Data centre operator successfully challenges decision to refuse it planning permission for two new centres

Data centre operator successfully challenges decision to refuse it planning permission for two new centres

BreakingNews.ie08-08-2025
A leading provider of data centres in Ireland has successfully challenged the decision of South Dublin County Council to refuse it planning permission for two new centres at its campus in west Dublin.
An Coimisiún Pleanála has upheld the appeal taken by EdgeConneX Ireland against the council's ruling in July 2023 to reject its planning application to construct two adjoining single storey data centres covering an area of over 15,000m² on a site at Ballymakaily, Lucan, Co Dublin.
Advertisement
The plans also provided for 24 standby diesel generators with associated 25-metre-high flues in a yard to the west of the data centres as well as a new internal access road and security gates.
However, the Commission imposed a planning condition that the standby generators have to be powered by a renewable fuel source.
South Dublin County Council had refused planning permission for the development on the basis that it had failed to demonstrate that the proposed use was acceptable for lands zoned to provide for enterprise and employment given the lack of a fixed connection agreement to the grid and a lack of significant on-site renewable energy.
In reaching its decision, the council said it also had regard to the existing insufficient capacity in the national grid as well as the applicant's reliance on gas powered plant to provide energy for the data centres and an absence of power purchase agreements (PPAs).
Advertisement
It also rejected EdgeConneX Ireland's application on a separate ground in relation to the retention and protection of existing green infrastructure.
Council planners said the county development plan placed a key emphasis on the requirement for data centres within its administrative area to be sustainable and for applicants to show there was sufficient capacity within the electricity network to accommodate them.
Elected representatives of South Dublin County Council had imposed a total ban on the development of new data centres but a ministerial directive issued in August 2022 reversed the controversial measure.
In its appeal, EdgeConneX Ireland accused the local authority of adopting 'an unduly rigid approach" to its county development plan.
Advertisement
The company claimed the council's decision on its planning application was 'inherently flawed' and its concerns were 'unfounded.'
EdgeConneX Ireland said that it was not within the remit of South Dublin County Council to determine whether there was sufficient capacity on the national grid.
Nevertheless, it confirmed that it had obtained a connection agreement with EirGrid who had developed policy criteria which applicants had to satisfy and which were largely designed to take into account capacity constraints on the grid.
EdgeConneX Ireland argued that the council should be satisfied that EirGrid, as the appropriate authority on the national grid, had determined that its data centre campus can connect to the grid.
Advertisement
It pointed out that the overall on-site dispatchable energy generation capacity on the campus was already established under a previous planning application and should not have to be reconsidered.
The company said it had sought to maximise the use of renewables through the design and future proofing of the power plant on the campus so that it had capacity to accept biogas and hydrogen when they become available.
It also argued that having gas as the primary fuel of the power plants played its part in decarbonising the national grid – which it claimed had been acknowledged in the Government's Climate Action Plan.
EdgeConneX Ireland said it had also provided 'robust evidence' of engagement with PPAs in Ireland.
Advertisement
The company said having an onsite generation plant that was predominantly powered by natural gas should not be a ground for refusal of itself.
In addition, it stressed that its power plant would reinforce the national grid once the EirGrid connection was realised.
The company accepted that some 760 metres of hedgerow would be removed as part of the project but stressed that over 1,300 metres of hedgerow would be retained and a further 1,052 metres of new hedgerow was being proposed which would result in 'a net biodiversity and ecological gain.'
Subject to compliance with a number of planning conditions, An Coimisiún Pleanála said it was satisfied that EdgeConneX Ireland had a fixed connection agreement to connect to the grid and that the data centres were not an 'islanded' development which was dependent solely on onsite energy generation.
The Commission said it was also satisfied that the company had incorporated strong energy efficiency measures to reduce its carbon footprint and had demonstrated engagement with PPAs as well as that there was sufficient capacity with the relevant water, wastewater and electricity network to accommodate the proposed use.
It accepted that EdgeConneX Ireland had sought to protect and enhance the biodiversity and ecological value of the existing green infrastructure network where possible.
The Commission also ruled that it would not seriously injure the residential or visual amenities of the area and would be acceptable in terms of the safety and convenience of pedestrians and other road users as well as not being prejudicial to public health.
The planning appeals authority said it was also satisfied that various mitigation measures proposed by the company would ensure that the development would not have any unacceptable direct, indirect or cumulative effects on the environment.
The Commission noted that data centres had been identified as core infrastructure and enablers of a technology-rich innovative economy and of significant importance from a national and international perspective in the Government Statement on the Role of Data Centres in Ireland's Enterprise Strategy published in July 2022.
It accepted that EdgeConneX Ireland had demonstrated that the proposed data centres would be in accordance with the twin transitions of 'digitisation and decarbonisation' as well as the principles outlined in the Government Statement.
One of the planning conditions is that the company enters into a corporate PPA with a renewable energy provider for the proposed data centres before they become operational.
EdgeConnex Ireland is also required to provide a draft agreement that it would be willing to connect to a future district heating network if one becomes available.
Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Further planning bid for Coalport pub undergoing revamp
Further planning bid for Coalport pub undergoing revamp

BBC News

time4 hours ago

  • BBC News

Further planning bid for Coalport pub undergoing revamp

The owner of a historic pub near the River Severn in a protected part of Shropshire has applied for permission to alter a refurbishment Brewery Inn, Coalport High Street, sits in the Ironbridge Gorge Unesco World Heritage Site where there are strict planning is currently being carried out on the pub ahead of its eventual reopening and owner Severn View Brewers Ltd has applied to make some changes to the design of a screen and a rear year, the pub was granted permission for extensions, holiday accommodation and changes to the layout of the Grade II listed property. Three applications have been lodged. The first to change the conditions of previous approval, the second to seek full planning permission, and a third for listed building architect Corey Waters said the proposals represented a "significant overall improvement" and Historic England advised the "best way to conserve a building is to keep it in use, or to find an appropriate new use if it has passed out of use".The architect also said in a heritage statement that the public body advised against an "unreasonable, inflexible approach" and encouraged a "reasonable and proportionate approach to owners' needs".Public consultation is ongoing. This news was gathered by the Local Democracy Reporting Service, which covers councils and other public service organisations. Follow BBC Shropshire on BBC Sounds, Facebook, X and Instagram.

Notorious Kinahan drug cartel introduces McDonald's-style franchise system to flood the streets of Ireland with cocaine
Notorious Kinahan drug cartel introduces McDonald's-style franchise system to flood the streets of Ireland with cocaine

Daily Mail​

time5 hours ago

  • Daily Mail​

Notorious Kinahan drug cartel introduces McDonald's-style franchise system to flood the streets of Ireland with cocaine

Ireland's notorious Kinahan drugs cartel has introduced a fast-food-style franchise system in its efforts to continue dominating the cocaine trade. The drugs syndicate has muscled its way back to being the dominant force in the Irish cocaine scene in recent months, reasserting itself as the main supplier to almost all major criminal organisations across the country again. Such is their stranglehold on the trade, that many of the gangs who filled some of the holes left by the mobsters when they fled to Dubai in the mid-2010s to exploit the lack of extradition agreement between the UAE and the EU, are also now back on board. Representatives from narcotics networks in Dublin and beyond are believed to have travelled to Dubai to meet high-ranking members of the Kinahan cartel to arrange future shipments directly from them. Those said to have travelled to the Middle East are a Clondalkin gang known as 'The Family' as well as another group who operate from Cabra, who have long been involved in major drug trafficking operations, according to The Times. It is reported that this power play by the Kinahans will now see them operate like a franchise, flooding cocaine to gangs through the streets of Ireland akin to how fast-food suppliers deliver produce to stores in an attempt to eliminate competition. The move may explain the recent decrease in gangland feuds and murders across Ireland, with the street price of the Class A drug also remaining at a stable level after a sharp increase last year. The Kinahan's new network structure is believed to be a repeat - or is at least similar - to how the cartel up bulked itself up during its original network before a series of global law enforcement operations targeted its leadership. Drugs kingpin Thomas 'Bomber' Kavanagh, who ran the UK arm of the Kinahan catrel, is one of the major players to be brought down in recent times. He was jailed for 21 years at Ipswich Crown Court in March 2022 after pleading guilty to conspiring to import class A and B drugs and money laundering offences in July 2020. Fearing the same fate, the cartel's leader Christy 'Dapper Don' Kinahan, 68, and his two sons Daniel, 48, and Christopher Jr, 44, have already devised a contingency plan should the gardai attempt to extradite them from their base in Dubai. The Irish government signed two treaties with UAE representatives which allowed them to extradite suspected organised crime accomplices last October - a move which now has the Kinahans on red alert. Security sources also told The Times that 'Dapper Don' now travels with a bodyguard when in public, such is his paranoia about being snared. Author Mark Galeotti, an expert on multi-country crime, told the publication that the cartel's move to seemingly become a drugs conglomerate made sense - for them. The three are said to have already devised a contingency plan should the gardai attempt to extradite them from their base in Dubai He said: 'If you've got all the architecture, the pipeline, the infrastructure in order to move the drugs and you know where the markets are, why would you abandon that? Isn't it better to trade that out to others who are going to be your proxies in effect?' The Kinahan's global clients are said to include Mexican cartels, Hezbollah and Iran's intelligence services. It is believed that the gang have assets worth around $1.5billion hidden in offshore accounts and in hidden international investments. The cartel was previously headed-up by Liam Byrne, who relocated to Dubai when Garda drug teams began closing in. He was arrested in June 2023 while holidaying in Mallorca and was later extradited to the UK. Byrne, a close friend of 'Dapper Don', was convicted of firearms offences by Britain's National Crime Agency and was released on licence in January. In April 2022, the US Department of State placed up to $5million in rewards for information that leads to each of the arrests and prosecution of 'Dapper Don' and his two sons, branding them the heads of a major international drugs cartel.

Cost of Victoria's renewable energy transmission plan projected to double
Cost of Victoria's renewable energy transmission plan projected to double

The Guardian

time10 hours ago

  • The Guardian

Cost of Victoria's renewable energy transmission plan projected to double

One of Australia's largest renewable energy transmission projects has expanded zones for solar, battery and wind developments with the cost of connection to almost double. The latest version of Victoria's 2025 Transmission Plan, released by state government agency VicGrid on Sunday, revealed a 200,000-hectare increase in the area available to developers. The plan outlines the parts of the state designated as renewable energy zones and the new transmission infrastructure needed in the next 15 years to connect them to the grid. The latest version increases areas of land designated as hubs for wind, solar and battery farms from 1.66m hectares proposed in May to 1.88m hectares across six proposed renewable energy zones. The amendment increases the footprint of these areas to 7.9% of the state, up from 7.0% in the original draft proposal, after industry feedback said larger areas were needed to make projects technically and commercially viable. The number of distinct zones has been increased to nine from seven, also in response to feedback. Sign up: AU Breaking News email The greatest change will be in the state's west with an expansion to the Wimmera-southern Mallee zone, while a new area around Coleraine has been added to the south west zone. The state energy minister, Lily D'Ambrosio, said more than 42% of Victoria's electricity was produced by renewables in the past financial year, with the state reaching record levels of renewable energy generation. 'Our record investment in renewable energy is paying off,' she said in a statement on Sunday. Sign up to Breaking News Australia Get the most important news as it breaks after newsletter promotion 'Victoria consistently has the lowest wholesale power prices in the country, helping to slash energy bills for families and businesses.' Victorians paid an average wholesale price of $107 per megawatt hour, compared with $151 in NSW, $138 in South Australia, $127 in Queensland and $115 in Tasmania, according to government data. But the latest modelling predicts the cost of connecting Victoria's renewable energy zones could almost double. The government initially estimated a $4.3bn cost, but VicGrid puts the latest price tag closer to $7.9bn, taking into account new Australian Energy Market Operator costings for the transmission lines. The costs are expected to be mostly recouped through higher consumer bills, although the government argues Victorians will overall be better off with wholesale energy costs lowered by the delivery of more renewable energy into the grid. The federal government has a target of 82% renewable energy in the national grid by 2030, up from 43% this year.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store