
‘Technical challenges' causing project delays on Finlay Mill Rd.
'A year at the outside,' officials added then, providing themselves a small cushion in case of complications.
Almost 70 weeks later, the job isn't finished and Finlay Mill Road, just north of Barrie, remains a one-way thoroughfare, causing traffic delays and congestion throughout the community.
Contrary to community speculation, the delay has little to do with the 'financial difficulties' of the company that was hired to do the installation, Earth Boring Company Ltd.
'The Township of Springwater became aware of Earth Boring Co. Limited's financial difficulties in April 2025, which was a matter of public record,' Trevor Harvey, the township's director of public works, told BarrieToday in an email. 'The implications associated with these difficulties do not affect the township directly as there are no contractual arrangements between the township and the contractor.
'The agreements are strictly with the developer,' he added.
According to information presented at the public information session, the developer, Rose Corporation, was footing the bill for the force-main installation with no contributions coming from municipal tax dollars.
According to a posting on BDO Canada's website, on April 17, 2025, 'Earth Boring Co. Ltd., Yarbridge Holdings Inc., Trolan Investments Ltd., and Yarfield Services Ltd. (collectively 'Earth Boring' or the 'Debtors') sought and obtained an initial order from the Ontario Superior Court of Justice (commercial list) pursuant to the Companies' Creditors Arrangement Act.'
Harvey explained that the delay has been caused by what's in the ground along the planned path of the force main.
'The issues contributing to the delays are related to technical challenges,' he said. 'Specifically, the construction process is facing difficulties due to the presence of cobbles and boulders in the planned path for drilling, which complicates the construction methods.
'Additionally, there are pending approvals needed from the Ministry of Transportation Ontario (MTO), which extends the progress of the timeline,' Harvey added.
He said the combination of these factors is what is causing the project delays.
Harvey said the township has requested an updated schedule and he expects one will be provided next week.
'We understand that delays in construction can be frustrating for residents,' he said. 'The project is designed to bring significant long-term benefits and improvements to the community.'
Originally designed to be completed in stages, stage one — Finlay Mill Road between Wattie Road and Doran Road — was supposed to take 12 weeks.
Stage two targeted Doran Road between Finlay Mill Road and Gill Road and was scheduled to be completed in six weeks.
Stage three was scheduled for 17 weeks and was to cover Finlay Mill Road between County Road 27 and Wattie Road.
Harvey said the township will keep the community informed about the progress of the project by providing regular updates through its official social-media channels and website.
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Business Insider
a day ago
- Business Insider
RBC Capital Sticks to Its Buy Rating for Birchcliff Energy (BIREF)
RBC Capital analyst Michael Harvey maintained a Buy rating on Birchcliff Energy on August 18 and set a price target of C$8.00. The company's shares closed yesterday at $4.34. Elevate Your Investing Strategy: Take advantage of TipRanks Premium at 50% off! Unlock powerful investing tools, advanced data, and expert analyst insights to help you invest with confidence. Harvey covers the Energy sector, focusing on stocks such as Tourmaline Oil, ARC Resources, and Birchcliff Energy. According to TipRanks, Harvey has an average return of 16.7% and a 55.42% success rate on recommended stocks. In addition to RBC Capital, Birchcliff Energy also received a Buy from Raymond James's Luke Davis in a report issued on August 14. However, on August 13, BMO Capital maintained a Hold rating on Birchcliff Energy (Other OTC: BIREF). The company has a one-year high of $5.71 and a one-year low of $3.15. Currently, Birchcliff Energy has an average volume of 67.12K. Based on the recent corporate insider activity of 24 insiders, corporate insider sentiment is negative on the stock. This means that over the past quarter there has been an increase of insiders selling their shares of BIREF in relation to earlier this year.
Yahoo
2 days ago
- Yahoo
How home sizes are changing in the UK: Are they getting bigger or smaller?
The average floor area of a flat or a detached home in England has shrunk over the past decade. But bungalows, terraced homes and semi-detached properties have typically grown in size between 2013 and 2023, according to according to analysis by Nationwide Building Society. The data was compiled by the building society from the English Housing Survey. Andrew Harvey, Nationwide's senior economist, said: 'Typical property sizes have increased slightly over the last decade. Since 2013, the average floor area has increased from 95.3 square metres to 96.2 square metres. He added: 'The largest increase has been in terraced houses, where the average floor area is 3.6 per cent bigger than in 2013. But the average size of flat, the smallest property type, is now 1.7 per cent smaller than 10 years ago at 60.3 square metres. 'Reflecting the composition of the stock, the owner occupier sector has the highest average floor area at 112 square metres. The average floor area in the private and social rented sectors is smaller at 76 square metres and 65 square metres respectively, due to greater concentration of flats.' Mr Harvey said the total housing stock in England has increased by 2.1 million homes to 25.4 million in 2023. He added: 'Of the total, 16.3 million dwellings are owner occupied, while 4.9 million are privately rented, with the remaining 4.2 million in the social rented sector (local authority or housing association properties).' Here are average floor areas for property types in England in square metres in 2013 followed by 2023 and the percentage change, according to Nationwide Building Society: Flats, 61.4, 60.3, minus 1.7 per cent Bungalow, 77.0, 77.5, 0.6 per cent Terraced, 88.7, 91.9, 3.6 per cent Semi-detached, 96.9, 99.1, 2.2 per cent Detached, 152.9, 151.9, minus 0.6 per cent


Chicago Tribune
5 days ago
- Chicago Tribune
Southland road work, bike path projects to receive Cook County grants
Several south and southwest suburbs are getting Cook County grant money for transportation projects such as repaving streets and building bike paths. Nearly $8.3 million in grants for 32 projects were announced last week by Cook County. The county awarded $300,000 to Calumet City to install stormwater bumpouts on Wentworth Avenue at 156th Street and 156th Place. Calumet Park will get $350,000 for design and construction of alley improvements in the village. The county awarded $300,000 to Harvey for engineering work on a project to make improvements along 157th Street between West Avenue and Dixie Highway in an industrial area of the city. Oak Forest will get $416,000 to build a bike and walking trail along Central Avenue north of 159th Street. The trail will connect with the existing Tinley Creek trail and also make sections of Oak Forest more accessible by foot or bike, including City Hall, Central Park, the library and Oak Forest High School, according to the county. The county awarded $306,000 to the Oak Lawn Park District for a bike and walking path at the Wolfe Wildlife Park, 109th Street and Laramie Avenue. The work will involve replacing and widening an existing asphalt path, installing lighting and building a new path along the east side of Richards High School, according to the county. Orland Park plans to make safety improvements at 159th Street and 94th Avenue, bordering Orland Hills, and will get $150,000 toward design of the work. Palos Hills will get $270,000 to make pedestrian safety improvements along 111th Street. Phoenix will get $430,000 toward design and construction of road improvements along 7th Avenue from 153rd Street to 155th Street. Resurfacing of the street comes after installation of a new water main on 7th Avenue. The county awarded $240,000 to Richton Park to design a rebuild of Richton Road, including making it a two-way street with a center turn lane. Tinley Park will receive $250,000 to make road improvements along 179th Street between 80th Avenue and 94th Avenue. Resurfacing the road is planned along with new sidewalks, according to the county. The funds come from the Invest in Cook program, which earmarks grants for transit projects. County officials said 63% of funds this year will go to projects in low- and moderate-income areas. They said in some projects funded, county money is leveraged with local, state or federal money to widen the scope of work. This the ninth year Invest in Cook money has been distributed, with a total over that time of more than $72 million.