How Dublin's Metrolink ‘could grievously impact homes'
Ireland's planned underground railway, the MetroLink, may go over budget by a massive €3.8 billion, and its completion date is likely not to be met.
The proposed € 9.6 billion Dublin rail line is facing a 40% overrun on its budget and is expected to leave numerous homes and businesses seriously affected, the MetroLink's own programme director has now warned.
Dr Sean Sweeney, the New Zealand-born project engineer, said the 2021 estimated cost of € 9.6 billion will have risen due to construction inflation and that the 2035 deadline is likely to be missed. Glasnevin North. Pic: MetroLink
The director highlighted that since 2021, there has been a 20% rise in construction costs.
'So do the math. The price is going to be some result of that simple multiplication. But we're doing that work now,' he said.
Dr Sweeney said the Government will have to face down 'fierce' public opposition to Dublin's MetroLink as a number of communities will be impacted by its construction.
'I deliver what I call 'nation-building projects', which make countries better,' he said. 'You leave the country better off, but that doesn't mean everyone is untouched. Some people get touched. Some people get grievously impacted. But the nation or the city is better off.'
In his experience, Dr Sweeney pointed out, public opposition to major projects disappears once they are up and running. The MetroLink map. Pic: MetroLink
On the most recent cost estimates, Dr Sweeney confirmed that the MetroLink budget was already likely to have grown from the € 9.5 billion conservative estimate to above € 11.5 billion.
He admitted that whatever the estimate ends up being, it will be exceeded, which the Government and the public must realise.
'There's been research on major rail projects, and as a global category, they on average come in about 40% over cost, and this is across lots of projects,' he told the Business Post.
'These are just too big for human beings to see that far over the horizon… [MetroLink] is a big project, and we're going to encounter things that we didn't realise existed.'
The project had been due to be completed in ten years' time, but that timeframe will not be adhered to. Griffith Park. Pic: MetroLink
'Any date I give you, until we sign up our major contractors, they are all estimates,' he said. 'Because the people that set the cost and the timeframe are your builders, and they might look at our dates and say, 'No way'. Or they might say, 'We can take a year out of that'.'
Finding a construction firm in the international market that can deal with a massive project like MetroLink was the greatest challenge, Dr Sweeney said.
And he pointed out that Ireland has 'nowhere near' the domestic construction capacity to build the MetroLink. He said that as a result of this, it must look to the international construction market.
'I noticed as soon as I got here, things take longer,' he said. 'I don't have a magic wand to sort that out.'
'There are € 160 billion worth of metro projects currently being carried out around the world, so that market is already crowded, and Ireland is not seen as attractive to bidders,' he said.
'The thing that's concerning me the most at the moment is getting an adequate response from the international construction market,' he said. 'Because if we don't, we're dead in the water.
'Now, at the moment, the international construction market is not sure about this project. It's been cancelled once…
'The Government looks like it's been treating this as a business-as-usual project, which it's not. So international firms look at that and ask, 'Are we going to spend money and effort chasing this or not?''
Dr Sweeney said Ireland moved much more slowly on infrastructure than the countries he has previously operated in.
'I noticed as soon as I got here, things take longer,' he admitted. 'And it's not a simple answer… It's a multitude of factors. And it costs Ireland. I don't have a magic wand to sort that out. And it's not going to be sorted out overnight. Maybe it'll never be sorted out.'
First mooted in 2000, the proposed 20km line, which will partially run underground between Swords and central Dublin, has been launched three times in total, but cancelled or delayed three times by successive governments, most recently in 2011 during the recession.
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Irish Examiner
an hour ago
- Irish Examiner
Central Bank 'cannot impose sanctions' on Israel, Oireachtas committee to hear
The head of the Central Bank is to tell politicians that it cannot refuse to approve the sale of Israeli war bonds despite mounting pressure to do so. Gabriel Makhlouf will say that the Central Bank is required to approve a prospectus where it meets the standards of completeness, consistency, and comprehensibility under the legislation. "Our legal obligations are clear and we do not need guidance to follow them," he is due to tell the Oireachtas Finance Committee on Wednesday. "The law is also clear that, by approving a prospectus, the Central Bank does not endorse the issuer and does not endorse the securities. "Rather, it means the Central Bank is satisfied that the issuer has disclosed the required information, in the required manner, to potential purchasers of the securities, so that investors can make their own informed investment decision." Mr Makhlouf will say that claims that the Central Bank could refuse to approve the Israeli bond prospectus on the basis of the International Court of Justice (ICJ) provisional rulings in the ongoing South Africa case is "incorrect". "The Central Bank cannot decide to impose sanctions for breaches or alleged breaches of international law," he is expected to tell the committee. Meanwhile, the Government will not be supporting a cross-party motion demanding the Central Bank end the facilitation of Israeli war bonds and will instead table its own counter motion. Calls to provide Fianna Fáil and Fine Gael TDs with a free vote on a motion supported by four opposition parties have also been ignored by the coalition parties ahead of a Dáil debate on Wednesday. The Social Democrats, Sinn Féin, Labour, and People Before Profit-Solidarity have united behind the motion that demands that the Government enact emergency legislation to explicitly force the Central Bank to stop facilitating the sale of Israel Bonds. It also calls on the coalition to advise the bank that "by acting as the enabling cog in Israel's fund-raising machine in the EU it is putting the State at risk of a charge of complicity in genocide". Read More Irish Medical Organisation joins calls for Government to help get aid to people in Gaza


Irish Post
an hour ago
- Irish Post
New plan revealed to modernise construction sector in Ireland
A NATIONAL plan has been launched in Ireland which is designed to modernise the construction industry. The Modern Methods of Construction (MMC) Action Plan provides a framework to support the adoption of modern, innovative tools that can improve the sector among the firms that work within it. It was revealed at an event held at the National Construction Training Campus in Offaly's Mount Lucas where work to build a new National Demonstration Park has now begun. "I am delighted to publish this landmark Action Plan which will assist in the accelerated adoption of Modern Methods of Construction (MMC), a significant representation of my Department's and the Government's commitment to meeting national skills needs,' Ireland's Further Education Minister James Lawless said. Minister Jim Lawless addresses the event in Mount Lucas "In addition, the National Demonstration Park will be Ireland's flagship centre for MMC showcasing, learning, and innovation. 'It will build industry and public confidence, technical expertise, and a national ecosystem around MMC." The MMC Action Plan, which has been developed by the Department of Further and Higher Education in partnership with industry and education providers, sets out 58 targeted actions across eight themes to scale the adoption of MMC across Ireland. The Demonstration Park, which is co-funded by three government departments, will be operated by the Laois-Offaly Education and Training Board (LOETB). Work has begun to build the National Demonstration Park It is designed to 'showcase leading MMC techniques, provide immersive learning, and support the growth of a national innovation ecosystem', it was confirmed this week. 'The National Demonstration Park for MMC at Mount Lucas represents a pivotal moment for construction education and training in Ireland,' Joe Cunningham, Chief Executive of LOETB, said. 'This isn't just about showcasing cutting-edge building techniques; it's about creating a living classroom where trainees and students, apprentices and professionals can experience, hands-on, the future of the industry.' He added: "The educational value of this park lies in its ability to bridge the gap between theory and practice, providing immersive learning opportunities that will equip our workforce with the vital skills needed to deliver on national housing and sustainability targets." The Demonstration Park will house live examples of MMC across a variety of MMC technologies. It will also serve as a research and training space for new entrants, upskilling professionals, and MMC innovators. The first units in the Demonstration Park are expected to be completed by the end of 2025, with training and industry and public engagement activity scaling throughout 2026.


The Irish Sun
4 hours ago
- The Irish Sun
Govt ministers could owe State thousands of euro after ‘absolutely unacceptable' pensions pay gaffes leads to 13k audits
GOVERNMENT ministers are among thousands of civil servants who have been accidentally overpaid or underpaid in their pensions in an embarrassing series of gaffes. Three separate mess ups at the National Shared Services Office has resulted in thousands of civil servants being either One of these mistakes relates to Due to an administration error, a number of current and former Other Ministers and senior civil servants will have to repay the State amounts ranging between the low hundreds up to €30,000. The NSSO began the process of contacting Ministers and former Ministers today to inform them about the mistake. READ MORE IN IRISH NEWS Another gaffe relates to the administration of Chargeable Excess Tax and Witholding There are 30 of these cases that need to be corrected with one person mistakenly overpaid up to €280,000. A third mess up by the NSSO relates to the miscalculation and under payment of pensions for some civil servants who were work sharing in their careers and spans back 20 years. Some 13,000 civil servants are having their cases audited to find out how much they need to be paid or owe the State over the mishap. Most read in Irish News Public Expenditure Minister The FURIOUS AT MISTAKES The mistakes were not the fault of any of the individuals impacted and are instead completely on the NSSO. The Minister is furious at the mistakes and has ordered the CEO of the NSSO to correct the matter immediately while also ordering a full external audit of the State pension body. He said: 'The issues that have been brought to my attention by the NSSO are completely unacceptable. 'The NSSO has responsibility for the essential function of the provision of pay and pensions to public and civil servants and it has failed in this fundamental duty. 'I have instructed the CEO of the NSSO that the multiple errors must be corrected by the NSSO as a matter of urgency, particularly regarding the treatment of retirees who had been on a work-sharing pattern in the civil service. 'I am committed to fully and comprehensively addressing this matter.' 1 Some Ministers are owed refunds of up to €20,000 Credit: Getty Images - Getty