Company Limited (HMY) Crashed On Friday
We recently published a list of . In this article, we are going to take a look at where Harmony Gold Mining Company Limited (NYSE:HMY) stands against other Friday's worst-performing stocks. Harmony Gold saw its share prices decline by 5.27 percent on Friday to finish at $14.56 apiece as investor sentiment was dampened by the death of another mine worker—allegedly the 10th death case recorded this year alone. The news sparked investor concerns about the company's safety regulations and strategy, especially as it aims to achieve zero harm and foster a proactive safety culture. An open pit mine with heavy excavation machinery toiling away against the backdrop of a hidden valley. 'Harmony Gold Mining Company Limited regrets to announce a loss of life due to a fall of ground at its Joel mine in the Free State province. All relevant authorities, family members, and colleagues have been informed,' it said. 'We have been on a journey to achieve zero harm since 2016, and we continually assess the maturity of this journey to identify areas for improvement,' it added. Harmony Gold Mining Company Limited (NYSE:HMY) said that it achieved six months of death-free shifts, showing that its strategy was correct. 'We continue to believe that zero loss of life is possible,' it noted. Overall, HMY ranks 4th on our list of Friday's worst-performing stocks. While we acknowledge the potential of HMY as an investment, our conviction lies in the belief that some AI stocks hold greater promise for delivering higher returns and have limited downside risk. If you are looking for an extremely cheap AI stock that is also a major beneficiary of Trump tariffs and onshoring, see our free report on the best short-term AI stock. READ NEXT: 20 Best AI Stocks To Buy Now and 30 Best Stocks to Buy Now According to Billionaires. Disclosure: None. This article is originally published at Insider Monkey.

Yahoo
2 days ago
- Yahoo
Microsoft to rank ‘safety' of AI models sold to cloud customers
Microsoft will start ranking artificial intelligence models based on their safety performance, as the software group seeks to build trust Sign in to access your portfolio

Yahoo
2 days ago
- Yahoo
Head of ‘sham' construction safety training school gets one year in prison
The owner of a fraudulent construction safety company that faked safety certifications for thousands of workers, including one man who fell to his death from a job site in 2022, has pleaded guilty to reckless endangerment and other charges and will do a year behind bars, the Manhattan District Attorney's Office announced. The company, Valor Security, previously one of the largest companies in New York City for job safety training, came under scrutiny in 2022 after worker Ivan Frias fell to his death from a 15-story Upper West Side building he was working on at 263 West End Ave., at W. 72nd St. Between December 2019 and April 2023, the company, founded by Alexander Shaporov, certified that 20,000 laborers had each completed 40 hours of courses, according to the district attorney's office. Laborers cannot work at most construction sites in the city without completing the training. But according to court documents, most of the workers who were certified by Valor were never trained — including Frias. Valor filed paperwork showing that Frias had received safety training, including eight hours of fall protection, but Frias never took the courses, court documents state. Shaporov and Valor Security both pleaded guilty to one count of attempted enterprise corruption, 10 counts of offering a false instrument and one count of reckless endangerment. Under the terms of their pleas, Shaporov is expected to be sentenced on Oct. 3 to one year in jail, 100 hours of community service and the forfeiture of $100,000. Valor also lost its security license. 'Valor Security is facing accountability for operating a sham safety training school, imperiling the workers in one of New York's most dangerous industries,' Bragg said. 'Valor's president, Alexander Shaporov, also pleaded guilty to recklessly endangering Ivan Frias, who tragically died when he fell from a construction site without proper training. We will continue to root out fraud with our partners at DOI and DOB,' he added, referring to the city's Department of Investigation and Department of Buildings. 'Ignoring the city's construction training standards poses grave risks and can have tragic consequences,' DOI Commissioner Jocelyn Strauber said. The plea comes one day after a construction worker was killed by a slab of concrete falling on him as he worked on a building shed in Brooklyn. In that fatal accident, DOB issued multiple violations for work without a permit — including demolition in progress of a walk-in freezer and a commercial kitchen — and for failing to maintain the structure. In addition, officials said, DOB ordered all construction work at the site to stop immediately and for the building to be vacated and sealed.