Dart extension to Wicklow town pushed back to 2030
An extension of the line to Wicklow town is currently under active review with battery-electric carriages, which are undergoing testing and expected to be used when the service begins operations.
The line extension has been hit with many false starts in recent years.
In 2019, it was announced that the Dart for Wicklow town would begin serving passengers by 2023-2024.
Timeframes for 2025 and 2026 were also promised but were subsequently missed.
In February 2025, representatives from Irish Rail met with members from the Transport, Infrastructure Delivery and Emergency Services, Strategic Policy Committee of Wicklow County Council where they were told that an hourly service would be introduced by the end of 2028.
This follows a presentation from then NTA CEO Anne Graham and now interim chief Hugh Creegan to Wicklow County Council's monthly meeting in October of last year, confirming that the NTA are looking at a four-to-five-year timeframe to introduce the service.
Now in a parliamentary update to Wicklow TDs John Brady and Jennifer Whitmore Transport Minister Darragh O'Brien confirmed that it won't be until the end of this decade when trains will begin carrying passengers on a more frequent basis.
'The new battery-electric Dart carriages will first be deployed from Dublin to Drogheda from next year. As more carriages arrive, it may be feasible to also deploy them to extend Dart services to and from Wicklow, subject to funding and approvals for the required charging infrastructure. The NTA is currently examining this issue with a view to progressing the extension around 2029.' he added.
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Irish Independent
3 days ago
- Irish Independent
Movement expected soon on south Wicklow greenway project
The greenway, which would pass through scenic areas of the former railway line along the Wicklow–Wexford border, including Shillelagh, Tinahely, Aughrim, Annacurra, Woodenbridge, and Arklow has been stuck in phase two since 2023. Phase 2 involved extensive work on assessing the impact of identified project constraints; the Phase 2: Options Selection report has been submitted by Wicklow County Council to TII and are currently being reviewed by officials. Subject t-Wexford TD Fionntán Ó Súilleabháin has said it is now important that the project doesn't face any further delays. 'This project is of huge importance to County Wicklow, in terms of health and wellbeing, local recreation and tourism. I am pleased that it should progress to Stage 3 for the autumn and hopefully through the remaining construction phases soon after. 'I also raised this delay directly with Minister Paschal Donohoe in the chamber of Leinster House last month and is a flagship project that I intend to pursue until we see it in place.' 'In such a scenic area, it will no doubt attract large numbers of people from throughout Ireland and indeed from further afield.' he added. Funding for the Greenways programme is reviewed on an annual basis by the Department of Transport. Investment in greenways and active travel projects is also subject to the requirements of the Infrastructure Guidelines and necessary statutory approvals. Greenway schemes in County Wicklow were allocated €1,650,000 in 2025, with €500,000 going towards the Arklow to Shillelagh project.


Irish Independent
3 days ago
- Irish Independent
Significant extra funding for Wicklow roadworks secured
The allocation represents a significant increase to the 2025 funding available under the Local Improvement Scheme (LIS) – bringing the overall investment to €817,793 for Wicklow for the year. Under the LIS, local authorities are responsible for identifying and prioritising roads for improvement works under the scheme, in consultation with residents/landowners. The scheme is designed to support the improvement of non-public roads in rural communities and access to rural homes and farms, as well as outdoor amenities. The works must be completed before the end of the year. Across the country there is an additional €14 million for the scheme, bringing the total to €30 million available to local authorities this year. This represents the highest annual funding level since the scheme was re-introduced. Under this scheme Wicklow County Council are responsible for identifying and prioritising roads for improvement works in consultation with residents and landowners, and the work must be completed by the end of the year. Welcoming the announcement, Wicklow-Wexford Deputy Brian Brennan said the funding allocation will be crucial. 'This additional funding demonstrates our commitment to improving connectivity for rural residents – whether it be access to homes, farms or outdoor amenities.' 'I spend a lot of time on the road in rural areas in south Wicklow, meeting with constituents, communities, organisations, clubs and businesses and I know that investment in our rural road network is critical to ensuring that the people of rural Ireland have the connectivity, access and quality of life that they deserve. Meanwhile Wicklow TD Edward Timmins pointed out the roads that are subject to the funding. 'Eligible roads include non- public roads providing access to parcels of land where two or more are owned or occupied by different people, one of which must be for agricultural purposes, and non-public roads leading to important community amenities such as graveyards, beaches, piers, and mountains.' 'I look forward to seeing how this additional funding is used to improve our rural roads across Wicklow'. Deputy Timmins concluded.


Irish Times
6 days ago
- Irish Times
Transport authority approves settlement of Swords BusConnects corridor legal action
The board of the National Transport Authority (NTA) has approved a proposed settlement to halt legal action taken against its planned BusConnects corridor from Swords to Dublin city centre. The NTA would not disclose the terms of the settlement, but the board's approval raises hopes judicial review proceedings will be dropped to allow construction of the 12km route granted planning permission more than a year ago. The Swords corridor is one of 12 segregated bus routes to be built as part of the €4 billion scheme to transform the capital's bus services. The planned route runs from the south side of Swords town in north Dublin, past Dublin Airport and through Santry along the Swords Road, then along the Drumcondra Road and Dorset Street to the top of O'Connell Street and Parnell Square. READ MORE The NTA secured permission from An Bord Pleanála for the route in June of last year, but judicial review proceedings against the board's decision were initiated in August by two separate parties: owners of a business park near the airport and a veterinary practice south of Swords. The cases have not yet been heard in the High Court but in their submissions to An Bord Pleanála both Brendan Collins, of Collinstown Business Park, and Conor O'Scanaill, of O'Scanaill Veterinary Surgeons raised concerns about the effect the bus corridor would have on their properties. Minutes of a recent NTA board meeting show details of a 'settlement proposal' were presented to the board by interim NTA chief executive Hugh Creegan. 'Following the overview provided, the board approved the terms of the proposed agreement to settle the particular judicial reviews proceedings being taken in relation to the Swords to City Centre Core Bus Corridor scheme,' the minutes state. This is the first settlement approved by the board in an effort to bring an end to legal action taken against one of the bus corridor schemes. Of the 12 corridors, judicial review proceedings have been taken in relation to seven, the corridors from Swords, Clongriffin, Belfield/Blackrock, Blanchardstown, Templeogue/Rathfarnham, Bray and Kimmage. The other five now have 'full' planning permission as the time frame by which they could be challenged in the courts has expired. These are the routes from Ballymun/Finglas, Liffey Valley , Ringsend, Tallaght/Clondalkin and Lucan. [ BusConnects route will come in 'on time, on budget', says Darragh O'Brien Opens in new window ] Green Party transport spokesman Feljin Jose said the delays caused by the judicial reviews were extremely concerning. 'The NTA has to build three of these at the same time over the next four to five years to get this done this side of 2035. Seven out of the 12 approved corridors in judicial review is not a good return rate and will add at least a year, maybe up to two years, delay.' The settlement of the Swords cases would be a win for Dubliners, he said. 'Without knowing the details of the settlement I can only say it's good news if the cases are dropped and the quicker we can get this done and have bus priority and improved cycling and pedestrian infrastructure.' The plaintiffs and their legal representatives declined to comment on the settlement agreement. A spokeswoman for the NTA said it could not comment on the details of the proposed agreement 'other than to acknowledge that the board approved the terms of the agreement at the June board' meeting. Construction of the first core bus corridor from Liffey Valley to the city centre is due to begin next month.