Right on track: What to expect as Malaysia's major train projects hit the rails

Right on track: What to expect as Malaysia's major train projects hit the rails

Malay Mail22-04-2025

KUALA LUMPUR, April 23 — Come second half of 2025, public transport enthusiasts and Malaysians will be able to look forward to the scheduled completion of several major transportation infrastructure projects nationwide.
Among those slated for completion and operation this year are the LRT Shah Alam Line (LRT3) and the Gemas-Johor Baru Electrified Double-Track (EDTP) rail project.
Malay Mail takes a look at these anticipated public rail infrastructure projects and how they will serve for the betterment of the public in terms of transport network interconnectivity.
A general view at LRT3 Johan Setia Depot in Klang July 4, 2023. — Picture by Yusof Mat Isa
LRT3
Announced under Budget 2015 and launched in 2016, the LRT3 project was initially designed with 26 stations (25 at present) to serve the western corridor of Greater Klang Valley with a total development cost initially set at RM9 billion, revised to RM16.6 billion in 2018 and RM21.33 billion by 2025.
Spanning 37.8 kilometres (including 2 kilometres of underground tunnel) in length, the fully automated and driverless rail system starts at Bandar Utama and ends at Johan Setia with interchanges at Bandar Utama (MRT Sungai Buloh-Kajang Line) and Glenmarie (LRT Kelana Jaya Line).
The LRT3 alignment spans 37.8km in length from Bandar Utama, Petaling Jaya to Johan Setia, Klang. — Picture via LRT3.com.my
Forming part of the Klang Valley Integrated Transit System once completed, the LRT3 Line is expected to serve several high-density areas such as Bandar Utama, Shah Alam and Klang — accommodating up to 18,630 commuters per hour per direction.
It is expected to benefit some two million residents along its alignment — especially those traveling between Petaling Jaya and Klang — with the aim of alleviating traffic congestion and boosting economic growth around the stations.
Due for operation: September 30
Gemas-JB EDTP
The Gemas-JB EDTP is a 192-kilometre electric train service project aimed at upgrading and complementing KTM's Electric Train Service (ETS) which runs from Padang Besar in Perlis to Gemas in Negeri Sembilan.
The Gemas-JB EDTP spans four major districts in Johor, namely Segamat, Kluang, Kulai and Johor Baru, with 11 stops along its route.
Announced in 2011 as part of Malaysia's EDTP, construction for the RM9.5 billion Gemas-JB EDTP began in 2018 and was initially scheduled for completion in October 2021.
However, challenges during the Covid-19 pandemic and land acquisition issues caused setbacks.
Once completed, the project would facilitate trade services between Kuala Lumpur and Johor Baru, positioning it as a key catalyst for enhancing connectivity and stimulating economic growth in the region.
Freight transport between Malaysia's two largest ports — Port Klang and Tanjung Pelepas — is also expected to be enhanced.
It is anticipated the project could accommodate some 3,000 daily passengers on the JB-KL route; including reducing commute time from JB to KL to four and a half hours from the previous seven hours by diesel train.
Due for operation: August 2025
Special mentions: JB-Singapore Rapid Transit System Link (RTS Link)
While not slated for completion this year, the RTS Link has nevertheless made significant progress with track installation and construction now more than 65 per cent completed.
The RTS Link is an international cross-border railway shuttle link consisting of two stations — Bukit Chagar in JB and Woodlands North in Singapore.
Approximately 4 kilometres in length, the RTS Link aims to provide an alternative means of transportation that will help alleviate the congestion at immigration checkpoints for both countries.
The link will be a modern Light Rail Transit (LRT) system that will provide a high volume, fast and efficient transportation system between the two stations. — Picture courtesy of MRT Corp
The link will have a peak capacity of 10,000 passengers per hour per direction and an expected ridership of about 40,000 passengers per day in a six-minute train journey.
As an international link between Malaysia and Singapore, the RTS Link includes the building of new co-located Immigration, Customs and Quarantine (ICQ) facilities at Bukit Chagar and Customs, Immigration and Quarantine (CIQ) Woodlands North respectively.
This means the entire immigration process of leaving and entering both countries will be completed at the departing station, and arriving passengers need not go through border crossing formalities again.
Due for operation: January 2027
The EMU train design and ECRL logo are pictured at Zenith Hotel in Putrajaya December 18, 2024. — Picture by Yusof Mat Isa
Special mentions: East Coast Rail Link (ECRL)
Although not slated for completion until December 2026, the 665-km double-track rail project has nevertheless completed excavation works for 38 tunnels along its rail alignment two months ahead of schedule.
This comes after the ECRL made two tunnel breakthroughs in Selangor this month — the Serendah 1 Tunnel (3.5 kilometres) and the Rawang-Bestari Jaya Tunnel (189 metres) — putting it on track to achieve its target of 41 tunnel breakthroughs by the third quarter of 2025.
A general view of the tunnel which can be seen during the ECRL Gombak Tunnel Breakthrough Ceremony here at Gombak. — Picture by Sayuti Zainudin
With these two breakthroughs, only three tunnels remain under excavation: the twin-bore Genting Tunnel (16.39 kilometres) and the Serendah 2 Tunnel (9.85 kilometres).
It was reported that the Genting Tunnel is expected to achieve breakthrough in mid-2025, while the Serendah 2 Tunnel is targeted for breakthrough in the third quarter of 2025.
The ECRL is separated into two phases — from Kota Baru in Kelantan to the Gombak Integrated Terminal (TBG) in Selangor (Phase 1) and Gombak with Port Klang (Phase 2).
The ECRL project involves the construction of 41 tunnels with a total length of approximately 69 kilometres along its route. — Picture courtesy of Malaysia Rail Link Sdn Bhd
Once completed, the ECRL will enable travel from Kota Baru to TBG in four hours at a speed of up to160 kilometres per hour compared to approximately seven hours by road transport and provide much improved connectivity throughout the East Coast region to the West Coast.
Due for operation: Phase 1 is scheduled for completion by December 2026 with operations set for January 2027 onwards; Phase 2 is expected to be completed by December 2027 and fully operational by January 2028.

Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Sun Bus Tech, Johor council pact sets RM4,000 skilled wage benchmark
Sun Bus Tech, Johor council pact sets RM4,000 skilled wage benchmark

New Straits Times

timean hour ago

  • New Straits Times

Sun Bus Tech, Johor council pact sets RM4,000 skilled wage benchmark

ISKANDAR PUTERI: Johor's push for a future-ready workforce gained traction today as Sun Bus Tech inked a strategic pact with the Johor Talent Development Council (JTDC), to introduce a new RM4,000 starting salary benchmark for skilled workers. The new pay scale benchmark supports state's push to raise wages and retain talent in high-demand sectors, such as mobility and advanced manufacturing. Under a memorandum of understanding, Sun Bus Tech will also offer structured, on-site industrial training for trainees from the state's small and medium-sized industries (SMIs) while bridging classroom theory with hands-on practice. Johor Education and Information Committee chairman Aznan Tamin said the collaboration was "a model public-private partnership", He added that Sun Bus Tech's commitment to competitive wages and talent development supports the state's ambition to attract skilled workers and sustainable investment. Sun Bus Tech chief executive officer Shyan Phang said the RM4,000 starting pay was more than a salary upgrade; it was a message to young Malaysians. "We believe a company's strength lies in its people. With this initiative, we are opening doors for young talent not just to find jobs, but to build careers," she said. "Our collaboration with JTDC signals our commitment to grow hand-in-hand with Johor." The initiative includes tuition support, technical immersion at Sun Bus Tech's Senai facility, a The model is seen as a potential blueprint for industry-led solutions to Malaysia's growing skilled labour gap. Sun Bus Tech has emerged as a transport solutions provider, specialising in high-quality bus bodies for conventional and electric fleets. In just a year since its formal establishment, the firm has secured a partnership with Swiss engineering giant Carrosserie HESS AG. It also opened a green-rated, solar-powered headquarters at Senai Airport City. The JTDC partnership marks another milestone in the company's rapid rise. It also signals Johor's renewed focus on workforce development and industrial innovation.

No option to opt out of sharing mobile phone data, says MCMC
No option to opt out of sharing mobile phone data, says MCMC

New Straits Times

time2 hours ago

  • New Straits Times

No option to opt out of sharing mobile phone data, says MCMC

CYBERJAYA: Malaysians do not have the option to opt out of having their mobile phone data (MPD) shared with the Malaysian Communications and Multimedia Commission (MCMC). MCMC deputy managing director Datuk Zulkarnain Mohd Yasin said this follows Cabinet approval for MPD to be used as a new data source in the production of national statistics. He added that the use of MPD is not unprecedented, as many countries have already adopted similar practices. On Friday, MCMC clarified that its collection of mobile phone data from mobile network operators does not involve the access, processing or disclosure of any personally identifiable information. MCMC said the mobile phone data will be used strictly to generate official statistics to support evidence-based policymaking in the information and communications technology (ICT) sector and the tourism sector. Communications Minister Datuk Fahmi Fadzil, on Sunday, said MCMC is not seeking any personal data of users from telecommunications companies. He said MCMC's recent request to telcos was for anonymised data to support evidence-based policymaking, including for network infrastructure improvements.

Sun Bus Tech sets RM4,000 premium salary, powers Johor Talent drive
Sun Bus Tech sets RM4,000 premium salary, powers Johor Talent drive

New Straits Times

time2 hours ago

  • New Straits Times

Sun Bus Tech sets RM4,000 premium salary, powers Johor Talent drive

ISKANDAR PUTERI: Johor's push for a future-ready workforce gained major traction today as Sun Bus Tech inked a strategic pact with the Johor Talent Development Council (JTDC), to introduce a premium RM4,000 starting salary for skilled workers. The bold new benchmark in the state's industrial pay scale, aligns with Johor government's call to raise wage standards and retain talent in high-demand sectors, particularly mobility and advanced manufacturing. Under the Note of Understanding, Sun Bus Tech will also offer structured, on-site industrial training for trainees from the state's small and medium-sized industries (SMIs) while bridging classroom theory with hands-on practice. Johor Education and Information Committee chairman Aznan Tamin said the collaboration was "model public-private partnership," adding, that Sun Bus Tech's commitment to both competitive wages and talent-building supports Johor's long-term ambition to become a magnet for skilled workers and sustainable investment. Sun Bus Tech chief executive officer Shyan Phang, said the RM4,000 starting pay was more than a salary upgrade, it was a message to young Malaysians. "We believe a company's strength lies in its people. With this initiative, we are opening doors for young talent to not just find jobs, but build careers," she said. "Our collaboration with JTDC signaled our long-term commitment to grow hand-in-hand with Johor." The initiative includes tuition support, technical immersion at Sun Bus Tech's Senai facility, and assured career pathways post-training. The model is being touted as a template for industry-led solutions to Malaysia's growing skilled labour gap. Sun Bus Tech has evolved into a key mobility player specialising in high-quality bus bodies for both conventional and electric fleets. In just a year since its formal establishment, the firm has secured a strategic partnership with Swiss engineering giant Carrosserie HESS AG and opened a green-rated, solar-powered headquarters at Senai Airport City. The JTDC partnership marked another milestone in the company's rapid rise. Its is also a broader signal that Johor is doubling down on its talent and industrial future.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into the world of global news and events? Download our app today from your preferred app store and start exploring.
app-storeplay-store