Eskom to pay R1 billion penalty over Koeberg steam generator dispute

Eskom to pay R1 billion penalty over Koeberg steam generator dispute

IOL News21-07-2025
Eskom has been ordered to pay French company Framatome almost R1 billion by the Western Cape High Court in a contractual dispute over the replacement of steam generators at the Koeberg Power Station.
Image: Supplied
Power utility Eskom must pay French nuclear power company Framatome nearly R1 billion in a contractual dispute over the replacement of steam generators at the Koeberg Nuclear Power Station.
Eskom hauled the company formerly known as Areva to the Western Cape High Court to challenge adjudicator Peter Ramsden's decisions on the merits and the quantum delivered in December 2022 and March 2023, respectively.
The entity's contention was that both decisions were beyond his jurisdiction and failed to apply the rules of natural justice.
Eskom complained that Ramsden failed to take into account its submissions, issue a reasoned decision and decide the issues that he was required to decide.
Video Player is loading.
Play Video
Play
Unmute
Current Time
0:00
/
Duration
-:-
Loaded :
0%
Stream Type LIVE
Seek to live, currently behind live
LIVE
Remaining Time
-
0:00
This is a modal window.
Beginning of dialog window. Escape will cancel and close the window.
Text Color White Black Red Green Blue Yellow Magenta Cyan
Transparency Opaque Semi-Transparent Background Color Black White Red Green Blue Yellow Magenta Cyan
Transparency Opaque Semi-Transparent Transparent Window Color Black White Red Green Blue Yellow Magenta Cyan
Transparency Transparent Semi-Transparent Opaque
Font Size 50% 75% 100% 125% 150% 175% 200% 300% 400% Text Edge Style None Raised Depressed Uniform Dropshadow Font Family Proportional Sans-Serif Monospace Sans-Serif Proportional Serif Monospace Serif Casual Script Small Caps
Reset
restore all settings to the default values Done
Close Modal Dialog
End of dialog window.
Advertisement
Video Player is loading.
Play Video
Play
Unmute
Current Time
0:00
/
Duration
-:-
Loaded :
0%
Stream Type LIVE
Seek to live, currently behind live
LIVE
Remaining Time
-
0:00
This is a modal window.
Beginning of dialog window. Escape will cancel and close the window.
Text Color White Black Red Green Blue Yellow Magenta Cyan
Transparency Opaque Semi-Transparent Background Color Black White Red Green Blue Yellow Magenta Cyan
Transparency Opaque Semi-Transparent Transparent Window Color Black White Red Green Blue Yellow Magenta Cyan
Transparency Transparent Semi-Transparent Opaque
Font Size 50% 75% 100% 125% 150% 175% 200% 300% 400% Text Edge Style None Raised Depressed Uniform Dropshadow Font Family Proportional Sans-Serif Monospace Sans-Serif Proportional Serif Monospace Serif Casual Script Small Caps
Reset
restore all settings to the default values Done
Close Modal Dialog
End of dialog window.
Next
Stay
Close ✕
In addition, Eskom stated that the adjudicator failed to receive and take into account its response to Framatome's amended claim as well as its submissions when determining the quantum.
Eskom was also unhappy that the adjudicator accepted the amounts in the company's amended claim without having enquired into the supporting documents or the details of the claim, failed to issue a reasoned decision and/or follow the procedure he laid down by himself.
The dispute dates back to 2014 when the parties concluded an agreement to replace the steam generators at Koeberg.
In terms of the contract, Framatome work included the supply and installation of two sets of three replacement steam generators, with one set to be installed in each of the reactor buildings at units one and two at Koeberg during their separate planned outages.
The work of replacing the steam generators can only be performed during maintenance and refuelling outages when the power station is offline and the outages are planned in advance and around Eskom's operational requirements.
Eskom had scheduled the outage dates and planned to replace the steam generators but then twice postponed for a later date.
The power utility then informed Framatome that it would not be continuing with the steam generator replacement work during one of the outages.
However, the company notified Eskom of an event which required it to notify the power supplier of such an event and that it required compensation after the postponement. This was acknowledged by the project manager.
Eskom then unsuccessfully approached the adjudicator, claiming that both decisions were unenforceable as contractual obligations and need not be complied with as he exceeded his powers.
It later filed an application for several declarators, which acting Judge Renata Williams dismissed with costs on Thursday.
Framatome succeeded in its counter-application and Eskom was ordered to pay the company €35,288,582 (about R729 million) exclusive of value-added tax (VAT) and subject to the price adjustment for inflation pursuant to secondary option clause of the contract.
Payment is also pursuant to certain clauses of the contract, interest thereon calculated at the London Interbank Offered Rate applicable at the time for amounts due in other currencies
Additionally, Eskom must pay Framatome more than R256.6m exclusive of VAT and subject to the price adjustment for inflation pursuant to secondary option clause of the contract and pursuant to certain clauses including interest.
The power utility was also ordered to pay the costs of Framatome's counter application including the costs of the company's France-based attorneys.
'There is no basis to set aside the decisions of the adjudicator which are valid and binding. In terms of the parties' contract Eskom was obliged to comply therewith,' acting Judge Williams ruled.
Eskom spokesperson Daphney Mokwena did not respond to requests for comment on Saturday.
Cape Times
Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Hope for change: Msunduzi ratepayers welcome Simon Mndebele's leadership
Hope for change: Msunduzi ratepayers welcome Simon Mndebele's leadership

IOL News

time2 hours ago

  • IOL News

Hope for change: Msunduzi ratepayers welcome Simon Mndebele's leadership

Msunduzi Municipality Manager, Simon Mndebele and Mzimkhulu Thebolla, Mayor of Msunduzi. Image: Msunduzi Municipality Msunduzi Municipality ratepayer associations are looking forward to a fresh and effective approach from new municipal manager Simon Mndebele to turn the city's fortunes around. Mndebele, who was appointed as the manager on Friday, was described by Mzimkhulu Thebolla, Msunduzi's mayor, as pivotal to reposition Msunduzi as a municipality that is responsive, financially stable, and people-centred. Mndebele previously served as a technical support expert for Msunduzi Municipality, deployed by the KwaZulu-Natal Department of Cooperative Governance and Traditional Affairs (COGTA). Mndebele also served as municipal manager at Govan Mbeki Local Municipality and director in its Corporate Services department at Chief Albert Luthuli Municipality. 'In this capacity, he led the development of the municipality's turnaround strategy, conducted diagnostic analyses, and helped establish critical performance oversight structures. His in-depth knowledge of Msunduzi's operational landscape provides a solid foundation for decisive leadership from day one,' Thebolla said. Video Player is loading. Play Video Play Unmute Current Time 0:00 / Duration -:- Loaded : 0% Stream Type LIVE Seek to live, currently behind live LIVE Remaining Time - 0:00 This is a modal window. Beginning of dialog window. Escape will cancel and close the window. Text Color White Black Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Background Color Black White Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Transparent Window Color Black White Red Green Blue Yellow Magenta Cyan Transparency Transparent Semi-Transparent Opaque Font Size 50% 75% 100% 125% 150% 175% 200% 300% 400% Text Edge Style None Raised Depressed Uniform Dropshadow Font Family Proportional Sans-Serif Monospace Sans-Serif Proportional Serif Monospace Serif Casual Script Small Caps Reset restore all settings to the default values Done Close Modal Dialog End of dialog window. Advertisement Video Player is loading. Play Video Play Unmute Current Time 0:00 / Duration -:- Loaded : 0% Stream Type LIVE Seek to live, currently behind live LIVE Remaining Time - 0:00 This is a modal window. Beginning of dialog window. Escape will cancel and close the window. Text Color White Black Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Background Color Black White Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Transparent Window Color Black White Red Green Blue Yellow Magenta Cyan Transparency Transparent Semi-Transparent Opaque Font Size 50% 75% 100% 125% 150% 175% 200% 300% 400% Text Edge Style None Raised Depressed Uniform Dropshadow Font Family Proportional Sans-Serif Monospace Sans-Serif Proportional Serif Monospace Serif Casual Script Small Caps Reset restore all settings to the default values Done Close Modal Dialog End of dialog window. Next Stay Close ✕ He added that with his leadership, Msunduzi aims to fast-track infrastructure development, improve basic services, strengthen financial controls, and restore institutional stability. Thebolla called upon all stakeholders to rally behind Mndebele and support his mission to lead a clean, capable, and service-driven administration. Jimmy Naidoo, chairperson of the Northern Areas Residents and Ratepayers Association (NARRA), stated that over the years, they have not had a municipal manager who has completed their term or addressed the core challenges that ratepayers face—particularly those related to billing systems, policy implementation, and credit control. 'We are hopeful that the newly appointed manager will take decisive and aggressive steps to fix the ongoing issues in the billing cycle. It is also crucial that accountability is enforced and that there are clear consequences for non-performance across all departments. We look forward to seeing whether he will bring a fresh and effective approach—one that finally delivers where others have fallen short,' Naidoo said. Msunduzi Association of Residents, Ratepayers and Civics (MARRC) CEO Anthony Waldhausen is concerned that the Govan Mbeki municipality was issued with a disclaimer notice for three financial periods from 2017/2018, 2018/2019, and 2019/2020 by the Auditor General. Waldhausen stated that Msunduzi had a revolving door where municipal managers have not served their full terms of office. 'Did the selection committee for the municipal manager conduct a thorough due diligence report to ensure that no other red flags were missed? Since 2010, we have had over five municipal managers, some left with a cloud over their heads from supposed suspension, and then to have the suspension overturned or withdrawn,' Waldhausen said. Waldhausen called for a professional, effective, and competent municipal workforce that can provide service delivery and development to the citizens of Pietermaritzburg, but it must be free from any form of political interference and internal factionalism. The MARRC stated that they would work with Mndebele to turn the fortunes of Pietermaritzburg around for the better. 'We call on the mayor and council to allow the municipal manager to do his job without fear and favour,' said Waldhausen. Waldhausen said that MARRC submitted a discussion document on the White Paper on Local Government, calling for an overhaul of local government. 'One of the suggestions is to make the selection and appointment of the municipal manager and senior management positions to be done in the public space, and to have the selection and appointment of the municipal manager and senior management positions conducted in the public space,' he said.

Book review- A new era for State-Owned Enterprises: Dr Nimrod Mbele's blueprint for change
Book review- A new era for State-Owned Enterprises: Dr Nimrod Mbele's blueprint for change

IOL News

time3 hours ago

  • IOL News

Book review- A new era for State-Owned Enterprises: Dr Nimrod Mbele's blueprint for change

Dr Nimrod Mbele agues that affirmative action take South Africa back in his new book Reimagining State-Owned Enterprises For Africa and Beyond Image: supplied In a landscape riddled with governance failures, Reimagined SOEs in Africa and Beyond emerges not from frustration, but from a profound sense of hope. Author Dr Nimrod Mbele, whose journey from the township of Thokoza profoundly shapes his perspective, presents a powerful diagnostic and blueprint for transforming State Owned Enterprises (SOEs) across Africa. His inspiration is deeply rooted in a decade of firsthand observation—engaging with boardrooms, public institutions, and media, all while witnessing the persistent governance failures plaguing SOEs. Yet, this experience didn't lead to despair. Instead, it ignited a conviction that reform is possible if governance is reframed "not as compliance, but as a leadership system rooted in public value." 'South Africa must shift from leader-centric to leadership-centric systems - where performance is not dependent on individual personalities but institutionalised within strong, accountable structures. 'This requires reinforcing board independence, implementing merit-based appointments, instituting clear performance compacts, and establishing a capable and credible State Holding Company to ensure strategic coherence and protect SOEs from political interference,' Mbele said. This central message, to "go beyond governance" toward institutional integrity, developmental purpose, and democratic accountability, is the driving force behind the book. 'Moreover, strategic SOEs like Eskom, SAA, and Transnet should operate on a commercial basis, with clearly defined mandates. 'Their profits should be reinvested into the national fiscus to support essential social objectives such as education, healthcare and social security. 'Persisting with outdated ideological approaches only entrenches inefficiency and deepens the financial reliance of SOEs on the fiscus, an unsustainable model, especially in a context where the economy has grown at less than 2% over the past decade. Reimagining SOEs is, therefore, not only about governance reform but also about restoring both public trust and institutional capability,' Mbele said. His Thokoza upbringing, marked by systemic challenges like under-resourced schools and weak service delivery, provides a critical lens. Mbele witnessed how dysfunctional institutions deepen inequality and erode hope, fueling his belief that reform transcends mere policy or structure. 'My journey from Thokoza, a township shaped by struggle and resilience, to becoming a thought leader in governance profoundly informs my perspective on institutional reform. Growing up amidst systemic challenges - under-resourced schools, weak service delivery, and socio-economic hardships. 'I witnessed firsthand how dysfunctional institutions deepen inequality and erode hope. This lived experience fuels my conviction that reform is not just about policy or structure, but about restoring trust, dignity, and accountability in public institutions. Institutional reform must be people-centered, prioritising transparency, ethical leadership and inclusive participation to break cycles of exclusion,' he said. For him, it's about "restoring trust, dignity, and accountability in public institutions." This lived experience, coupled with insights from consulting, academia, and broadcasting, culminates in a strategic agenda for renewal that bridges personal narrative, rigorous research, and public dialogue. Mbele's advocacy for "governance that is accessible and responsive" underscores his commitment to ensuring institutions serve all citizens, especially those from historically marginalised communities. This empathetic approach, combined with a demand for technical excellence, forms the bedrock of his vision for sustainable SOE reform. The book is, at its core, a testament to the author's unwavering conviction that African SOEs can and must be instruments of transformation, not political patronage. [email protected]

Why South African taxpayers should double-check their auto-assessments
Why South African taxpayers should double-check their auto-assessments

IOL News

time4 hours ago

  • IOL News

Why South African taxpayers should double-check their auto-assessments

Tax With millions of South Africans auto-assessed by Sars in 2024, financial experts warn of potential errors that could cost taxpayers. Discover how to ensure your auto-assessment is accurate and avoid costly mistakes. Image: Freepik Millions of South Africans were auto-assessed by the South African Revenue Service (Sars) in 2024, a move designed to simplify the tax season. But with convenience comes risk. Financial experts warn that auto-assessments, which rely solely on third-party data, can contain critical errors that might cost taxpayers dearly if left unchecked. According to Procompare, an online platform that connects South Africans with local professionals, Sars auto-assessed around 3.5 million individuals in 2024, nearly half of the country's tax base. The process draws on pre-submitted data from employers, banks, medical aids, and retirement fund administrators to estimate a taxpayer's return, but the estimation isn't always spot on, it says. Procompare says errors may include omitted income, overlooked deductions, or incorrectly reported figures. "An auto-assessment can be convenient if your tax affairs are simple, but don't assume it's 100% correct," says Adriana Taljaard of AT Accounting & Taxation Solutions, an accountant affiliated with Procompare. Video Player is loading. Play Video Play Unmute Current Time 0:00 / Duration -:- Loaded : 0% Stream Type LIVE Seek to live, currently behind live LIVE Remaining Time - 0:00 This is a modal window. Beginning of dialog window. Escape will cancel and close the window. Text Color White Black Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Background Color Black White Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Transparent Window Color Black White Red Green Blue Yellow Magenta Cyan Transparency Transparent Semi-Transparent Opaque Font Size 50% 75% 100% 125% 150% 175% 200% 300% 400% Text Edge Style None Raised Depressed Uniform Dropshadow Font Family Proportional Sans-Serif Monospace Sans-Serif Proportional Serif Monospace Serif Casual Script Small Caps Reset restore all settings to the default values Done Close Modal Dialog End of dialog window. Advertisement Video Player is loading. Play Video Play Unmute Current Time 0:00 / Duration -:- Loaded : 0% Stream Type LIVE Seek to live, currently behind live LIVE Remaining Time - 0:00 This is a modal window. Beginning of dialog window. Escape will cancel and close the window. Text Color White Black Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Background Color Black White Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Transparent Window Color Black White Red Green Blue Yellow Magenta Cyan Transparency Transparent Semi-Transparent Opaque Font Size 50% 75% 100% 125% 150% 175% 200% 300% 400% Text Edge Style None Raised Depressed Uniform Dropshadow Font Family Proportional Sans-Serif Monospace Sans-Serif Proportional Serif Monospace Serif Casual Script Small Caps Reset restore all settings to the default values Done Close Modal Dialog End of dialog window. Next Stay Close ✕ Tax experts list several common pitfalls with Sars auto-assessments: Incomplete or missing third-party data : If employers or financial institutions delay or fail to submit information, key income or deductions won't reflect in the auto-assessment. Incorrect reporting : Errors from banks, medical schemes, or other entities can result in Sars populating incorrect figures. Exclusions of non-standard deductions : Expenses such as home office costs, travel allowances, charitable donations, and unreimbursed medical expenses are not included unless captured by third parties. Undeclared personal income streams : Rental earnings, freelance work, or side businesses not reported to Sa rs wo n't feat ure in auto-calculations, potentially leading to under-reporti ng. Taljaard says Sars itself cautions that there 'might be some income sources and certainly expenses... of which Sars may not be aware', reinforcing the need for taxpayers to validate their data. "For the additional income, a P&L must be compiled in order to submit the profits or losses that the additional source of income," advises Rushaan Toefy, owner of Rushaan Toefy Financial Services in Cape Town. "As for the travel allowance, a complete logbook detailing must be provided in order for Sars to account for the extra tax savings." Procompare says if you suspect your auto-assessment may be flawed, prompt action is essential. Here's how to respond: Log into Sars eFiling and verify data : review the third-party certificates used and compare them with your own (IRP5s, IT3(b), medical tax certificates). Correct errors at source : contact banks or employers to amend inaccuracies and resubmit official data to Sars . File a complete ITR12 return : add missing income and deductions, ensuring your final return reflects the full scope of your tax situation. Submit before the deadline : most individuals must file by around 20 October. Failure to act means Sars' assessment becomes legally binding. Retain supporting documentation : keep evidence of any additions or changes for at least five years in case of an audit. Confirm your updated assessment : Sars will issue an ITA34 with your revised outcome. Review it thoroughly to ensure accuracy.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store