
Early onset of monsoon catches GHMC off guard
The Greater Hyderabad Municipal Corporation's monsoon preparatory work is wanting in a number of aspects, while the authorities blame the early monsoons for the predicament.
Long stretches of roads are still dug up or not re-laid after being filled, posing danger for commuters. Nala de-silting is a half-completed job with the excavated silt heaped on the roadside at several locations. Widening of the stormwater drain has not been finished at several locations, and open drains continue to pose grave danger.
Trenches dug for various works still lie open near Mehdipatnam foot overbridge, the Fort Road in Gudimalkapur, Road No.1, Banjara Hills and several other areas.
'The stretch from Virinchi Hospitals up to the Taj Krishna junction has been dug up for nearly two months., which has reduced the road width considerably leading to traffic issues. The restoration works have started only recently, after the monsoons have arrived, and the works are the cause of traffic snarls now,' shared Shafiur Rehman, a local resident.
Restoration works have not even started on the stretch between Mecca Colony and Anas Model School in Tadban near Shamseergunj where the road was dug up for stormwater drain works.
One more infamous instance is the road that passes via Qutb Shahi Tombs, a heritage complex and tourist location. The road remains dug up for years, say the residents of the surrounding colonies.
'Fun fact: A friend's kid was born when the Seven Tombs roadwork started. That kid is now going to kindergarten. Meanwhile, the road is still a crater-filled warzone. Time moves on. GHMC? Not so much,' posted one Muzaffar on social media platform X, in a long thread about the road's condition.
At several other locations such as Chintalkunta, Jubilee Hills, and Serilingampally the trenches dug up for sewerage works have been filled up, but restoration works have not been taken up so far.
GHMC is the sole authority to grant road cutting permissions to all agencies, whether private or public. The corporation collects road cutting charges from the utilities, so that the road can be restored after the work is finished.
Officials in charge admit that there was inordinate delay in granting the road cutting permissions this time, due to hiccups in work redistribution in the Engineering wing. The works which were to begin in November, began towards the end of January. Added to it is the early arrival of monsoons, which were not expected till June-end.
'To the field level Engineering officials, we gave time up to June 10 to wrap up the pending works and make the roads motorable. Our teams are on the job,' assures a senior official.
Part of the reason is also the transition from the agencies to which the Comprehensive Road Maintenance works were granted. During their five year stint, the CRMP agencies were authorised for granting the road cutting permissions on several major stretches, and also were responsible for restoration works.
Desilting
While GHMC has awarded tenders for desilting of stormwater drains much ahead of time, the work done is hardly enough to withstand one bountiful rain, as proven in case of Chandanagar area, which was flooded after Tuesday's rain.
Commissioner of the Hyderabad Disaster Response and Asset Protection Agency, A.V.Ranganath who inspected the drain near the Lingampally Road Under Bridge (RUB), noted that the drain was clogged completely by volumes of garbage. HYDRAA forces had to be instructed to clear the trash and facilitate free flow of water.
'Silt was piled up by the drain at Aramghar crossroads, but not removed immediately. With one rain, all the silt would be back in the drain, along with the public funds spent on the work,' fumes a resident.
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Hans India
3 days ago
- Hans India
Expedite drainage works ahead of monsoon: GHMC chief
Hyderabad: As a part of monsoon preparedness, GHMC Commissioner RV Karnan on Friday instructed officials to expedite drain works promptly ensuring the public experiences no inconvenience. He inspected drain works in the Santoshnagar Circle, Charminar zone. He was accompanied by Yakutpura MLA Jaffar Hussain Meraj, MLC Mirza Riaz-ul-Hasan Effendi and officers from different departments. The main purpose of the inspection was to tackle overflow issues caused by interconnected nalas and sewage lines. The officials inspected Maula Ka Chilla, Ganganagar nala and others. Proposals are being prepared to submit to the corporation. The aim is to resolve overflow issue, particularly at Rangeeli Khidki, near Rahmania Madarsa. Jaffar Hussain detailed the challenges the residents of colonies experience due to the drains. EE BL Srinivas informed the commissioner that repair to Ganganagar nala was 70 per cent completed. Karnan instructed the project officer to expedite the work as soon as possible. As the water pipeline runs parallel to both sides of the Ganganagar nala, the GHMC maintenance engineering wing, along with the Water Board officials, has been directed to collaborate on its cleaning. The necessity for building a drainage canal from Jahangir Nagar Colony to Maula Ka Chilla nala was communicated to the commissioner; engineering officials were tasked with drafting proposals. During the visit they discussed the upcoming Moharram routes and maintenance of Ashurkhaanas. Karnan souoght proposals, assuring immediate sanction of work to ensure all preparations are in place.


New Indian Express
4 days ago
- New Indian Express
GHMC halts new cellar excavations from May 30
HYDERABAD: In view of the monsoon setting in, the Greater Hyderabad Municipal Corporation will not allow any new cellar excavations from May 30, 2025, until the end of the season. For cellars already excavated, notices will be served to builders and site owners, instructing them to implement standard precautionary measures, including soil strengthening, construction of retaining walls, proper barricading, and prevention of water stagnation. Officials have also been directed to complete the survey and take action in accordance with the Standard Operating Procedures (SOPs). A review meeting in this regard was held on Thursday by GHMC Commissioner RV Karnan and Chief City Planner Srinivas with Town Planning officials from the head office, zonal offices and circle offices. 428 dilapidated structures identified According to GHMC officials, 428 dilapidated structures and 62 cellar excavations have been identified so far. Of the 428 structures, action such as repairs or vacation has been completed for 131. The remaining 297 structures are under follow-up, including issuance of notices, assessment of structural safety and counselling of owners for vacation.


The Hindu
5 days ago
- The Hindu
148 years after it was built, Hyderabad's James Street Police Station gets a new lease of life
148 years after it was built, the iconic James Street Police Station with its soaring belfry, clock and louver windows that came to be known as Ramgopalpet Police Station, has got a fresh lease of life. Lit up with an off white light, the street offers a glimpse of life in Secunderabad as it was in the colonial era. 'We researched using archival material and photographs to ensure that the geometrical similarity, form, colour, original features, and built components, including the Palladian pediment and semi-circular arches of the building are restored to the original form,' said conservation architect Surya Narayan Murthy when asked about the restoration. 'It took us 14 months to execute the project as the building had suffered extensive damage with deterioration of lime plaster, which in turn harmed the wooden rafters due to water seepage and moisture,' says Mir Khan of Deccan Terrain who carried out the restoration work. 'The wooden rafters had to be replaced, the 20th century cement plastering intervention had to be undone. The seepage affected the madras terrace (built using terracotta tiles and lime mortar) as well as the jack arch roofing,' informs Mr. Khan. Prior to the restoration, the Greater Hyderabad Municipal Corporation had asked the Hyderabad Police to vacate the building in 2016 citing its dilapidated condition. The building was designated a heritage building in 1998 and the police department had a plan to turn into a museum. Now that goal appears closer as the 400-kg brass bell in the belfry has been taken down and kept on the ground floor as an attraction. 'The police department has a plan to use it as an outpost or turn it into a museum,' informed Mr. Khan. The James Street Police Station named after the Resident James Kirkpatrick was financed by the businessman Seth Ramgopal who had his home in the same street. While the home is built with influence from Rajasthani architecture, the police station had an air of a colonial building.