Monsoon causes ‘minor damages' to NHPC's Subansiri hydro project; commissioning delayed further
The project cost has also been anticipated to escalate more than four times to around Rs 26,075 crore at the time of completion next year from the initial estimate of Rs 6,285 crore in December 2002.
The commissioning of the Subansiri Lower Hydro Electric Project has been further delayed till May 2026 from the earlier announced 2023-24 fiscal end, which was already more than 10 years late from the original completion schedule of December 2012, the NHPC said.
Guwahati, Jun 12 (PTI) NHPC's much-delayed 2,000 MW Subansiri hydro project along Assam-Arunachal Pradesh border has suffered 'minor damages' during the recent monsoon rains though the main structure remained unaffected, the company said on Thursday.
'No such structural damage has occurred to the dam structure which may cause safety concerns. Only minor damages to the spillway lip portion have occurred during this monsoon season,' NHPC said in a statement.
During the monsoon season, the river flow is accompanied by silt, wooden logs and boulders, it added.
'Rolling of the boulders and wooden logs causes minor damages on the upper surface of the spillway glacis and lip portion during the passing of the river flow from the spillway gates. The functionality of the dam is not affected by such minor damage,' the company said.
After the passing of the monsoon season, the area shall be inspected, and the minor damages shall be repaired and restored as a general practice in any hydroelectric project, it added.
The company asserted that there is no risk at all to the dam structure, which is 116 metres high from the river bed level.
The Subansiri Lower Hydro Electric Project, which faced multiple bottlenecks since its inception stage, has been delayed several times and its deadline for commissioning has been revised on many occasions.
On its official website, NHPC said, 'Date of Commercial Operation (COD) – Project is likely to be completed in MAY 2026.' It also stated that the project cost has now been anticipated to be Rs 26,075.54 crore on completion compared to Rs 6,285.33 crore as per the initial estimate in December 2002.
According to a company estimate in January 2020, the cost of the mega project, which was originally scheduled to be commissioned in December 2012, had escalated to around Rs 20,000 crore.
On completion, the Subansiri project, which is a run-of-river scheme, will generate around 7,500 million units of power annually in a '90 per cent dependable year' with the help of eight Francis turbines of 250 MW capacity each.
In June 2023, commissioning of the 2,000 MW hydro project was postponed till the end of the 2023-24 fiscal with more than 90 per cent of the total work of the project completed by then.
The Assam government in March 2022 had informed the state Assembly that partial commissioning of the 2,000 MW project was postponed till August 2022.
In December 2020, the company had set a target of March 2022 for commissioning the project, being constructed at Gerukamukh along the Assam-Arunachal Pradesh border.
NHPC had commenced the construction work of the Subansiri project in January 2005 after obtaining forest clearance in October 2004.
Construction work of the project was stalled from December 2011 to October 14, 2019 due to protests by locals and many groups fearing safety and downstream impact.
To address the concerns of the agitators, multiple committees were formed by the Assam government and the Centre. The outcomes of their reports varied from one to another.
After clearing all the legal issues by the National Green Tribunal (NGT), the NHPC re-started construction of the project from October 15, 2019. PTI TR NN
This report is auto-generated from PTI news service. ThePrint holds no responsibility for its content.

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Indian Express
18 minutes ago
- Indian Express
PU's UIAMS sees highest package of Rs 16.42 LPA, average stands at Rs 6.84 LPA
As many as 87 MBA students at the University Institute of Applied Management Sciences (UIAMS), Panjab University (PU), Chandigarh, have secured campus placements, with 9 of them receiving an impressive Rs 16.42 lakh per annum (LPA) package, the highest package for the institute students this season, with the average being Rs 6.84 LPA. The placement drive witnessed participation from 26 leading companies across diverse sectors, including banking, finance, IT, insurance, marketing, and consulting. Federal Bank, Mahindra Finance, Capgemini, Bunge, Tirupati HealthCare, SBI Mutual Funds, HDFC Life, Policy Bazaar, Growwtide, and Vodafone Idea, were some of the major recruiters. The recruitment season saw companies offering roles such as management trainees, sales executives, relationship managers, business development managers, client consultants, and HR analysts to the students. Notably, Federal Bank emerged as the highest-paying recruiter, offering nine positions with the highest offer being 16.42 LPA. Federal Bank has been recruiting UIAMS MBA students since 2012. Mahindra Finance, another regular recruiter, offered Rs 10 LPA to three students. Appreciating the placements, PU Vice-Chancellor Renu Vig said, 'students of various departments of the PU continue to shine academically and professionally. The remarkable placement outcomes reflect the strength of our academics and the employability of our students. I congratulate the placement team, teachers, and students on their achievements'. UIAMS Director Anupreet Kaur Mavi has congratulated the students and the placement team, stating, 'we are proud of the career paths our students are embarking on. The numbers of placements reflect the quality of education and the institute's growing reputation among recruiters'. Dr Amandeep Singh Marwaha, training-cum-placement Officer, UIAMS, expressed his appreciation for the students' efforts and acknowledged the continued support of the industry partners. 'Our focus has always been to align academic excellence with industry expectations. This year's placements reflect the quality, resilience, and preparedness of our students,' Marwaha said.


NDTV
23 minutes ago
- NDTV
After Dreamliner Crash, Insurance Cost May Raise Airfare By 2-5%
New Delhi: The aviation insurance industry may consider raising the premium paid by airlines in the next cycle, following the crash of the Air India Boeing 787-8 Dreamliner in Ahmedabad. A mix of expanding exposure to international routes, regulatory scrutiny, and high-value claims is expected to make the price of premium more expensive than it is now. An expert told NDTV Profit if the aviation industry passes on the rising cost of insurance premium to consumers, airfare may see a rise of up to 2 to 5 per cent. Air India and IndiGo have already renewed their policies for the year, said Sourav Biswas, business head - aviation insurance at Alliance Insurance Brokers. However, there could be a marked rise in premiums in the next billing cycle, Mr Biswas said. The loss of Air India's Boeing 787-8 Dreamliner along with the deaths of 241 people who were on board and 10 at the doctors' hostel where the plane crashed comes at a time when a multi-billion-dollar court ruling in the UK ordered global reinsurers to compensate for aircraft seized by Russia due to geopolitical tension. The timing of the UK court order and the crash, one of the deadliest aviation accidents in India, would add more strain on reinsurers who deal with hull insurance, which covers the aircraft itself, and liability insurance, which includes both passenger legal liability and third-party liability. The sum total of all these factors and India being one of the fastest growing markets for the aviation industry will likely raise the premiums. India's aviation industry's insurance premiums have been around Rs 1,000 crore historically, but it may get disrupted and the figure could change drastically. Aviation insurance for big airlines such as Air India are given on a fleet basis and reinsured across global markets like London and New York, said Narendra Bharindwal, President, Insurance Brokers Association of India. A single insurer does not take responsibility for the entire risk coverage; it is distributed among global reinsurers, with shares ranging from 1.5 per cent to 2 per cent. A lead reinsurer usually takes up to 15 per cent risk. "This incident, along with others in recent months, will likely result in a hardening of the aviation insurance market, not just for the airline involved, but across the entire aviation sector," Mr Bharindwal said. The Life Insurance Corporation of India (LIC) today announced immediate measures to ease the financial burden on the families of those who died in the plane crash. The insurer said that it would expedite claim settlements and offer concessions to support the affected families.


The Print
24 minutes ago
- The Print
Garuda Aerospace sets up agri-drones indigenisation facility near Chennai
Spread across 35,000 sq ft at Thalambur, near the city, the state-of-the-art facility was inaugurated by Union Minister of State for Rural Development Kamlesh Paswan on Thursday. The facility, a first-of-its-kind initiative, augments Garuda Aerospace's existing manufacturing unit located near Chennai and a major leap in advancing drone manufacturing. The products that would be produced at the facility include 7 subsystems (of Unmanned Aerial Systems), 33 parts among others. The production would be covered under the Centre's ambitious 'Atmanirbhar Bharat' campaign. Chennai, Jun 13 (PTI) Drone manufacturer Garuda Aerospace has established an Agri-Drone Indigenisation facility near the city to design and manufacture advanced Unmanned Aerial Systems among many others, a top official said on Friday. Garuda Aerospace also launched 300 Centres of Excellence, established in association with various educational institutions and industry partners across the country. It would advance drone innovation, research and skill development. A Train-the-Trainer programme aimed at enhancing skills on operating the drones was also unveiled on the occasion. 'Our new Agri-Drone Indigenisation facility is equipped to manufacture over 33 different parts and 7 subsystems. This reinforces our commitment to self-reliance,' Garuda Aerospace founder and CEO Agnishwar Jayaprakash said in a release here. 'All of these efforts and initiatives have powered Garuda Aerospace to become one of India's most valuable drone startups, with a fast-growing global footprint,' he said. A live demonstration of Agri-Drones showcasing Garuda Aerospace's commitment to fostering self-reliance and innovation within the burgeoning drone ecosystem was also conducted on the occasion. PTI VIJ VIJ KH This report is auto-generated from PTI news service. ThePrint holds no responsibility for its content.