Eskom ordered to cough up R1 billion in costs after cancelled Koeberg project

Eskom ordered to cough up R1 billion in costs after cancelled Koeberg project

IOL News4 days ago
Eskom loses court bid to fend off R1bn payment after cancelling a contract.
Image: Supplied
Eskom has been ordered to pay close to R1 billion to French nuclear contractor Framatome, after the Western Cape High Court found the utility refused to pay damages after it cancelled a contract to install steam generators at Koeberg nuclear power station.
The ruling stems from a 2014 agreement Eskom originally concluded with Areva, which was later ceded to Framatome. The deal covered the design, manufacture and installation of six replacement steam generators – three for each unit at Koeberg.
Framatome, which has been in operation for 60 years, was contracted to supply and install two sets of three replacement steam generators, one set to be installed in each of the reactor buildings at units 1 and 2 at Koeberg during separate planned outages of these units.
These installations were meant to take place during a scheduled maintenance outage, which kept getting postponed. Two months after the outage was finally scheduled to happen, 'Eskom informed Framatome that it would not be continuing with the steam generator replacement,' the judgement said.
As a result of the cancellation of the deal, Eskom's project manager 'acknowledged that Eskom's decision to postpone the work constituted a compensation event,' the judgment read.
Although the project manager had acknowledged that Eskom's cancellation triggered compensation, he determined that the value of compensation was nil.
The entire matter then went to arbitration, where the adjudicator ordered that Eskom must pay compensation for cancelling the contract, including for storing equipment, as well as implementation activities, which work had been wasted by Eskom delaying the date of the planned maintenance outage.
Video Player is loading.
Play Video
Play
Unmute
Current Time
0:00
/
Duration
-:-
Loaded :
0%
Stream Type LIVE
Seek to live, currently behind live
LIVE
Remaining Time
-
0:00
This is a modal window.
Beginning of dialog window. Escape will cancel and close the window.
Text Color White Black Red Green Blue Yellow Magenta Cyan
Transparency Opaque Semi-Transparent Background Color Black White Red Green Blue Yellow Magenta Cyan
Transparency Opaque Semi-Transparent Transparent Window Color Black White Red Green Blue Yellow Magenta Cyan
Transparency Transparent Semi-Transparent Opaque
Font Size 50% 75% 100% 125% 150% 175% 200% 300% 400% Text Edge Style None Raised Depressed Uniform Dropshadow Font Family Proportional Sans-Serif Monospace Sans-Serif Proportional Serif Monospace Serif Casual Script Small Caps
Reset
restore all settings to the default values Done
Close Modal Dialog
End of dialog window.
Advertisement
Video Player is loading.
Play Video
Play
Unmute
Current Time
0:00
/
Duration
-:-
Loaded :
0%
Stream Type LIVE
Seek to live, currently behind live
LIVE
Remaining Time
-
0:00
This is a modal window.
Beginning of dialog window. Escape will cancel and close the window.
Text Color White Black Red Green Blue Yellow Magenta Cyan
Transparency Opaque Semi-Transparent Background Color Black White Red Green Blue Yellow Magenta Cyan
Transparency Opaque Semi-Transparent Transparent Window Color Black White Red Green Blue Yellow Magenta Cyan
Transparency Transparent Semi-Transparent Opaque
Font Size 50% 75% 100% 125% 150% 175% 200% 300% 400% Text Edge Style None Raised Depressed Uniform Dropshadow Font Family Proportional Sans-Serif Monospace Sans-Serif Proportional Serif Monospace Serif Casual Script Small Caps
Reset
restore all settings to the default values Done
Close Modal Dialog
End of dialog window.
Next
Stay
Close ✕
After some back and forth between the parties and the adjudicator, during which the parties didn't agree on costs, 'Eskom made it clear that it had no intention of providing the adjudicator with any further information or participating any further in the adjudication process,' the ruling read.
As a result, the adjudicator issued a determination of the damages amount, and Eskom decided to take the issue to the Western Cape High Court, arguing that the amount in damages was not determined by the date it was due – voiding his determination.
In defending Eskom's legal action, Framatome argued that none of the arbitration proceedings were improper, nor was the adjudicator abusing his power.
The Judge ruled that 'there is no basis to set aside the decisions of the adjudicator which are valid and binding. In terms of the parties' contract Eskom was obliged to comply therewith.'
Eskom, it found, had to comply with its contractual obligations. The court found that Framatome was entitled to the full amount it sought.
In addition to the R1bn payment, Eskom had to pay interest and costs.
IOL
Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Eskom system remains stable as winter demand peak approaches
Eskom system remains stable as winter demand peak approaches

The Citizen

time35 minutes ago

  • The Citizen

Eskom system remains stable as winter demand peak approaches

This comes as the power system shows sustained reductions in unplanned outages while effectively managing winter electricity requirements. South Africa's power system continues to operate reliably as the country navigates the winter electricity demand period, with Eskom maintaining grid stability without load shedding for more than two months. The utility announced on Friday, 25 July 2025, that 3,960MW of generation capacity will return to service ahead of Monday evening's peak demand period to further strengthen grid stability. This comes as the power system shows sustained reductions in unplanned outages while effectively managing winter electricity requirements. No Eskom load shedding since mid-May Eskom has not implemented load shedding since 15 May 2025, recording only 26 hours of power cuts between 1 April and 24 July 2025. The achievement marks a significant improvement in system reliability during the critical winter period. 'With 37 days of Eskom's Winter Outlook period still remaining, the system remains well-positioned to maintain stability and meet demand effectively,' the utility stated. As of Friday, unplanned outages stood at 11,695MW while available generation capacity reached 30,236MW. Friday's electricity demand was expected to reach 27,715MW, with current capacity sufficient to meet both daily requirements and anticipated weekend demand. ALSO READ: No fines or penalties over Koeberg delays, Eskom says Eskom system performance shows improvement During the week of 18 to 24 July 2025, planned maintenance averaged 5,050MW. The Energy Availability Factor (EAF) ranged between 62% and 66% over the same period, with the month-to-date average increasing to 63.11%. 'To further strengthen grid stability, Eskom is planning to return a total of 3,960MW of generation capacity to service ahead of the evening peak on Monday, 28 July 2025, and throughout the coming week,' the utility confirmed. The Unplanned Capability Loss Factor (UCLF), which measures generation capacity lost due to unplanned outages, decreased to 28.99% between 1 April and 24 July 2025. This represents a reduction of approximately 0.5% compared to the previous week, though it remains about 2.4% higher than the 26.60% recorded during the same period last year. As of 24 July, the UCLF stood at 23.79%, indicating notable performance improvements. ALSO READ: Ekurhuleni mayor to suspend electricity tariff hike after protests in Thembisa Reduced reliance on emergency generation According to Eskom, the open-cycle gas turbine (OCGT) load factor decreased significantly this week to 1.86%, down from 8.6% recorded during the previous week of 11 to 17 July 2025. This reduction indicates a decrease in reliance on expensive emergency generation. 'From 1 April to 24 July 2025, diesel spend remains within the budget allocated for 1 April to 31 July 2025,' Eskom said. Eskom winter outlook remains valid The utility's Winter Outlook, covering the period ending 31 August 2025, remains unchanged. The outlook suggests that load shedding will not be necessary if unplanned outages remain below 13 000 MW. 'It indicates that load shedding will not be necessary if unplanned outages stay below 13,000MW. If outages rise to 15,000MW, load shedding would be limited to a maximum of 21 days out of 153 days and restricted to Stage 2,' the utility explained. ALSO READ: Nersa's mistakes will hit you hard Diesel spend correction Eskom issued a correction regarding diesel expenditure figures published in the previous week's Power Alert. 'We identified a discrepancy in the reported diesel amount. The actual diesel spend should have been R5.554 billion, not R5.897 billion as stated,' the utility corrected. The utility explained that the figure 5,897 was actually the R/MWh rate and was mistakenly captured as total spend instead of the per-unit cost. 'This regretfully resulted in an inadvertent overstatement of the diesel spend, which we hereby correct.' ALSO READ: Load shedding: Hiccup in Eskom's power plans For the week of 18 to 24 July 2025, unplanned outages averaged 11 555MW. This represents a decrease from the previous week but remains 1 077MW higher than the same period last year and 1,445MW below the base case estimate of 13 000MW. According to Eskom, for the financial year-to-date, planned maintenance has averaged 5 221MW, representing 11.11% of total generation capacity. This reflects a decrease from the previous week but shows a 0.7% increase compared to the same period last year. 'The year-to-date EAF stands at 59.42%, excluding the 720MW contribution from Kusile Unit 6, which has been supplying electricity to the national grid since 23 March 2025, although not yet in commercial operation,' Eskom reported. This figure remains below the 62.42% recorded during the same period last year, mainly due to a 2.4% increase in unplanned maintenance compared to the previous year. ALSO READ: City Power denies claims its headquarters raided by Hawks Fuel costs and generation output Between 1 April and 24 July 2025, Eskom spent R5.616 billion on fuel for its OCT plants, generating 952.41GWh of electricity. This output significantly exceeds the 493.16GWh generated during the same timeframe last year. The year-to-date load factor for OCTs has marginally decreased to 10.11%, reflecting a 0.53% decrease compared to the previous week. However, this figure remains substantially higher than the 5.23% recorded during the same period last year. Customer advisory on infrastructure protection With load shedding suspended and electricity demand rising during winter, Eskom has urged customers to act responsibly to help safeguard the power system. The utility highlighted concerns about illegal connections and meter bypassing, which constitute theft and strain the network infrastructure. These activities often lead to transformer overloads, equipment damage, and in severe cases, explosions and extended outages. 'To protect critical infrastructure, Eskom is compelled to implement load reduction by switching off lower during peak hours in high-risk, isolated areas to prevent potential damage. 'To help maintain a stable and uninterrupted electricity supply, customers are strongly urged to avoid bypassing meters and refrain from illegal connections. Electricity should be purchased only through Eskom-accredited vendors, and users are encouraged to regularise their electricity usage,' the utility advised. 'These steps are essential to ensuring safe, reliable, and fair access to electricity for all. Eligible households are encouraged to register for free basic electricity with their local municipalities,' Eskom added. The utility will provide its next update on Friday, 1 August 2025, or communicate significant changes as they occur. READ NEXT: Get your blankets out: Double cold snap to hit Gauteng this week

Here's Gauteng's load reduction schedule for the rest of July
Here's Gauteng's load reduction schedule for the rest of July

The Citizen

time35 minutes ago

  • The Citizen

Here's Gauteng's load reduction schedule for the rest of July

Eskom's load reduction schedule indicates that several areas across Gauteng will continue to face scheduled power cuts during peak hours. Gauteng residents continue to face an uneven experience with load reduction, as Eskom-serviced areas continue to face scheduled power cuts. Eskom conducts a daily load reduction programme that runs from Monday to Sunday. Consumers can expect approximately six and five hours of outages, with different time slots for different areas. Affected areas under Eskom's load reduction schedule The current Eskom load reduction schedule shows that numerous areas across Gauteng will continue to experience scheduled power cuts during peak periods. Areas experiencing morning load reduction between 5am and 9am include Duduza, Protea Glen, and Tsakane. Other affected areas include Dobsonville, Mabopane, and various settlements across Gauteng. ALSO READ: Eskom power system remains stable as winter demand peak approaches Evening load reduction between 5pm and 10pm impacts regions including Mofolo, Slovoville, Dlamini, Kagiso, Khutsong and surrounding areas. Other affected zones include Cuba, Graceland, Havana, Jetta, Lakeside, and various extensions in surrounding regions. The schedule operates on a seven-day rotation, with different areas affected on different days of the week, giving residents some predictability about when they might experience power outages. This week, the affected areas include: Rethabiseng Moroka Kudube Meadowlands Riverside Skhosana Chiawelo Zola Langaville To see if your area is affected, click on or download the document below Load-reduction-schedule-GAUTENG-JULY-2025 NOW READ: No fines or penalties over Koeberg delays, Eskom says

Audi cuts forecast over US tariffs and restructuring costs
Audi cuts forecast over US tariffs and restructuring costs

TimesLIVE

timean hour ago

  • TimesLIVE

Audi cuts forecast over US tariffs and restructuring costs

German carmaker Volkswagen's premium brand Audi lowered its full-year financial guidance on Monday, citing the impact of higher US import tariffs and ongoing restructuring costs. The Ingolstadt-based company expects revenue of between €65bn (R1,355,406,000,000) and €70bn (R1,459,560,200,000), down from its previous forecast of €67.5bn (R1,407,537,000,000) to €72.5bn (R1,511,687,350,000). Audi also cut its operating margin forecast to 5% to 7%, compared to the earlier range of 7% to 9%. Audi said it is assessing the implications of the trade deal reached between the US and the EU on Sunday. The agreement set a 15% baseline US tariff on imports from the EU, including cars, which had previously faced customs duties of 27.5%. "Should the 15% tariff stay in place long-term, it would put Audi at a competitive disadvantage because its key peers have a more pronounced US production footprint," said Fabio Hoelscher, an analyst from Warburg Research. Audi is among the carmakers most exposed to US tariffs as it has no manufacturing facilities in the US. Though the deal provides clarity on the new tariff regime, enabling better operational and strategic planning, the 15% rate represents a structural shift from the 2.5% rate before US President Donald Trump took office, said Pal Skirta, equity analyst from Metzler Equities. That leaves German carmakers facing persistently higher US tariffs on their exports and long-term competitiveness challenges, he said. The Volkswagen Group also cut its full-year guidance on Friday after taking a $1.5bn (R26,781,448,350) tariff hit in the first half of the year. Global carmakers have booked billions of losses and some issued profit warnings due to US import tariffs. The European industry is also facing stiffening competition from China and domestic regulations aimed at speeding up the electric-vehicle transition.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store