'Battery of the nation' undersea power cable at risk

'Battery of the nation' undersea power cable at risk

The Advertiser2 days ago
One of the nation's largest energy projects could be in doubt amid a government stoush and a cost blowout.
The multi-billion-dollar Marinus Link undersea power cable project to connect Tasmania to the mainland has been touted as critical to making the island state the "battery of the nation" by increasing its capacity to export green power.
The $5.5 billion project is set to be funded by the federal, Tasmanian and Victorian governments.
The Tasmanian government's decision on its 17.7 per cent share of the link's Stage 1 cable, initially promised by July 31, has been delayed.
Tasmania's Shadow Energy Minister Janie Finlay on Saturday accused Premier Jeremy Rockliff of blocking a briefing from Energy Minister Nick Duigan on the Marinus business case.
It had been hoped the briefing would create bipartisan support to secure the project as Tasmania's Liberal government scrambles for survival following the July 19 election.
"We are days away from a critical decision on one of Tasmania's largest infrastructure projects," Ms Finlay told reporters.
"The business case has been sitting in the premier's office for two months, but Jeremy Rockliff won't let Tasmanians see it.
"Not only have they just not briefed Tasmanian Labor, but the premier has stepped in and actively blocked that."
Tasmanian Minerals, Manufacturing and Energy Council chief executive Ray Mostogl said the delay and uncertainty placed the entire project at risk.
Marinus Link must "issue notice to proceed" by the end of August or lose a $1.07 billion contract with the Italy-based ­Prysmian Group to supply the 345km cable.
Tasmania's Liberal government is in caretaker mode after the state election delivered another large crossbench, some of whom oppose the Marinus project.
Ms Finlay accused the Rockliff government of hiding the Marinus Link business case for political gain because it included significant price impacts to pay for transmission infrastructure.
The government has denied Mr Rockliff or his staff blocked a briefing, saying the opposition would be briefed in line with caretaker conventions.
"We are carefully and methodically working through the details, with a decision expected soon," Mr Duigan said.
The undersea electricity and data connector would link Tasmania's northwest with Victoria's Latrobe Valley and allow the smaller state to import surplus solar while exporting hydropower to the mainland grid, where it could help reduce the risk of brownouts.
The project was scaled back in September 2023 after the cost of two cables blew out by $1.7 billion to an estimated $5.5 billion.
Under the plan, Victoria has a 33.3 per cent share and Tasmania 17.7 per cent, with an option to sell its stake to the Commonwealth on completion.
Marinus Link has been touted as a critical component in making Tasmania the "battery" of the nation by increasing the island's capacity to export green power and allow excess energy generated on the mainland to be stored in Tasmania's hydro storage.
The first stage is not slated to be finished until 2028/29.
One of the nation's largest energy projects could be in doubt amid a government stoush and a cost blowout.
The multi-billion-dollar Marinus Link undersea power cable project to connect Tasmania to the mainland has been touted as critical to making the island state the "battery of the nation" by increasing its capacity to export green power.
The $5.5 billion project is set to be funded by the federal, Tasmanian and Victorian governments.
The Tasmanian government's decision on its 17.7 per cent share of the link's Stage 1 cable, initially promised by July 31, has been delayed.
Tasmania's Shadow Energy Minister Janie Finlay on Saturday accused Premier Jeremy Rockliff of blocking a briefing from Energy Minister Nick Duigan on the Marinus business case.
It had been hoped the briefing would create bipartisan support to secure the project as Tasmania's Liberal government scrambles for survival following the July 19 election.
"We are days away from a critical decision on one of Tasmania's largest infrastructure projects," Ms Finlay told reporters.
"The business case has been sitting in the premier's office for two months, but Jeremy Rockliff won't let Tasmanians see it.
"Not only have they just not briefed Tasmanian Labor, but the premier has stepped in and actively blocked that."
Tasmanian Minerals, Manufacturing and Energy Council chief executive Ray Mostogl said the delay and uncertainty placed the entire project at risk.
Marinus Link must "issue notice to proceed" by the end of August or lose a $1.07 billion contract with the Italy-based ­Prysmian Group to supply the 345km cable.
Tasmania's Liberal government is in caretaker mode after the state election delivered another large crossbench, some of whom oppose the Marinus project.
Ms Finlay accused the Rockliff government of hiding the Marinus Link business case for political gain because it included significant price impacts to pay for transmission infrastructure.
The government has denied Mr Rockliff or his staff blocked a briefing, saying the opposition would be briefed in line with caretaker conventions.
"We are carefully and methodically working through the details, with a decision expected soon," Mr Duigan said.
The undersea electricity and data connector would link Tasmania's northwest with Victoria's Latrobe Valley and allow the smaller state to import surplus solar while exporting hydropower to the mainland grid, where it could help reduce the risk of brownouts.
The project was scaled back in September 2023 after the cost of two cables blew out by $1.7 billion to an estimated $5.5 billion.
Under the plan, Victoria has a 33.3 per cent share and Tasmania 17.7 per cent, with an option to sell its stake to the Commonwealth on completion.
Marinus Link has been touted as a critical component in making Tasmania the "battery" of the nation by increasing the island's capacity to export green power and allow excess energy generated on the mainland to be stored in Tasmania's hydro storage.
The first stage is not slated to be finished until 2028/29.
One of the nation's largest energy projects could be in doubt amid a government stoush and a cost blowout.
The multi-billion-dollar Marinus Link undersea power cable project to connect Tasmania to the mainland has been touted as critical to making the island state the "battery of the nation" by increasing its capacity to export green power.
The $5.5 billion project is set to be funded by the federal, Tasmanian and Victorian governments.
The Tasmanian government's decision on its 17.7 per cent share of the link's Stage 1 cable, initially promised by July 31, has been delayed.
Tasmania's Shadow Energy Minister Janie Finlay on Saturday accused Premier Jeremy Rockliff of blocking a briefing from Energy Minister Nick Duigan on the Marinus business case.
It had been hoped the briefing would create bipartisan support to secure the project as Tasmania's Liberal government scrambles for survival following the July 19 election.
"We are days away from a critical decision on one of Tasmania's largest infrastructure projects," Ms Finlay told reporters.
"The business case has been sitting in the premier's office for two months, but Jeremy Rockliff won't let Tasmanians see it.
"Not only have they just not briefed Tasmanian Labor, but the premier has stepped in and actively blocked that."
Tasmanian Minerals, Manufacturing and Energy Council chief executive Ray Mostogl said the delay and uncertainty placed the entire project at risk.
Marinus Link must "issue notice to proceed" by the end of August or lose a $1.07 billion contract with the Italy-based ­Prysmian Group to supply the 345km cable.
Tasmania's Liberal government is in caretaker mode after the state election delivered another large crossbench, some of whom oppose the Marinus project.
Ms Finlay accused the Rockliff government of hiding the Marinus Link business case for political gain because it included significant price impacts to pay for transmission infrastructure.
The government has denied Mr Rockliff or his staff blocked a briefing, saying the opposition would be briefed in line with caretaker conventions.
"We are carefully and methodically working through the details, with a decision expected soon," Mr Duigan said.
The undersea electricity and data connector would link Tasmania's northwest with Victoria's Latrobe Valley and allow the smaller state to import surplus solar while exporting hydropower to the mainland grid, where it could help reduce the risk of brownouts.
The project was scaled back in September 2023 after the cost of two cables blew out by $1.7 billion to an estimated $5.5 billion.
Under the plan, Victoria has a 33.3 per cent share and Tasmania 17.7 per cent, with an option to sell its stake to the Commonwealth on completion.
Marinus Link has been touted as a critical component in making Tasmania the "battery" of the nation by increasing the island's capacity to export green power and allow excess energy generated on the mainland to be stored in Tasmania's hydro storage.
The first stage is not slated to be finished until 2028/29.
One of the nation's largest energy projects could be in doubt amid a government stoush and a cost blowout.
The multi-billion-dollar Marinus Link undersea power cable project to connect Tasmania to the mainland has been touted as critical to making the island state the "battery of the nation" by increasing its capacity to export green power.
The $5.5 billion project is set to be funded by the federal, Tasmanian and Victorian governments.
The Tasmanian government's decision on its 17.7 per cent share of the link's Stage 1 cable, initially promised by July 31, has been delayed.
Tasmania's Shadow Energy Minister Janie Finlay on Saturday accused Premier Jeremy Rockliff of blocking a briefing from Energy Minister Nick Duigan on the Marinus business case.
It had been hoped the briefing would create bipartisan support to secure the project as Tasmania's Liberal government scrambles for survival following the July 19 election.
"We are days away from a critical decision on one of Tasmania's largest infrastructure projects," Ms Finlay told reporters.
"The business case has been sitting in the premier's office for two months, but Jeremy Rockliff won't let Tasmanians see it.
"Not only have they just not briefed Tasmanian Labor, but the premier has stepped in and actively blocked that."
Tasmanian Minerals, Manufacturing and Energy Council chief executive Ray Mostogl said the delay and uncertainty placed the entire project at risk.
Marinus Link must "issue notice to proceed" by the end of August or lose a $1.07 billion contract with the Italy-based ­Prysmian Group to supply the 345km cable.
Tasmania's Liberal government is in caretaker mode after the state election delivered another large crossbench, some of whom oppose the Marinus project.
Ms Finlay accused the Rockliff government of hiding the Marinus Link business case for political gain because it included significant price impacts to pay for transmission infrastructure.
The government has denied Mr Rockliff or his staff blocked a briefing, saying the opposition would be briefed in line with caretaker conventions.
"We are carefully and methodically working through the details, with a decision expected soon," Mr Duigan said.
The undersea electricity and data connector would link Tasmania's northwest with Victoria's Latrobe Valley and allow the smaller state to import surplus solar while exporting hydropower to the mainland grid, where it could help reduce the risk of brownouts.
The project was scaled back in September 2023 after the cost of two cables blew out by $1.7 billion to an estimated $5.5 billion.
Under the plan, Victoria has a 33.3 per cent share and Tasmania 17.7 per cent, with an option to sell its stake to the Commonwealth on completion.
Marinus Link has been touted as a critical component in making Tasmania the "battery" of the nation by increasing the island's capacity to export green power and allow excess energy generated on the mainland to be stored in Tasmania's hydro storage.
The first stage is not slated to be finished until 2028/29.
Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Strategic CEO hire to drive NeuroScientific stem cell therapy release
Strategic CEO hire to drive NeuroScientific stem cell therapy release

Sydney Morning Herald

time7 minutes ago

  • Sydney Morning Herald

Strategic CEO hire to drive NeuroScientific stem cell therapy release

NeuroScientific Biopharmaceuticals has made a second heavy-hitting appointment in less than a week, bringing in experienced Melbourne-based executive Nathan Smith as its chief executive officer, as the company gears up for the commercial release of its innovative StemSmart stem cell technology. Smith has extensive experience in cell and gene therapies in senior commercial, operational and strategic roles in Australia and the United States, which should prove invaluable as the company navigates the regulatory and commercial pathways for its innovative StemSmart technology. The company says his deep expertise in good practice manufacturing will be critical for converting the biotechnology startup into a scaled-up commercial stem cell company. NeuroScientific acquired the StemSmart technology in late June via its $4.1 million acquisition of unlisted Perth-based stem cell company Isopgen. StemSmart uses a specific type of stem cell, mesenchymal stromal stem cells (MSC), as a last-line infusion treatment for critically ill patients, including those experiencing severe immune complications from bone marrow transplants, kidney and lung transplant rejection and inflammatory Crohn's disease. 'I was attracted to NSB given the historical success of StemSmart in multiple serious clinical disorders and the clear potential of the technology for further development.' NeuroScientific Biopharmaceuticals chief executive officer Nathan Smith Adding to the company's ranks of highly credentialled personnel, NeuroScientific announced on Friday that it had also recruited well-regarded Perth-based paediatric haematologist and oncologist Dr Catherine Cole as its chief medical officer. The news of both appointments has continued to fuel a stellar rise in the company's share price, which traded 11.3 per cent higher today to 24.5 cents on the best turnover since April. The company's share price is up 360 per cent since the start of June. Smith was the director of business development at Melbourne's Cell Therapies, which develops and manufactures advanced cell-based therapies and is located within the city's pioneering Peter MacCallum Cancer Centre. He has held key roles at Genzyme Corporation, Mesoblast Inc and GlaxoSmithKline in the US, as well as other leading companies in the cell therapy sector.

Helicopter landing site riles locals in this prized coastal area
Helicopter landing site riles locals in this prized coastal area

Sydney Morning Herald

time7 minutes ago

  • Sydney Morning Herald

Helicopter landing site riles locals in this prized coastal area

He said it was inappropriate and concerning that a helicopter could be taking off, landing and flying near such an environmentally sensitive area teeming with birdlife. His group raised concerns about noise, but the tribunal heard expert evidence that the sound produced by the proposed helicopter would be within the legally allowed levels. Queenscliff resident and former councillor David Kenwood, who opposed the application in tribunal hearings, said it was deeply worrying that the distinctive areas and landscape designation had not been considered. 'The great worry of this is the precedent it sets particularly for this area,' he said. 'It's virtually impossible to stop another helicopter operation.' The Borough of Queenscliffe has previously reported nearly 200 bird species have been seen in Swan Bay and that its intertidal mudflats are home to about 10,000 migratory birds each summer. Ramsey's property is located within a rural conservation zone, and it is also covered by a significant landscape overlay and environmental significance overlay. But the tribunal found these were also not relevant to the proposed use in the helicopter landing site application. The Age made multiple attempts to seek a response from Ramsey, including through his lawyers, but he could not be reached for comment. Kenwood said the area beside Lakers Cutting was serene and inappropriate for a helicopter. 'It's probably the quietest place in the borough.' The zoning of the land and its designation as a distinctive area and landscape should have been enough to protect it from uses including helicopter flights, he said. 'You think you've got safeguards, but once you get into VCAT they're not existent.' The tribunal determined the Bellarine Peninsula Statement of Planning Policy was not incorporated or referred to expressly in the planning scheme. The statement of planning policy sets out a 50-year vision for the area to protect its 'outstanding landscapes and coastal landforms', living Indigenous cultural heritage and history and important infrastructure. The policy lists more than a dozen public entities that are responsible for the declared area, including the Borough of Queenscliffe, Parks Victoria and the Department of Energy, Environment and Climate Action. However, VCAT is not among them. Monash University urban planning and design senior lecturer Liz Taylor said the Queenscliffe council had initially refused a permit for the landing site, but later supported the application. Third-party objectors then spoke out against the application at the tribunal hearings. Taylor said the state government declared the Bellarine Peninsula a distinctive area and landscape several years ago, which meant it was part of Victoria's planning provisions. However, she said the state government needed to make a planning scheme amendment to formally incorporate the declaration into the Queenscliffe planning scheme. A Victorian government spokeswoman said work was under way to incorporate the Bellarine Peninsula Statement of Planning Policy through an amendment to relevant planning schemes. However, it said local councils must consider the policy when making relevant decisions within the declared area. The tribunal granted the permit to Ramsey subject to several conditions, including that flight movements not exceed 16 per calendar month. The helicopter movements can only occur between 7am and 7pm.

Helicopter landing site riles locals in this prized coastal area
Helicopter landing site riles locals in this prized coastal area

The Age

time7 minutes ago

  • The Age

Helicopter landing site riles locals in this prized coastal area

He said it was inappropriate and concerning that a helicopter could be taking off, landing and flying near such an environmentally sensitive area teeming with birdlife. His group raised concerns about noise, but the tribunal heard expert evidence that the sound produced by the proposed helicopter would be within the legally allowed levels. Queenscliff resident and former councillor David Kenwood, who opposed the application in tribunal hearings, said it was deeply worrying that the distinctive areas and landscape designation had not been considered. 'The great worry of this is the precedent it sets particularly for this area,' he said. 'It's virtually impossible to stop another helicopter operation.' The Borough of Queenscliffe has previously reported nearly 200 bird species have been seen in Swan Bay and that its intertidal mudflats are home to about 10,000 migratory birds each summer. Ramsey's property is located within a rural conservation zone, and it is also covered by a significant landscape overlay and environmental significance overlay. But the tribunal found these were also not relevant to the proposed use in the helicopter landing site application. The Age made multiple attempts to seek a response from Ramsey, including through his lawyers, but he could not be reached for comment. Kenwood said the area beside Lakers Cutting was serene and inappropriate for a helicopter. 'It's probably the quietest place in the borough.' The zoning of the land and its designation as a distinctive area and landscape should have been enough to protect it from uses including helicopter flights, he said. 'You think you've got safeguards, but once you get into VCAT they're not existent.' The tribunal determined the Bellarine Peninsula Statement of Planning Policy was not incorporated or referred to expressly in the planning scheme. The statement of planning policy sets out a 50-year vision for the area to protect its 'outstanding landscapes and coastal landforms', living Indigenous cultural heritage and history and important infrastructure. The policy lists more than a dozen public entities that are responsible for the declared area, including the Borough of Queenscliffe, Parks Victoria and the Department of Energy, Environment and Climate Action. However, VCAT is not among them. Monash University urban planning and design senior lecturer Liz Taylor said the Queenscliffe council had initially refused a permit for the landing site, but later supported the application. Third-party objectors then spoke out against the application at the tribunal hearings. Taylor said the state government declared the Bellarine Peninsula a distinctive area and landscape several years ago, which meant it was part of Victoria's planning provisions. However, she said the state government needed to make a planning scheme amendment to formally incorporate the declaration into the Queenscliffe planning scheme. A Victorian government spokeswoman said work was under way to incorporate the Bellarine Peninsula Statement of Planning Policy through an amendment to relevant planning schemes. However, it said local councils must consider the policy when making relevant decisions within the declared area. The tribunal granted the permit to Ramsey subject to several conditions, including that flight movements not exceed 16 per calendar month. The helicopter movements can only occur between 7am and 7pm.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store