Kenya wins $2bln claim case in London over failed railway concession

Kenya wins $2bln claim case in London over failed railway concession

Zawya4 days ago
Kenya has blocked a $2 billion claim lodged by Rift Valley Railways (RVR) in the London Court of International Arbitration (LCIA) over a collapsed 25-year concession to run the 2,350-kilometre Kenya-Uganda railway.
The concession was terminated by Nairobi and Kampala in 2017 after RVR, the consortium that managed the railway system, failed to meet the contractual obligations.
The case began when KU Railway Holdings Ltd (formerly Sheltam Rail Company Pty) and RVR Investments Ltd initiated arbitral proceedings at the London Court of Arbitration against Kenya and Uganda in 2020, seeking compensation for breach of the concession agreements for the sum of $2,005,900,000.
These agreements related to the operation, construction and management of the now-defunct Rift Valley Railways line, a joint freight and passenger transport project between the two nations.
In its ruling, the LCIA entirely dismissed the $2 billion claim, awarding costs in favour of Kenya, according to its Attorney-General.'This outcome not only upholds the integrity of Kenya's legal and commercial commitments but also protects the Kenyan taxpayer from what would have been a staggering financial liability,' said a press statement from the AG's office on Friday. 'This win reaffirms Kenya's resolve to uphold lawful governance, protect public resources and maintain international credibility.'Termination noticesThe dispute stemmed from a 25-year concession granted to RVR in 2006 to operate the metre gauge railway in Kenya and Uganda, following a World Bank recommendation in 1998.
RVR operated the line until its concession was terminated in 2017, just around the time Kenya unveiled its standard gauge railway (SGR) line, reflecting the challenges of public-private partnerships (PPP) in infrastructure projects in the East African region.
RVR had failed to meet contractual obligations, including payment of concession fees and achieving freight targets.
In 2017, Kenya Railways issued RVR a 90-day notice of intention to terminate the concession on account of unpaid fees amounting to Ksh600 million ($4.65 million), inadequate investment and failure to meet the contractual freight volumes. This was followed by a termination notice after RVR failed to address the issues.
Kenya was followed by Uganda in terminating the concession to run its railway line in the same year.
Uganda also cited failure by RVR to meet its obligations as set out in the concession agreement signed when the firm took over the Kenya-Uganda Railway in 2006.
Kenya was on April 2020, served with an initial notice of arbitration and an amended notice of arbitration a week later notifying the Nairobi and Kampala governments of the arbitral proceedings.
The Kenya Railway Corporation and Uganda Railway Corporation had signed the concession documents in a deal that would have seen the two bodies transfer their railway assets to RVR in return for an 11 percent of gross revenue during the concession period.
© Copyright 2022 Nation Media Group. All Rights Reserved. Provided by SyndiGate Media Inc.
Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Ambassador Gao Wenqi Attends the Working Meeting between Leaders of Export-Import Bank of China and Ministry of Finance and Economic Planning of Rwanda
Ambassador Gao Wenqi Attends the Working Meeting between Leaders of Export-Import Bank of China and Ministry of Finance and Economic Planning of Rwanda

Zawya

timean hour ago

  • Zawya

Ambassador Gao Wenqi Attends the Working Meeting between Leaders of Export-Import Bank of China and Ministry of Finance and Economic Planning of Rwanda

AFRICA On July 31, Ambassador Gao Wenqi attended the working meeting betweenYang Dongning, Vice Governor of Export-Import Bank of China and Hon. Yusuf MURANGWA, Minister of Finance and Economic Planning of Rwanda. Both sides exchanged views on promoting the trade, economic and financial cooperation between China and Rwanda. Distributed by APO Group on behalf of Embassy of the People's Republic of China in the Republic of Rwanda. Disclaimer: The contents of this press release was provided from an external third party provider. This website is not responsible for, and does not control, such external content. This content is provided on an 'as is' and 'as available' basis and has not been edited in any way. Neither this website nor our affiliates guarantee the accuracy of or endorse the views or opinions expressed in this press release. The press release is provided for informational purposes only. The content does not provide tax, legal or investment advice or opinion regarding the suitability, value or profitability of any particular security, portfolio or investment strategy. Neither this website nor our affiliates shall be liable for any errors or inaccuracies in the content, or for any actions taken by you in reliance thereon. You expressly agree that your use of the information within this article is at your sole risk. To the fullest extent permitted by applicable law, this website, its parent company, its subsidiaries, its affiliates and the respective shareholders, directors, officers, employees, agents, advertisers, content providers and licensors will not be liable (jointly or severally) to you for any direct, indirect, consequential, special, incidental, punitive or exemplary damages, including without limitation, lost profits, lost savings and lost revenues, whether in negligence, tort, contract or any other theory of liability, even if the parties have been advised of the possibility or could have foreseen any such damages. © ZAWYA 2025

South Africa: Cooperative Governance and Traditional Affairs (COGTA) Chairperson Concerned by Closure of Emfuleni Local Municipality Client Service Centre
South Africa: Cooperative Governance and Traditional Affairs (COGTA) Chairperson Concerned by Closure of Emfuleni Local Municipality Client Service Centre

Zawya

timean hour ago

  • Zawya

South Africa: Cooperative Governance and Traditional Affairs (COGTA) Chairperson Concerned by Closure of Emfuleni Local Municipality Client Service Centre

The Chairperson of the Select Committee on Cooperative Governance and Public Administration (Traditional Affairs, Human Settlements and Water&Sanitation), Mr Mxolisi Kaunda, is concerned by reports of the closure of the Emfuleni Local Municipality client service centre due to unpaid rent. 'The closure of the client service centre negatively impacts the ability of the municipality to collect rates and taxes, a key driver of municipal revenue. The inability to collect revenue will have an unintended negative impact on the ability to deliver quality services to the people,' Mr Kaunda said. The 6th Parliament select committee visited the municipality and criticised the lack of progress in resolving material risks of governance and financial control within the municipality, which exacerbate the already dire state of poor service delivery. Furthermore, the continued attachment of the municipality's bank accounts by service providers, such as Eskom and Rand Water, due to non-payment for services requires a focused and deadline-driven approach. 'While it is not sustainable that the accounts of the municipality are attached, it is also unsustainable that the municipality does not pay for services. The residents of the municipality deserve better basic services in line with the objects of municipalities as envisioned in Section 152 of the Constitution,' Mr Kaunda suggested. The Chairperson also highlighted the importance of government departments paying the municipality for services to improve cash flow management and enable the municipality to provide services. The Chairperson called on the municipality and the provincial executive to find a workable solution to ensure that the client service centre is reopened and that service providers are paid on time. Distributed by APO Group on behalf of Republic of South Africa: The Parliament.

Seychelles: President Ramkalawan Attends Foundation Stone laying Ceremony for Orchid Village Affordable Housing Development Phases II & III
Seychelles: President Ramkalawan Attends Foundation Stone laying Ceremony for Orchid Village Affordable Housing Development Phases II & III

Zawya

timean hour ago

  • Zawya

Seychelles: President Ramkalawan Attends Foundation Stone laying Ceremony for Orchid Village Affordable Housing Development Phases II & III

President Wavel Ramkalawan, accompanied by First Lady Mrs. Linda Ramkalawan and Vice President Ahmed Afif, attended the foundation stone laying ceremony for the second and third phases of the Orchid Village affordable housing development at Grand Anse Mahé on Friday morning. The comprehensive housing initiative encompasses 80 affordable residential units, comprising 32 two-bedroom and 48 three-bedroom accommodations. Ascent Project Limited will execute the construction over a 24-month timeline,with the project generously funded by the United Arab Emirates government at an investment of approximately USD 7.3 million. President Ramkalawan, alongside His Excellency Mr. Ahmed Saeed Alneyadi, Chargé d'Affaires of the UAE Embassy, and Minister for Land and Housing Billy Rangasamy, unveiled the commemorative plaque and laid the foundation stone, marking the project's commencement. The delegation also participated in a symbolic tree-planting ceremony. In his address, Minister Rangasamy expressed profound gratitude to the UAE government for their substantial investment in Seychelles' housing sector. The Minister announced the concurrent development of regional sewage treatment plants to service multiple housing estates, including this project, aligning with the nation's comprehensive infrastructure agenda for sustainable development. His Excellency Mr. Ahmed Saeed Alneyadi emphasized that the project "represents a significant milestone in the United Arab Emirates' commitment to providing quality housing for Seychellois citizens and fostering community growth. This grant transcends mere financial investment, it exemplifies the enduring friendship and solidarity between Seychelles and the UAE." President Ramkalawan conveyed his appreciation and satisfaction with the project's progress, noting it as one of three generous initiatives from the UAE government, alongside the English River rehabilitation project and the Anse Royale Sports Complex. "Let this village become a source of pride and cultivate a sense of community that enables our people to flourish," the President declared. National Assembly Member for Grand Anse Mahé District, Mr. Waven William, urged prospective beneficiaries to maintain consistent payment schedules to secure housing allocation. He encouraged current residents to preserve their properties through proper maintenance and foster harmonious neighborhood relations. William advocated for revised housing agreements reflecting contemporary realities, permitting homeowners to undertake repairs while preserving structural integrity, and called for proactive enforcement measures to maintain community standards. The ceremony was attended by Minister of Foreign Affairs and Tourism Mr. Sylvestre Radegonde, Minister of Health Mrs. Peggy Vidot, Principal Secretaries, Chief Executive Officers, National Assembly members, Grand Anse Mahé District Administrator Mrs. Retania Leon, Ministry of Land and Housing personnel, district residents, and distinguished guests. Distributed by APO Group on behalf of State House Seychelles.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store