Torex Gold Reports Q1 2025 Results
"With our highest cash outflow and lowest production quarter of the year now behind us, our focus is set on further unlocking value for our shareholders through returning to positive free cash flow, executing our exploration program across the entire Morelos Property, implementing a formal return of capital policy, delivering on full-year guidance for the seventh consecutive year, and ramping up Media Luna to the designed mining rate by mid-2026."
"As is typical of our cash flow seasonality, the first quarter was the highest for tax and royalty payments for the year. These payments, coupled with the final capital spend on Media Luna and limited production, necessitated the net $130 million draw on our credit facility per our plan. As we hit our projected free cash flow inflection point mid-year with completion of Media Luna Project spending, we expect to repay the modest amount of debt drawn quickly, particularly as production ramps up under a backdrop of record gold prices.
"Production levels for the quarter were in line with our expectations given the four-week shutdown at the processing plant. Production is expected to pick up during the second quarter through the early stages of ramp up and increase further through the back half of the year, with annual guidance being maintained. All-in sustaining costs 1 for Q1 were much better than originally anticipated as initial sales from Media Luna did not commence until early April. As a result, the higher cost ore associated with the commissioning phase of the Media Luna mine will now be recognized in Q2, aligning with initial sales from Media Luna.
"The first quarter was marked with significant milestones for Torex. We completed the tie-ins at the processing plant not only on time but, more importantly, safely. We also delivered first concentrate production, with regular shipments commencing in April. Earlier this week, we proudly declared commercial production at Media Luna, marking the conclusion of the project phase and the beginning of our transition back to positive free cash flow 1 generation.
Toronto, Ontario--(Newsfile Corp. - May 7, 2025) - Torex Gold Resources Inc. (the "Company" or "Torex") (TSX: TXG) reports the Company's financial and operational results for the three months ended March 31, 2025. Torex will host a conference call tomorrow morning at 9:00 AM (ET) to discuss the results.
Story Continues
FIRST QUARTER 2025 HIGHLIGHTS
Safety performance: The Company recorded one lost-time injury during the quarter when a contractor suffered an ankle fracture. As at March 31, 2025, the lost-time injury frequency ("LTIF") for the Morelos Complex was 0.59 per million hours worked for both employees and contractors on a rolling 12-month basis. During the quarter, the internal investigation into the fatal carbon monoxide exposure that occurred in December 2024 was concluded and follow up action items are being tracked to completion. In addition, the Company has embarked on a comprehensive 'Next Level Safety' program with a view to ensuring that the operations resumes and maintains its prior fatality free status.
Gold payable production: On a gold equivalent ounce ("oz AuEq") basis, payable production for the quarter was 59,630 oz AuEq 2 , including 58,330 oz Au. Production in the quarter was as expected and driven by the planned four-week tie-in period at the processing plant in connection with the Media Luna Project. The Company is on track to achieve annual payable production guidance of 400,000 to 450,000 oz AuEq 2 .
Gold sold: The Company sold 60,568 oz AuEq 2 at a record quarterly average realized gold price 1 of $2,793 per oz, contributing to revenue of $170.0 million, which was lower than the quarterly average as sales of metal produced from the new circuits as part of the Media Luna Project commenced in April.
All-in sustaining costs 1 : All-in sustaining costs of $1,405 per oz AuEq sold 2 relative to guidance of $1,400 to $1,600 per oz AuEq sold 2 . All-in sustaining costs margin 1 of $1,388 per oz AuEq sold, implying an all-in sustaining costs margin 1 of 50%. Cost of sales was $94.1 million or $1,554 per oz AuEq sold in the quarter.
Net income and adjusted net earnings 1 : Reported net income of $39.0 million or earnings of $0.45 per share on both a basic and dilutive basis. Adjusted net earnings of $35.9 million or $0.42 per share on a basic basis and $0.41 per share on a diluted basis.
EBITDA 1 and adjusted EBITDA 1 : Generated EBITDA of $88.1 million and adjusted EBITDA of $91.8 million.
Cash flow generation: Net cash used in operating activities totalled $9.9 million and $17.7 million before changes in non-cash operating working capital. Net cash used in operating activities (including changes in non-cash operating working capital) of $9.9 million including income taxes paid of $101.6 million, reflecting the annual payment of mining taxes and annual true-up of corporate income taxes, and payment of the 0.5% royalty in respect of 2024 of $4.7 million. Negative free cash flow 1 of $133.3 million is net of cash outlays for capital expenditures, lease payments, and interest, including borrowing costs capitalized. Negative free cash flow was a result of the lower sales volumes due to the four-week tie-in period at the processing plant and capital expenditures of $123.5 million in the first quarter of 2025.
Financial liquidity: The quarter closed with $197.6 million in available liquidity 1 , including $106.5 million in cash and $91.1 million available on the $300.0 million credit facilities, net of borrowings of $195.0 million and letters of credit outstanding of $13.9 million.
Media Luna Project: In late March, the tie-in period was completed at the processing plant and the Company achieved first production of copper concentrate, marking the substantial completion of the Media Luna Project. Effective April 26, 2025, Media Luna reached the production stage, and commercial production was declared. During the quarter, $55.5 million was invested in the project and as of March 31, 2025, physical progress on the Project was approximately 98%.
Exploration and Drilling Activities: In February, the Company announced results from the ongoing drilling program at Media Luna West and results from initial drill testing at Media Luna East 3 . The advanced exploration drilling program at Media Luna West has defined a mineralized footprint of 600 metres ("m") by 400 m with multiple high-grade intercepts. The intercepts indicate the exploration upside to the west of the defined resource boundaries of Media Luna and EPO. Initial drill testing at Media Luna East returned strong results, with multiple high-grade intercepts, many with copper ("Cu") grades in excess of 2%. Drilling at both targets is part of the Company's exploration strategy, which is focused, in part, on unlocking the resource potential of the Morelos Complex in order to enhance and extend the production profile.
Year-end Mineral Reserves & Resources4: At EPO, an inaugural Probable Reserve of 781 koz AuEq was declared in September 2024 and an updated reserve estimate for EPO is currently being undertaken as part of the internal feasibility study. Due to drilling undertaken in 2024 north of the EPO deposit, Inferred Resources at EPO increased 32% to 954 koz AuEq from 721 koz AuEq. At ELG Underground, drilling was successful at replacing depletion with Proven and Probable Reserves increasing 1% to 662 koz AuEq during the year, supporting a reserve life through early 2029, which assumes an average mining rate of 2,800 tpd through 2026 and approximately 2,000 tpd thereafter. At Media Luna, updated mineral reserves and mineral resources primarily reflect results of definition drilling as well as modest refinements to some stope shapes. With the completion of the Media Luna Project, step-out and infill drilling at Media Luna is set to resume in 2025, with the goal of expanding and upgrading mineral resources as well as replacing mineral reserves. The positive results from the 2024 drilling program solidifies annual payable production of at least 450,000 koz AuEq through 2030 and a reserve life out to at least 2035. With approximately 125,000 m of drilling planned in 2025, almost double the metres drilled in 2024, the Company is focused on enhancing the base case production profile beyond 2030, extending the reserve life of the underground deposits, and further showcasing the underlying potential of the broader Morelos Property by testing several regional targets.
1. These measures are non-GAAP financial measures ("Non-GAAP Measures") which are not standardized financial measures under IFRS, the framework used to prepare the financial statements of the Company and might not be comparable to similar financial measures used by other companies. For a detailed reconciliation of each Non-GAAP Measure to its most directly comparable measure in accordance with the IFRS, see Tables 2 to 11 of this press release. For additional information on these Non-GAAP Measures, please refer to the Company's MD&A for the three months ended March 31, 2025, dated May 7, 2025, which is incorporated by reference into this news release. The MD&A and the Company's unaudited condensed consolidated interim financial statements and related notes for the three months ended March 31, 2025, are available on Torex's website (www.torexgold.com) and under the Company's SEDAR+ profile (www.sedarplus.ca).
2. Gold equivalent ounces produced and sold include production of silver and copper converted to a gold equivalent based on a ratio of the average market prices for each commodity sold in the period. For the three months ended March 31, 2025, market prices averaged $2,860/oz gold, $31.88/oz silver, and $4.24/lb copper. Guidance for 2025 assumed metal prices of $2,500/oz gold, $28/oz silver, and $4.30/lb copper.
3. For more information on Media Luna drilling results, see the Company's news release titled "Torex Gold Reports Excellent Drill Results from Media Luna West and Initial Results from Media Luna East" issued on February 24, 2025, and filed on SEDAR+ at www.sedarplus.ca and on the Company's website at www.torexgold.com.
4. Mineral reserve and mineral resource estimates for the Morelos Complex can be found in tables 12 and 13, respectively, of this press release. AuEq values account for underlying metal prices and metallurgical recoveries used in reserve and resource estimates. For additional information on the mineral reserve and mineral resource estimates for the Morelos Complex, please see the Company's annual information form for the year ended December 31, 2024, or the Company's news release titled "Torex Gold Reports Year-end 2024 Reserves & Resources" issued on March 19, 2025, and filed on SEDAR+ at www.sedarplus.ca and on the Company's website at www.torexgold.com.
CONFERENCE CALL AND WEBCAST DETAILS
The Company will host a conference call tomorrow at 9:00 AM (ET) where senior management will discuss the first quarter operating and financial results. For expedited access to the conference call, registration is open to obtain an access code in advance, which will allow participants to join the call directly at the scheduled time. Alternatively, dial-in details are as follows:
Toronto local or International: 1-647-846-8914
Toll-Free (North America): 1-833-752-3842
A live webcast and replay of the conference call will be available on the Company's website at https://torexgold.com/investors/upcoming-events/. The webcast will be archived on the Company's website.
Table 1: Operating and Financial Highlights
Three Months Ended
Mar 31,
Dec 31,
Mar 31,
In millions of U.S. dollars, unless otherwise noted
2025
2024
2024
Safety
Lost-time injury frequency1
/million hours
0.59
0.61
0.15
Total recordable injury frequency1
/million hours
1.52
1.48
0.97
Operating Results - Gold Equivalent basis
Gold equivalent payable produced2
oz AuEq
59,630
105,132
117,054
Gold equivalent sold2
oz AuEq
60,568
110,419
114,106
Total cash costs2,3
$/oz AuEq
1,020
932
944
Total cash costs margin2,3
$/oz AuEq
1,773
1,555
1,079
All-in sustaining costs2,3
$/oz AuEq
1,405
1,112
1,222
All-in sustaining costs margin2,3
$/oz AuEq
1,388
1,375
801
Average realized gold price2,3
$/oz
2,793
2,487
2,023
Financial Results
Revenue
$
170.0
295.0
236.5
Cost of sales
$
94.1
153.5
157.4
Earnings from mine operations
$
75.9
141.5
79.1
Net income
$
39.0
60.4
43.1
Per share - Basic
$/share
0.45
0.70
0.50
Per share - Diluted
$/share
0.45
0.69
0.50
Adjusted net earnings3
$
35.9
70.6
35.9
Per share - Basic3
$/share
0.42
0.82
0.42
Per share - Diluted3
$/share
0.41
0.81
0.42
EBITDA3
$
88.1
162.8
98.0
Adjusted EBITDA3
$
91.8
154.3
113.2
Cost of sales - gold equivalent basis
$/oz AuEq
1,554
1,390
1,378
Net cash (used in) generated from operating activities
$
(9.9
)
122.8
79.8
Net cash (used in) generated from operating activities before changes in non-cash operating working capital
$
(17.7
)
136.3
72.5
Free cash flow3
$
(133.3
)
(7.7
)
(59.4
)
Cash and cash equivalents
$
106.5
110.2
113.2
Debt, net of deferred finance charges
$
193.1
62.9
-
Lease-related obligations
$
86.5
78.3
44.0
Net (debt) cash3
$
(175.0
)
(33.1
)
69.2
Available liquidity3
$
197.6
331.5
405.3
1. On a 12-month rolling basis, per million hours worked.
2. Gold equivalent ounces produced and sold include production of silver and copper converted to a gold equivalent based on a ratio of the average market prices for each commodity sold in the period. Refer to the "Gold Equivalent Reporting" section of the Company's MD&A for the three months ended March 31, 2025, dated May 7, 2025 for the relevant average market prices by commodity, available on Torex's website (www.torexgold.com) and under the Company's SEDAR+ profile (www.sedarplus.ca).
3. Total cash costs, total cash costs margin, all-in sustaining costs, all-in sustaining costs margin, average realized gold price, adjusted net earnings, adjusted net earnings per share, EBITDA, adjusted EBITDA, free cash flow, net (debt) cash and available liquidity are non-GAAP financial measures with no standardized meaning under IFRS and might not be comparable to similar financial measures disclosed by other issuers. For a detailed reconciliation of each Non-GAAP Measure to its most directly comparable measure in accordance with the IFRS as issued by the International Accounting Standards Board see Tables 2 to 11 of this press release. For additional information on these Non-GAAP Measures, please refer to the Company's MD&A for the three months ended March 31, 2025, dated May 7, 2025. The MD&A and the Company's the Company's unaudited condensed consolidated interim financial statements and related notes for the three months ended March 31, 2025, are available on Torex's website (www.torexgold.com) and under the Company's SEDAR+ profile (www.sedarplus.ca)
Table 2: Reconciliation of Total Cash Costs and All-in Sustaining Costs to Production Costs and Royalties
Three Months Ended
Mar 31,
Dec 31,
Mar 31,
In millions of U.S. dollars, unless otherwise noted
2025
2024
2024
Gold sold
oz
59,756
108,647
111,642
Total cash costs per oz sold
Production costs1
$
56.2
94.7
100.8
Royalties
$
6.0
8.2
6.9
Less: Silver sales
$
(1.1
)
(1.8
)
(1.5
)
Less: Copper sales
$
(1.2
)
(3.1
)
(3.7
)
Less: Realized gain on foreign currency contracts
$
(0.4
)
-
-
Total cash costs
$
59.5
98.0
102.5
Total cash costs per oz sold
$/oz
996
902
918
All-in sustaining costs per oz sold
Total cash costs
$
59.5
98.0
102.5
General and administrative costs2
$
8.7
7.3
8.0
Reclamation and remediation costs
$
1.0
1.0
1.3
Sustaining capital expenditure
$
13.6
11.6
22.4
Total all-in sustaining costs
$
82.8
117.9
134.2
Total all-in sustaining costs per oz sold
$/oz
1,386
1,085
1,202
Gold equivalent sold3
oz AuEq
60,568
110,419
114,106
Total cash costs per oz AuEq sold
Production costs1
$
56.2
94.7
100.8
Royalties
$
6.0
8.2
6.9
Less: Realized gain on foreign currency contracts
$
(0.4
)
-
-
Total cash costs
$
61.8
102.9
107.7
Total cash costs per oz AuEq sold3
$/oz AuEq
1,020
932
944
All-in sustaining costs per oz AuEq sold
Total cash costs
$
61.8
102.9
107.7
General and administrative costs2
$
8.7
7.3
8.0
Reclamation and remediation costs
$
1.0
1.0
1.3
Sustaining capital expenditure
$
13.6
11.6
22.4
Total all-in sustaining costs
$
85.1
122.8
139.4
Total all-in sustaining costs per oz AuEq sold3
$/oz AuEq
1,405
1,112
1,222
1. This amount excludes temporary suspension costs of $nil, $3.1 million and $nil for the three months ended March 31, 2025, December 31, 2024, and March 31, 2024, respectively.
2. This amount excludes a loss of $7.6 million, loss of $6.8 million and loss of $4.2 million for the three months ended March 31, 2025, December 31, 2024, and March 31, 2024, respectively, in relation to the remeasurement of share-based payments. This amount also excludes corporate depreciation and amortization expenses totalling $0.1 million, $0.2 million and $0.1 million for the three months ended March 31, 2025, December 31, 2024, and March 31, 2024, respectively, within general and administrative costs. Included in general and administrative costs is share-based compensation expense in the amount of $2.3 million or $38/oz ($38/oz AuEq) for the three months ended March 31, 2025, $1.6 million or $15/oz ($14/oz AuEq) for the three months ended December 31, 2024, $2.3 million or $21/oz ($20/oz AuEq) for the three months ended March 31, 2024. This amount excludes other expenses totalling $nil, $1.4 million and $1.2 million for the three months ended March 31, 2025, December 31, 2024, and March 31, 2024, respectively.
3. Gold equivalent ounces produced and sold include production of silver and copper converted to a gold equivalent based on a ratio of the average market prices for each commodity sold in the period. Refer to the "Gold Equivalent Reporting" section of the Company's MD&A for the three months ended March 31, 2025, dated May 7, 2025 for the relevant average market prices by commodity, available on Torex's website (www.torexgold.com) and under the Company's SEDAR+ profile (www.sedarplus.ca).
Table 3: Reconciliation of Sustaining and Non-Sustaining Capital Expenditures to Additions to Property, Plant and Equipment
Three Months Ended
Mar 31,
Dec 31,
Mar 31,
In millions of U.S. dollars
2025
2024
2024
Sustaining
$
13.6
11.6
21.6
Capitalized Stripping (Sustaining)
$
-
-
0.8
Total Sustaining
$
13.6
11.6
22.4
Non-sustaining
Media Luna Project1
$
55.5
100.5
126.4
EPO Project
$
4.0
0.6
-
Media Luna Cluster Drilling and Other
$
0.2
2.4
1.3
Working Capital Changes and Other
$
50.2
12.7
(24.0
)
Capital expenditures2
$
123.5
127.8
126.1
1. This amount includes a realized gain (or an increase in the capitalized expenditures) of $nil, loss of $0.1 million and gain of $0.8 million for the three months ended March 31, 2025, December 31, 2024, and March 31, 2024, respectively, in relation to the settlement of foreign exchange zero cost collars that were entered into to manage the capital expenditure risk related to a further strengthening of the Mexican peso.
2. The amount of cash expended on additions to property, plant and equipment in the period as reported in the Condensed Consolidated Interim Statements of Cash Flows.
Table 4: Reconciliation of Average Realized Gold Price and Total Cash Costs Margin to Revenue
Three Months Ended
Mar 31,
Dec 31,
Mar 31,
In millions of U.S. dollars, unless otherwise noted
2025
2024
2024
Gold sold
oz
59,756
108,647
111,642
Revenue
$
170.0
295.0
236.5
Less: Silver sales
$
(1.1
)
(1.8
)
(1.5
)
Less: Copper sales
$
(1.2
)
(3.1
)
(3.7
)
Less: Realized loss on gold contracts
$
(0.8
)
(19.9
)
(5.4
)
Total proceeds
$
166.9
270.2
225.9
Average realized gold price
$/oz
2,793
2,487
2,023
Less: Total cash costs
$/oz
996
902
918
Total cash costs margin
$/oz
1,797
1,585
1,105
Total cash costs margin
%
64
64
55
Gold equivalent sold1
oz AuEq
60,568
110,419
114,106
Revenue
$
170.0
295.0
236.5
Less: Realized loss on gold contracts
$
(0.8
)
(19.9
)
(5.4
)
Total proceeds
$
169.2
275.1
231.1
Average realized gold price
$/oz
2,793
2,487
2,023
Less: Total cash costs1
$/oz AuEq
1,020
932
944
Total cash costs margin1
$/oz AuEq
1,773
1,555
1,079
Total cash costs margin
%
63
63
53
1. Gold equivalent ounces produced and sold include production of silver and copper converted to a gold equivalent based on a ratio of the average market prices for each commodity sold in the period. Refer to the "Gold Equivalent Reporting" section of the Company's MD&A for the three months ended March 31, 2025, dated May 7, 2025 for the relevant average market prices by commodity, available on Torex's website (www.torexgold.com) and under the Company's SEDAR+ profile (www.sedarplus.ca).
Table 5: Reconciliation of All-in Sustaining Costs Margin to Revenue
Three Months Ended
Mar 31,
Dec 31,
Mar 31,
In millions of U.S. dollars, unless otherwise noted
2025
2024
2024
Gold sold
oz
59,756
108,647
111,642
Revenue
$
170.0
295.0
236.5
Less: Silver sales
$
(1.1
)
(1.8
)
(1.5
)
Less: Copper sales
$
(1.2
)
(3.1
)
(3.7
)
Less: Realized loss on gold contracts
$
(0.8
)
(19.9
)
(5.4
)
Less: All-in sustaining costs
$
(82.8
)
(117.9
)
(134.2
)
All-in sustaining costs margin
$
84.1
152.3
91.7
Average realized gold price
$/oz
2,793
2,487
2,023
Total all-in sustaining costs margin
$/oz
1,407
1,402
821
Total all-in sustaining costs margin
%
50
56
41
Gold equivalent sold1
oz AuEq
60,568
110,419
114,106
Revenue
$
170.0
295.0
236.5
Less: Realized loss on gold contracts
$
(0.8
)
(19.9
)
(5.4
)
Less: All-in sustaining costs
$
(85.1
)
(122.8
)
(139.4
)
All-in sustaining costs margin
$
84.1
152.3
91.7
Average realized gold price
$/oz
2,793
2,487
2,023
Total all-in sustaining costs margin1
$/oz AuEq
1,388
1,375
801
Total all-in sustaining costs margin
%
50
55
40
1. Gold equivalent ounces produced and sold include production of silver and copper converted to a gold equivalent based on a ratio of the average market prices for each commodity sold in the period. Refer to the "Gold Equivalent Reporting" section of the Company's MD&A for the three months ended March 31, 2025, dated May 7, 2025 for the relevant average market prices by commodity, available on Torex's website (www.torexgold.com) and under the Company's SEDAR+ profile (www.sedarplus.ca).
Table 6: Reconciliation of Adjusted Net Earnings to Net Income
Three Months Ended
In millions of U.S. dollars, unless otherwise noted
Mar 31,
Dec 31,
Mar 31,
2025
2024
2024
Basic weighted average shares outstanding
shares
86,125,855
85,988,115
85,949,559
Diluted weighted average shares outstanding
shares
87,326,899
87,414,063
86,499,360
Net income
$
39.0
60.4
43.1
Adjustments:
Temporary suspension costs
$
-
3.1
-
Unrealized foreign exchange gain
$
(0.7
)
(2.0
)
(0.6
)
Unrealized (gain) loss on derivative contracts
$
(3.2
)
(16.4
)
11.6
Loss on remeasurement of share-based payments
$
7.6
6.8
4.2
Derecognition of provisions for uncertain tax positions
$
(9.2
)
-
(12.1
)
Tax effect of above adjustments
$
1.2
4.6
(3.3
)
Tax effect of currency translation on tax base
$
1.2
14.1
(7.0
)
Adjusted net earnings
$
35.9
70.6
35.9
Per share - Basic
$/share
0.42
0.82
0.42
Per share - Diluted
$/share
0.41
0.81
0.42
Table 7: Reconciliation of EBITDA and Adjusted EBITDA to Net Income
Three Months Ended
Mar 31,
Dec 31,
Mar 31,
In millions of U.S. dollars
2025
2024
2024
Net income
$
39.0
60.4
43.1
Finance costs (income), net
$
2.6
(0.3)
(1.7)
Depreciation and amortization1
$
32.0
47.7
49.8
Current income tax expense
$
6.0
42.9
26.2
Deferred income tax expense (recovery)
$
8.5
12.1
(19.4)
EBITDA
$
88.1
162.8
98.0
Adjustments:
Temporary suspension costs
$
-
3.1
-
Unrealized (gain) loss on derivative contracts
$
(3.2)
(16.4)
11.6
Unrealized foreign exchange gain
$
(0.7)
(2.0)
(0.6)
Loss on remeasurement of share-based payments
$
7.6
6.8
4.2
Adjusted EBITDA
$
91.8
154.3
113.2
1. Includes depreciation and amortization included in cost of sales, general and administrative expenses and exploration and evaluation expenses.
Table 8: Reconciliation of Free Cash Flow to Net Cash Generated from Operating Activities
Three Months Ended
Mar 31,
Dec 31,
Mar 31,
In millions of U.S. dollars
2025
2024
2024
Net cash (used in) generated from operating activities
$
(9.9
)
122.8
79.8
Less:
Additions to property, plant and equipment1
$
(123.5
)
(127.8
)
(126.1
)
Value-added tax receivables, net
$
7.6
3.1
(10.3
)
Lease payments
$
(3.4
)
(2.9
)
(1.4
)
Interest and other borrowing costs paid2
$
(4.1
)
(2.9
)
(1.4
)
Free cash flow
$
(133.3
)
(7.7
)
(59.4
)
1. The amount of cash expended on additions to property, plant and equipment in the period as reported on the Condensed Consolidated Interim Statements of Cash Flows.
2. Including borrowing costs capitalized to property, plant and equipment.
Table 9: Reconciliation of Net (Debt) Cash to Cash and Cash Equivalents
Mar 31,
Dec 31,
Mar 31,
In millions of U.S. dollars
2025
2024
2024
Cash and cash equivalents
$
106.5
110.2
113.2
Less:
Debt
$
(193.1)
(62.9
)
-
Lease-related obligations
$
(86.5
)
(78.3
)
(44.0
)
Deferred finance charges
$
(1.9
)
(2.1
)
-
Net (debt) cash
$
(175.0
)
(33.1
)
69.2
Table 10: Reconciliation of Available Liquidity to Cash and Cash Equivalents
Mar 31,
Dec 31,
Mar 31,
In millions of U.S. dollars
2025
2024
2024
Cash and cash equivalents
$
106.5
110.2
113.2
Add: Available credit of the Debt Facility
$
91.1
221.3
292.1
Available liquidity
$
197.6
331.5
405.3
Table 11: Reconciliation of Unit Cost Measures to Production Costs
Three Months Ended
In millions of U.S. dollars, unless otherwise noted
Mar 31, 2025
Dec 31, 2024
Mar 31, 2024
Gold sold (oz AuEq)
60,568
110,419
114,106
Gold sold (oz)
59,756
108,647
111,642
Tonnes mined - ELG open pit (kt)
672
2,400
8,981
Tonnes mined - ELG underground (kt)
187
207
168
Tonnes processed (kt)
705
1,094
1,194
Total cash costs:
Total cash costs ($) - gold equivalent basis
61.8
102.9
107.7
Total cash costs per oz AuEq sold ($)
1,020
932
944
Total cash costs ($) - gold only basis
59.5
98.0
102.5
Total cash costs per oz sold ($)
996
902
918
Breakdown of production costs
$
$/t
$
$/t
$
$/t
Mining - open pit
6.0
8.87
14.1
5.85
31.6
3.52
Mining - underground
15.0
80.45
12.4
60.07
13.8
82.34
Processing
25.2
35.72
42.9
39.21
42.5
35.64
Site support
8.1
11.53
16.0
14.60
14.3
12.00
Mexican profit sharing (PTU)
2.1
2.98
4.7
4.30
3.0
2.50
Capitalized stripping
-
-
(0.8
)
Inventory movement
(1.5
)
6.6
(4.3
)
Other
1.3
1.1
0.7
Production costs
56.2
97.8
100.8
Table 12: Mineral Reserve Estimate - Morelos Complex (December 31, 2024)(2*)
Tonnes
Au
Ag
Cu
Au
Ag
Cu
AuEq
AuEq
(kt)
(gpt)
(gpt)
(%)
(koz)
(koz)
(Mlb)
(gpt)
(koz)
Media Luna Underground
Proven
2,834
3.14
31.0
1.01
286
2,826
63
5.18
471
Probable
21,347
2.42
24.7
0.86
1,661
16,962
404
4.14
2,840
Proven & Probable
24,180
2.50
25.5
0.88
1,946
19,788
467
4.26
3,311
ELG Underground
Proven
1,441
4.89
8.0
0.26
226
372
8
5.41
251
Probable
2,578
4.47
7.9
0.24
370
657
14
4.96
411
Proven & Probable
4,019
4.62
8.0
0.25
597
1,029
22
5.12
662
EPO Underground
Proven
-
-
-
-
-
-
-
-
-
Probable
5,029
2.27
29.8
1.29
367
4,820
143
4.83
781
Proven & Probable
5,029
2.27
29.8
1.29
367
4,820
143
4.83
781
ELG Open Pit
Proven
62
2.78
8.3
0.14
6
16
0
2.86
6
Probable
883
2.53
12.6
0.37
72
357
7
2.68
76
Proven & Probable
945
2.55
12.3
0.36
77
373
7
2.69
82
Surface Stockpiles
Proven
6,235
1.19
4.2
0.12
239
842
16
1.30
261
Probable
-
-
-
-
-
-
-
-
-
Proven & Probable
6,235
1.19
4.2
0.12
239
842
16
1.30
261
Total Morelos Complex
Proven
10,571
2.23
11.9
0.37
756
4,056
87
2.91
988
Probable
29,836
2.57
23.8
0.86
2,470
22,796
568
4.28
4,108
Proven & Probable
40,408
2.48
20.7
0.74
3,226
26,851
656
3.92
5,096
Notes to accompany the mineral reserve table:
1. Mineral reserves were developed in accordance with CIM (2014) guidelines.
2. Mineral reserves are founded on Measured and Indicated Mineral Resources, with an effective date of December 31, 2024 (unless otherwise noted).
3. Rounding may result in apparent summation differences between tonnes, grade, and contained metal content. Surface Stockpile mineral reserves are estimated using production and survey data and apply the gold equivalent ("AuEq") formula for the intended processing method.
4. AuEq of Total Morelos Complex is established from combined contributions of the various deposits.
5. The qualified person for the mineral reserve estimate is Johannes (Gertjan) Bekkers, P. Eng., VP of Mines Technical Services.
6. The qualified person is not aware of mining, metallurgical, infrastructure, permitting, or other factors that materially affect the mineral reserve estimates.
Notes to accompany the Media Luna Underground mineral reserves:
1. Media Luna Underground mineral reserves are reported above an in-situ ore cut-off grade of 2.4 g/t AuEq.
2. Media Luna Underground cut-off grades and mining shapes are considered appropriate for a metal price of $1,500/oz gold ("Au"), $19/oz silver ("Ag") and $3.50/lb copper ("Cu") and metal recoveries of 90% Au, 86% Ag, and 93% Cu.
3. Mineral reserves within designed mine shapes assume long-hole open stoping, supplemented with mechanized cut-and-fill mining and includes estimates for dilution and mining losses.
4. Media Luna Underground (including Media Luna surface stockpiles) AuEq = Au (g/t) + Ag (g/t) * (0.0121) + Cu (%) * (1.6533), accounting for metal prices and metallurgical recoveries.
Notes to accompany the ELG Underground mineral reserves:
1. El Limón Underground mineral reserves are reported above an in-situ ore cut-off grade of 2.8 g/t AuEq and an in-situ incremental cut-off grade of 1.6 g/t AuEq.
2. Cut-off grades and mining shapes are considered appropriate for a metal price of $1,500/oz Au, $19/oz Ag, and $3.50/lb Cu and metal recoveries of 90% Au, 86% Ag, and 93% Cu, accounting for the planned copper concentrator.
3. Mineral reserves within designed mine shapes assume mechanized cut and fill supplemented with long hole mining method and include estimates for dilution and mining losses.
4. ELG Underground AuEq = Au (g/t) + Ag (g/t) * (0.0121) + Cu (%) * (1.6533), accounting for metal prices and metallurgical recoveries.
Notes to accompany the EPO Underground mineral reserves:
1. Mineral reserves for EPO Underground have an effective date of June 30, 2024.
2. *Mineral reserves are based on EPO Underground Indicated Mineral Resources with an effective date of December 31, 2023.
3. EPO Underground mineral reserves are reported above an in-situ ore cut-off grade of 2.5 gpt AuEq.
4. EPO Underground cut-off grade and mining shapes are considered appropriate for a metal price of $1,500/oz Au, $19/oz Ag, and $3.50/lb Cu and metal recoveries of 87% Au, 85% Ag, and 92% Cu.
5. Mineral reserves within designed mine shapes assume long-hole open stoping and include estimates for dilution and mining losses.
6. EPO Underground AuEq = Au (gpt) + Ag (gpt) * (0.0124) + Cu (%) * (1.6920), accounting for metal prices and metallurgical recoveries.
Notes to accompany the ELG Open Pit mineral reserves and Surface Stockpiles:
1. ELG Open Pit mineral reserves are reported above an in-situ cut-off grade of 1.2 g/t Au and including low grade mineral reserves are reported above an in-situ cut-off grade of 0.88 g/t Au.
2. It is planned that ELG low grade mineral reserves within the designed pit will be stockpiled during pit operation and processed during pit closure.
3. Mineral reserves within the designed pit include assumed estimates for dilution and ore losses.
4. Cut-off grades and designed pits are considered appropriate for a metal price of $1,500/oz Au and metal recovery of 89% Au.
5. Mineral reserves are reported using an Au price of $1,500/oz, Ag price of $19/oz, and Cu price of $3.50/lb.
6. Average metallurgical recoveries of 89% for Au, 30% for Ag, and 15% for Cu.
7. ELG Open Pit (including open pit surface stockpiles) AuEq = Au (g/t) + Ag (g/t) * (0.0043) + Cu (%) * (0.2697), accounting for metal prices and metallurgical recoveries.
Table 13: Mineral Resource Estimate - Morelos Complex (December 31, 2024)
Tonnes
Au
Ag
Cu
Au
Ag
Cu
AuEq
AuEq
(kt)
(gpt)
(gpt)
(%)
(koz)
(koz)
(Mlb)
(gpt)
(koz)
Media Luna Underground
Measured
2,994
3.95
40.0
1.30
380
3,855
86
6.55
630
Indicated
26,120
2.83
30.2
1.05
2,374
25,385
603
4.90
4,114
Measured & Indicated
29,114
2.94
31.2
1.07
2,754
29,240
689
5.07
4,744
Inferred
7,675
2.38
22.8
0.90
587
5,632
152
4.12
1,017
ELG Underground
Measured
3,164
5.04
7.4
0.27
512
751
19
5.56
566
Indicated
5,287
4.42
8.9
0.28
752
1,521
33
4.99
848
Measured & Indicated
8,451
4.65
8.4
0.28
1,264
2,272
51
5.20
1,414
Inferred
1,961
3.86
7.8
0.21
243
490
9
4.30
271
EPO Underground
Measured
-
-
-
-
-
-
-
-
-
Indicated
7,060
2.66
31.2
1.28
604
7,082
200
5.18
1,176
Measured & Indicated
7,060
2.66
31.2
1.28
604
7,082
200
5.18
1,176
Inferred
6,883
1.76
39.3
1.24
390
8,690
188
4.31
954
ELG Open Pit
Measured
189
3.89
7.0
0.20
24
43
1
3.97
24
Indicated
865
2.46
9.0
0.43
69
251
8
2.62
73
Measured & Indicated
1,054
2.72
8.7
0.38
92
294
9
2.86
97
Inferred
6
3.56
5.9
0.24
1
1
0
3.65
1
Total Morelos Complex
Measured
6,347
4.49
22.8
0.75
916
4,649
105
5.98
1,220
Indicated
39,332
3.00
27.1
0.97
3,798
34,239
844
4.91
6,211
Measured & Indicated
45,679
3.21
26.5
0.94
4,714
38,888
949
5.06
7,431
Inferred
16,526
2.30
27.9
0.96
1,222
14,813
349
4.22
2,243
Notes to accompany the mineral resource table:
1. Mineral resources were prepared in accordance with the CIM Definition Standards (May 2014).
2. The effective date of the estimates is December 31, 2024.
3. Mineral resources are depleted above a mining surface or to the as-mined solids as of December 31, 2024.
4. Gold equivalent ("AuEq") of total mineral resources is established from combined contributions of the various deposits.
5. Mineral resources for all deposits are based on an underlying gold ("Au") price of $1,650/oz, silver ("Ag") price of $22/oz, and copper ("Cu") price of $3.75/lb.
6. Mineral resources are inclusive of mineral reserves (ex-stockpiles). Mineral resources that are not mineral reserves do not have demonstrated economic viability.
7. Numbers may not add due to rounding.
8. Mineral resources may be materially affected by environmental, permitting, legal, title, taxation, sociopolitical, marketing, or other relevant issues.
9. The estimate was prepared by Mrs. Rochelle Collins, P.Geo. (Ontario), Principal, Mineral Resources.
Notes to accompany Media Luna Underground mineral resources:
1. Mineral resources for Media Luna Underground are reported above a 2.0 gpt AuEq cut-off grade. The assumed underground mining methods are a combination of long-hole open stoping and mechanized cut-and-fill.
2. Mineral resources were estimated using ID3 methods applied to 1.0 m capped downhole assay composites within lithology domains and internal grade domains. Block model size is 5 m x 5 m x 5 m with 2.5 m x 2.5 m x 2.5 m sub-blocks.
3. Metallurgical recoveries at Media Luna Underground average 90% Au, 86% Ag, and 93% Cu.
4. The dataset allowed the bulk density to be directly estimated into the domains with an average bulk density of 3.2 g/cm3.
5. Media Luna Underground AuEq = Au (gpt) + (Ag (gpt) * 0.0127) + (Cu (%) * 1.6104), accounting for underlying metal prices and metallurgical recoveries.
Notes to accompany ELG Underground mineral resources:
1. Mineral resources for ELG Underground are reported above a cut-off grade of 2.2 gpt AuEq. The assumed underground mining method is mechanized cut-and-fill.
2. Mineral resources were estimated using ID3 methods applied to 1.0 m capped downhole assay composites within lithology domains and internal grade domains. Block model size is 5 m x 5 m x 5m with 2.5 m x 2.5 m x 2.5m sub-blocks.
3. Average metallurgical recoveries are 90% Au, 86% Ag, and 93% Cu, accounting for recoveries with planned copper concentrator.
4. The dataset allowed the bulk density to be directly estimated into the domains with an average bulk density of 3.4 g/cm3.
5. ELG Underground AuEq = Au (gpt) + (Ag (gpt) * 0.0127) + (Cu (%) * 1.6104), accounting for underlying metal prices and metallurgical recoveries.
Notes to accompany EPO Underground mineral resources:
1. Mineral resources for EPO Underground are reported above a 2.0 gpt AuEq cut-off grade. The assumed mining method is from underground methods, using long-hole open stoping.
2. Mineral resources were estimated using ID3 methods applied to 1.0 m capped downhole assay composites within lithology domains and internal grade domains. Block model size is 5 m x 5 m x 5m with 2.5 m x 2.5 m x 2.5 m sub-blocks.
3. Metallurgical recoveries at EPO average 87% Au, 85% Ag, and 92% Cu.
4. The dataset allowed the bulk density to be directly estimated into the domains with an average bulk density of 3.5 g/cm3.
5. EPO Underground AuEq = Au (gpt) + (Ag (gpt) * 0.0130) + (Cu (%) * 1.6480), accounting for underlying metal prices and metallurgical recoveries.
Notes to accompany the ELG Open Pit mineral resources:
1. Mineral resources for ELG Open Pit are reported above an in-situ cut-off grade of 0.78 gpt Au.
2. Mineral resources were estimated using ID3 methods applied to 1.0 m capped downhole assay composites within lithology domains and internal grade domains. Block model size is 5 m x 5 m x 5m with 2.5 m x 2.5 m x 2.5 m sub-blocks. Mineral resources are reported inside an optimized pit shell, underground mineral reserves at ELD within the El Limón pit shell have been excluded from the open pit mineral resources.
3. Average metallurgical recoveries are 89% Au, 30% Ag, and 15% Cu.
4. The dataset allowed the bulk density to be directly estimated into the domains with an average bulk density of 3.4 g/cm3.
5. ELG Open Pit AuEq = Au (gpt) + (Ag (gpt) * 0.0045) + (Cu (%) * 0.2627), accounting for underlying metal prices and metallurgical recoveries.
ABOUT TOREX GOLD RESOURCES INC.
Torex Gold Resources Inc. is an intermediate gold producer based in Canada, engaged in the exploration, development, and operation of its 100% owned Morelos Property (the "Morelos Property"), an area of 29,000 hectares in the highly prospective Guerrero Gold Belt located 180 kilometres southwest of Mexico City.
The Company's principal asset is the Morelos Complex, which includes the producing Media Luna Underground, ELG Underground, and ELG Open Pit mines, the development stage EPO Underground Project, a processing plant, and related infrastructure. Commercial production from the Morelos Complex commenced on April 1, 2016 and an updated Technical Report for the Morelos Complex was released in March 2022.
Torex's key strategic objectives are: deliver Media Luna to full production and build EPO; optimize Morelos production and costs; grow reserves and resources; disciplined growth and capital allocation; retain and attract best industry talent; and industry leader in responsible mining. In addition to realizing the full potential of the Morelos Property, the Company is seeking opportunities to acquire assets that enable diversification and deliver value to shareholders.
FOR FURTHER INFORMATION, PLEASE CONTACT:
TOREX GOLD RESOURCES INC.
Jody Kuzenko
President and CEO
Direct: (647) 725-9982
jody.kuzenko@torexgold.com
Dan Rollins
Senior Vice President, Corporate Development & Investor Relations
Direct: (647) 260-1503
dan.rollins@torexgold.com
QUALIFIED PERSONS
The scientific and technical data contained in this news release pertaining to mineral resources have been reviewed and approved by Rochelle Collins, P.Geo., Principal, Mineral Resource Geologist with Torex Gold, who is a qualified person as defined by NI 43-101.
The scientific and technical data contained in this news release pertaining to mineral reserves have been reviewed and approved by Johannes (Gertjan) Bekkers, P.Eng., the Vice-President, Mines Technical Services for Torex Gold, who is a qualified person as defined by NI 43-101.
CAUTIONARY NOTES ON FORWARD-LOOKING INFORMATION
This press release contains "forward-looking statements" and "forward-looking information" within the meaning of applicable Canadian securities legislation. Forward-looking information also includes, but is not limited to, statements that: the Company is at the beginning of its transition back to positive free cash flow generation; production is expected to pick up during the second quarter through the early stages of ramp up and increase further through the back half of the year, with annual guidance being maintained; as the Company hits its projected free cash flow inflection point mid-year with completion of Media Luna Project spending, the Company expects to repay the modest amount of debt drawn quickly, particularly as production ramps up under a backdrop of record gold prices; the Company's focus is set on further unlocking value for our shareholders through returning to positive free cash flow, executing its exploration program success across the entire Morelos Property, implementing a formal return of capital policy, delivering on full-year guidance for the seventh consecutive year, and ramping up Media Luna to the designed mining rate by mid-2026; the Company is on track to achieve annual payable production guidance of 400,000 to 450,000 oz AuEq; the Company's exploration strategy is focused, in part, on unlocking the resource potential of the Morelos Complex in order to enhance and extend the production profile; the Company is focused on enhancing the base case production profile beyond 2030, extending the reserve life of the underground deposits, and further showcasing the underlying potential of the broader Morelos Property by testing several regional targets and key strategic objectives are: deliver Media Luna to full production and build EPO; optimize Morelos production and costs; grow reserves and resources; disciplined growth and capital allocation; retain and attract best industry talent; and industry leader in responsible mining. Generally, forward-looking information and statements can be identified by the use of forward-looking terminology such as "forecast," "plans," "expects," or "does not expect," "is expected," "strategic," "to be" or variations of such words and phrases or statements that certain actions, events or results "will", "may," "could," "would," "might," "on track,", or "well positioned to" occur. Forward-looking information is subject to known and unknown risks, uncertainties and other factors that may cause the actual results, level of activity, performance or achievements of the company to be materially different from those expressed or implied by such forward-looking information, including, without limitation, risks and uncertainties identified in the technical report (the "Technical Report") released on March 31, 2022, entitled "NI 43-101 Technical Report ELG Mine Complex Life Of Mine Plan and Media Luna Feasibility Study", which has an effective date of March 16, 2022, and the Company's annual information form ("AIF") and management's discussion and analysis ("MD&A") or other unknown but potentially significant impacts. Forward-looking information and statements are based on the assumptions discussed in the Technical Report, AIF and MD&A and such other reasonable assumptions, estimates, analysis and opinions of management made in light of its experience and perception of trends, current conditions and expected developments, and other factors that management believes are relevant and reasonable in the circumstances at the date such statements are made. Although the company has attempted to identify important factors that could cause actual results to differ materially from those contained in the forward-looking information, there may be other factors that cause results not to be as anticipated. There can be no assurance that such information will prove to be accurate, as actual results and future events could differ materially from those anticipated in such information. Accordingly, readers should not place undue reliance on forward-looking information. The Company does not undertake to update any forward-looking information, whether as a result of new information or future events or otherwise, except as may be required by applicable securities laws. The Technical Report, MD&A and AIF are filed on SEDAR+ at www.sedarplus.ca and available on the Company's website at www.torexgold.com.
To view the source version of this press release, please visit https://www.newsfilecorp.com/release/251143

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Business Wire
an hour ago
- Business Wire
Sherritt Reports Shareholder Meeting Results, Board Appointments and Committee Updates
TORONTO--(BUSINESS WIRE)--Sherritt International Corporation ('Sherritt' or the 'Corporation') (TSX:S) today announced the voting results of its 2025 Annual and Special Meeting of Shareholders held June 10, 2025, the appointment of John Ewing to the Board of Directors (the 'Board'), the appointments of Leon Binedell as Executive Chairman and Shelley Brown as Lead Independent Director, respectively, and other governance updates. 2025 Annual and Special Meeting of Shareholders Voting Results A total of 283,623,833 common shares or 57.15% of Sherritt's issued and outstanding common shares were represented in person or by proxy at the meeting. A majority of the votes were cast in favour of all items of business put forth at the meeting, including the re-appointment of Deloitte LLP as external auditors, amendments to the Corporation's stock option plan and the non-binding advisory resolution known as 'Say on Pay.' Election of Directors Each of the six director nominees standing for election was elected as a director of Sherritt to serve until the next annual general meeting of the company or until his or her successor is elected or appointed: The full Report of Voting Results has been filed on SEDAR+ at Director Appointment and Continued Commitment to Board Renewal To fill the vacancy on the Board resulting from Sir Richard Lapthorne's retirement as announced on June 9, 2025, and consistent with the Corporation's ongoing commitment to good governance and Board renewal, following the meeting, the Board appointed John Ewing, bringing the total number of directors to seven. A biography for Mr. Ewing is provided below. The Board intends to continue the Board renewal process with the appointment of at least one additional independent director, preferably with mining engineering expertise and the potential to assume a leadership position on the Board, by December 31, 2025. All directors are independent within the meaning of applicable securities laws, other than Leon Binedell who also serves as President and CEO of the Corporation. John Ewing is the nominee of Sherritt shareholder Ewing Morris & Co. Investment Partners Ltd. ('Ewing Morris'), and Richard Moat is the nominee of Sherritt shareholder Kyma Capital Limited. Board Leadership and Committee Updates In connection with the reconstitution of the Board, the Corporation announces that Leon Binedell has been appointed Executive Chairman, following the retirement of former Chairman Sir Richard Lapthorne. Shelley Brown, an independent director of Sherritt since August 2024, has been named Lead Independent Director. The Board committees have also been reconstituted to better align with the expertise of the new directors, including the appointment of Mr. Ewing to the Reserves, Operations and Capital Committee and Mr. Moat to the Audit Committee. Additionally, the former HR Committee and the former Nominating and Corporate Governance Committee have been consolidated into a single committee. This streamlining reflects the Corporation's commitment to enhancing Board efficiency, while reducing management's administrative burden to support a greater focus on operational priorities. Sherritt shareholders SC2 Inc. ('SC2') and Ewing Morris have expressed their alignment with the Corporation's ongoing Board renewal process and have committed to supporting Sherritt's director nominees through the 2026 annual meeting of shareholders. 'I believe in Sherritt's potential,' said John Ewing, Sherritt Director and Co-Founder of Ewing Morris. 'I look forward to collaborating with my colleagues on the Board to help Sherritt achieve new milestones and deliver long-term value for all stakeholders.' 'We are encouraged with the progress in Sherritt's Board renewal process,' said Casey McKenzie, President, SC2. 'We recognize the Corporation's potential and look forward to supporting management in driving continued improvements in performance.' Leon Binedell, Sherritt Executive Chairman added: 'On behalf of Sherritt, I would like to thank Ewing Morris, SC2, and our broader shareholder base for their engagement and ongoing support. In addition, Sherritt and Seablinc look forward to re-establishing a normal commercial relationship. Over the past few years, we have worked with determination to position Sherritt for sustainable growth and value creation. I am confident that John will make valuable contributions to the Board and the Corporation as we continue to strengthen and build upon this foundation.' About John Ewing Mr. Ewing is Chief Investment Officer of Ewing Morris & Co. Investment Partners. He co-founded the firm in June 2011 with Darcy Morris. Mr. Ewing graduated with distinction from the University of Guelph with an Honours Bachelor of Science in Engineering degree and a Minor in Business Administration. About Sherritt Sherritt is a world leader in using hydrometallurgical processes to mine and refine nickel and cobalt – metals deemed critical for the energy transition. Sherritt's Moa Joint Venture has an estimated mine life of approximately 25 years and is advancing an expansion program focused on increasing annual MSP production by 20% of contained nickel and cobalt. The Corporation's Power division, through its ownership in Energas, is the largest independent energy producer in Cuba with installed electrical generating capacity of 506 MW, representing approximately 10% of the national electrical generating capacity in Cuba. The Energas facilities are comprised of two combined cycle plants that produce low-cost electricity from one of the lowest carbon emitting sources of power in Cuba. Sherritt's common shares are listed on the Toronto Stock Exchange under the symbol 'S'. FORWARD-LOOKING STATEMENTS Certain statements and other information included in this press release constitute 'forward-looking information' or 'forward-looking statements' (collectively, 'forward-looking statements') under applicable securities laws (such statements are often accompanied by words such as 'anticipate', 'forecast', 'expect', 'believe', 'may', 'will', 'should', 'estimate', 'intend' or other similar words). All statements in this press release, other than those relating to historical information, are forward-looking statements, including, but not limited statements regarding strategies, plans and estimated production amounts resulting from expansion of mining operations at the Moa Joint Venture. The Corporation cautions readers of this press release not to place undue reliance on any forward-looking statement as a number of factors could cause actual future results, conditions, actions or events to differ materially from the targets, expectations, estimates or intentions expressed in the forward-looking statements. The key risks and uncertainties should be considered in conjunction with the risk factors described in the Corporation's other documents filed with the Canadian securities authorities, including without limitation the 'Managing Risk' section of the Management's Discussion and Analysis for the three months ended March 31, 2025 and the Annual Information Form of the Corporation dated March 24, 2025 for the period ending December 31, 2024, which is available on SEDAR+ at The forward-looking information and statements contained in this press release are made as of the date hereof and the Corporation undertakes no obligation to update publicly or revise any oral or written forward-looking information or statements, whether as a result of new information, future events or otherwise, except as required by applicable securities laws. The forward-looking information and statements contained herein are expressly qualified in their entirety by this cautionary statement.
Yahoo
2 hours ago
- Yahoo
Global Uranium Corp. Announces LIFE Offering for up to C$1,500,000
NOT FOR DISTRIBUTION TO UNITED STATES NEWSWIRE SERVICES OR FOR DISSEMINATION IN THE UNITED STATES VANCOUVER, British Columbia, June 10, 2025 (GLOBE NEWSWIRE) -- Global Uranium Corp. (CSE: GURN | FRA: Q3J) (the 'Company') is pleased to announce that it intends to complete a non-brokered private placement financing (the 'Offering') of a minimum of 1,666,666 units of the Company (each, a 'Unit') and a maximum of 10,000,000 Units, at a price of C$0.15 per Unit, for gross minimum proceeds of C$250,000 and gross maximum proceeds of C$1,500,000. Each Unit shall be comprised of one common share in the capital of the Company (each, a 'Share') and one Share purchase warrant ('Warrant'), with each Warrant entitling the holder to purchase one Share at a price of C$0.20 for a period of 24 months from Closing (as defined herein). Closing of the Offering is anticipated to occur on or about July 25, 2025 ('Closing'), subject to the satisfaction of certain conditions, including, but not limited to, the receipt of all necessary regulatory and other approvals. The net proceeds of the Offering are intended to be used for exploration activities, for general administrative expenditures, and for general working capital purposes. Subject to compliance with applicable regulatory requirements and in accordance with National Instrument 45-106 – Prospectus Exemptions ('NI 45-106'), the securities issuable under the Offering will be offered for sale to purchasers resident in all of the provinces of Canada (except Quebec) pursuant to the listed issuer financing exemption under Part 5A.2 of NI 45-106 (the 'LIFE Exemption'). As such, the securities issued to subscribers will not be subject to resale restrictions in accordance with applicable Canadian securities laws. There is an offering document dated June 10, 2025 related to the Offering that can be accessed under the Company's profile at and on the Company's website at This offering document contains additional detail regarding the Offering, including additional detail regarding the expected use of proceeds therefrom. Prospective investors in the Offering should read this offering document before making an investment decision. The securities described herein have not been and will not be registered under the United States Securities Act of 1933, as amended (the 'U.S. Securities Act'), or any United States state securities laws, and may not be offered or sold in the United States or to, or for the account or benefit of, United States persons absent registration or any available exemption from the registration requirements of the U.S. Securities Act and applicable United States state securities laws. This press release does not constitute an offer to sell or a solicitation of an offer to buy nor shall there be any sale of the securities in any jurisdiction in which such offer, solicitation or sale would be unlawful. ABOUT GLOBAL URANIUM CORP. Global Uranium Corp. focuses on exploring and developing uranium assets primarily in North America. The Company currently holds key uranium projects: the Wing Lake Property in the Mudjatik Domain of Northern Saskatchewan, Canada; the Northwest Athabasca Joint Venture with Forum Energy Metals Corp. and NexGen Energy Ltd. in the Northwest Athabasca region of Saskatchewan, Canada; the Astro Uranium Project with Cosa Resources Corp in the eastern Athabasca Basin, Saskatchewan; and the Great Divide Basin District Projects, the Gas Hills District Projects, and the Copper Mountain District Projects in Wyoming, USA. ON BEHALF OF THE BOARD OF DIRECTORSUngad ChaddaCEO 587-330-0045info@ FORWARD-LOOKING STATEMENTS Certain statements contained in this press release constitute forward-looking information. These statements relate to future events or future performance. The use of any of the words 'could', 'intend', 'expect', 'believe', 'will', 'projected', 'estimated' and similar expressions and statements relating to matters that are not historical facts are intended to identify forward-looking information and are based on the Company's current belief or assumptions as to the outcome and timing of such future events. In particular, this press release contains forward-looking information relating to, among other things, the Offering, including the total anticipated proceeds, the expected use of proceeds, and the closing (including the proposed closing date) of the Offering. Various assumptions or factors are typically applied in drawing conclusions or making the forecasts or projections set out in forward-looking information, including the assumption that the Company will close the Offering on the timeline anticipated, will raise the anticipated amount of gross proceeds from the Offering and will use the proceeds of the Offering as anticipated. Those assumptions and factors are based on information currently available to the Company. Although such statements are based on reasonable assumptions of the Company's management, there can be no assurance that any conclusions or forecasts will prove to be accurate. Forward-looking information involves known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements to be materially different from any future results, performance or achievements expressed or implied by the forward-looking information. Such factors include: the risk that the Offering does not close on the timeline expected, or at all; the risk that the Company raises less than the anticipated amount of gross proceeds from the Offering; the risk that the Company does not use the proceeds from the Offering as currently expected; risks inherent in the exploration and development of mineral deposits, including risks relating to receiving requisite permits and approvals, changes in project parameters or delays as plans continue to be redefined, that mineral exploration is inherently uncertain and that the results of mineral exploration may not be indicative of the actual geology or mineralization of a project; that mineral exploration may be unsuccessful or fail to achieve the results anticipated by the Company; operational risks; regulatory risks, including risks relating to the acquisition of the necessary licenses and permits; financing, capitalization and liquidity risks; title and environmental risks; and risks relating to the failure to receive all requisite regulatory approvals. The forward-looking information contained in this release is made as of the date hereof, and the Company is not obligated to update or revise any forward-looking information, whether as a result of new information, future events or otherwise, except as required by applicable securities laws. Because of the risks, uncertainties and assumptions contained herein, investors should not place undue reliance on forward-looking information. The foregoing statements expressly qualify any forward-looking information contained herein. The Canadian Securities Exchange has not reviewed, approved, or disapproved the contents of this press release.Error in retrieving data Sign in to access your portfolio Error in retrieving data Error in retrieving data Error in retrieving data Error in retrieving data
Yahoo
2 hours ago
- Yahoo
Prime Drink Group Provides an Update on Its Bottling Subsidiary Receivership
MONTREAL, June 10, 2025 (GLOBE NEWSWIRE) -- Prime Drink Group Corp. (CSE: PRME) ('Prime' or the 'Company') announces that its bottling subsidiary, formerly known as Triani Canada Inc. ('Triani'), has been placed into receivership and has ceased operations. Triani's receivership was ordered on June 10, 2025, by the Superior Court, District of Montreal, at the request of Triani's principal creditors pursuant to Section 243 of the Bankruptcy and Insolvency Act (Canada), as disclosed in the Company's press release dated April 7, 2025. The Company wishes to clarify that the parent company, Prime Drink Group Corp., and all of its other subsidiaries are not subject to this receivership. Ownership of the freshwater rights is segregated from Triani, and operations are continuing. Consistent with its objective of resuming growth of its business and brands, Prime is currently evaluating several options, including its intention to submit an offer to the principal creditors to acquire certain strategic assets of Triani. In addition, the Company is considering other avenues of recourse with respect to Triani and the various stakeholders. 'The receivership of Triani a few months after its acquisition puts us in a challenging situation but our resolve and vision remain unwavering. It is our intention to fight to recover what is owed to Prime and to continue developing our valuable strategic water and beverage assets. We are fortunate to have an experienced team in innovation, brand strategy and marketing that will be able to leverage Prime's assets for the benefit of our shareholders and come out stronger,' said Olivier Primeau, VP Marketing, Strategic Vision and Acquisitions at Prime. The Company reaffirms its commitment to the responsible development of its water resources in Québec. Discussions with government authorities are progressing well. Prime also wishes to announce the appointment of Jean Gosselin as Chief Financial Officer of the Company. Jean has over 40 years of experience in finance and operations and previously served as Vice President of Finance and Corporate Secretary of Prime. About Prime Drink Group Prime Drink Group Corp (CSE: PRME) is a Québec-based corporation focused on becoming a leading diversified holding company in the beverage, influencer media and hospitality sectors. For further information, please contact: Jean Gosselin, CFOPhone: (514) 394-7717 Email: info@ This press release contains 'forward-looking information' within the meaning of applicable Canadian securities legislation. Generally, forward-looking information can be identified by the use of forward-looking terminology such as 'plans', 'expects' or 'does not expect', 'is expected', 'budget', 'scheduled', 'estimates', 'forecasts', 'intends', 'anticipates' or 'does not anticipate', or 'believes', or variations (including negative and grammatical variations) of such words and phrases or statements that certain acts, events or results 'may', 'could', 'would', 'might' or 'will be taken', 'occur' or 'be achieved'. Forward-looking information in this press release may include, without limitation, statements relating to the receivership and the Company's intentions with respect to recovering Triani from receivership. These statements are based upon assumptions that are subject to significant risks and uncertainties, including risks regarding the beverage industry, market conditions, availability of financing to the Company on acceptable terms, general economic factors, and the equity markets generally. Because of these risks and uncertainties and as a result of a variety of factors, the actual results, expectations, achievements or performance of Prime may differ materially from those anticipated and indicated by these forward-looking statements. Any number of factors could cause actual results to differ materially from these forward-looking statements as well as future results. Although Prime believes that the expectations reflected in forward-looking statements are reasonable, they can give no assurances that the expectations of any forward-looking statements will prove to be correct. Except as required by law, Prime disclaims any intention and assumes no obligation to update or revise any forward-looking statements to reflect actual results, whether as a result of new information, future events, changes in assumptions, changes in factors affecting such forward-looking statements or otherwise. Error in retrieving data Sign in to access your portfolio Error in retrieving data Error in retrieving data Error in retrieving data Error in retrieving data