logo
Historic Stirling bridge to reopen after nine months of £1.2m restoration works

Historic Stirling bridge to reopen after nine months of £1.2m restoration works

Daily Record2 days ago

The overpass - which sits on the B8034, over the River Forth, between Port of Menteith and Arnprior, in Stirling - saw a £1.2million repair project begin, with work originally scheduled to be complete by mid-March.
The historic Cardross Bridge is set to reopen next week after a nine-month-long restoration effort.
Restoration works on the 250-year-old category B-listed structure began last September, with an initial completion date set for mid-March, but a series of setbacks has kept the bridge closed.

Stirling Council has now confirmed that the bridge, which spans the River Forth on the B8034 between Port of Menteith and Arnprior, is expected to be accessible again next week following a £1.2million repair project.

Motorists have been contending with a 12-mile diversion since the closure, which will persist until the works are finalised and the route re-opens.
The B8034 has been fully closed since September, with an alternative route via Thornhill in operation.
A council spokesperson this week said: "Based on the latest information from the contractor working on the bridge, it is expected to reopen next week (week commencing June 16).
"We will provide another update to the local community tomorrow (11 June) on this following the completion of some critical activities at the site.
"Once again, we would like to thank all local residents and businesses for their patience and understanding during these essential works and we continue to work with the contractor to re-open the bridge at the earliest opportunity."

Stirling Council, with the guidance of a NatureScot, sanctioned a specialist ecologist to oversee the repairs.
The original March completion date was postponed until May. After additional repair works were identified during excavation works, the repair was extended again in to mid-June.
In September last year, a Stirling Council spokesperson said that the local community would be fully informed on progress with regular updates and confirmed that "regular engagement sessions" would be held throughout the work.

Additionally, the spokesperson said: "We would like to thank all local residents and businesses for their patience and understanding during these essential works."
This conservation effort stems from Stirling Council's hefty £6.6m investment into improving its road network.

It is one of 72 projects taking place across the council area as part of its commitment to maintain and upgrade its road and footway network.
During the works, contractors have removed and rebuilt the bridge walls and undertook a full repointing of the stone using traditional materials. Cracks have also been repaired, with works to protect the bridge from river erosion, as well as the installation of a new bridge deck.
Once refurbishment is complete, the bridge will enforce a maximum load capacity of 10 tonnes.

The closure of the key road has caused disruption for residents in both Port of Menteith and Arnprior, as well as businesses along the route.
This includes holiday cottages, cabins and celebrity TV chef Nick Nairn's restaurant, Nick's at Port of Menteith.
The bridge was originally constructed in 1774 using funds from forfeited lands.

Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Raploch war memorial plans take next step as long-running project moves closer
Raploch war memorial plans take next step as long-running project moves closer

Daily Record

timea day ago

  • Daily Record

Raploch war memorial plans take next step as long-running project moves closer

The group behind the memorial plans have found more than 120 men and women who served in World War Two from the area - with hopes to commemorate their sacrifice with a permanent monument. Raploch is stepping closer to achieving its goal of creating a lasting monument to its war dead. Rev Barry Hughes and Raploch Community Council have now lodged a planning application with Stirling Council planners to install the memorial at the north west corner of Raploch Community Campus on Drip Road. ‌ A fundraising campaign was launched last year in a bid to raise £30,000 for the war memorial to honour the community's fallen. ‌ In 2019, two local residents discovered not only the names of over 60 local men who served their country and were among the fallen of World War II, but also where they had lived in Raploch. This discovery gave the impetus for a project to build a war memorial in the Village Square outside the Raploch Community Campus, to commemorate all those from Raploch who have lost their lives in conflict. The Raploch War Memorial Group formed and then discovered over 120 men and women who also served during World War II and were injured, prisoners of war or awarded and recognised for their actions during service. They also aim to honour these men and women with a history book that has some of the stories they have discovered. The group said last year: 'We are pleased to announce that we are now in a position to begin our fundraising for the war memorial. 'It has taken us longer than we expected but we didn't want to start this process until we had everything in place to begin the official application for planning permission. ‌ 'We are hoping to raise £30,000 to fund the construction of the war memorial.' A public consultation in the area in 2022 asked people to vote on a number of options for the memorial. Asked what they would prefer to see on the memorial, 55 per cent said a list of the names of the fallen in all conflicts of the 20th/21st centuries; 30 per cent said a tribute quote to all the fallen in all conflicts; 7.5 per cent opted for only a list of the names of the fallen in World War II; and 7.5 per cent went for 'other'. ‌ A second question asking people whether the top two winning designs and quote from a local children's war memorial design competition should be included saw 94.59 per cent of respondents say yes, with 5.41 per cent saying no and 2.7 per cent unsure. The proposals for the permanent memorial to the fallen were dreamt up by local pensioner Mick Lowe and partnerships with local groups including Raploch Community Partnership, St Mark's and St Margaret's, Stirling Council and the Salvation Army have been formed for the project. The project came about after pensioner Mick began researching soldiers to find out more about his dad John, who died in 1948 after being a prisoner of war during World War Two. ‌ Mick discovered a total of 68 soldiers who died during the Second World War from Raploch. But the proposals would see a war memorial erected to pay tribute to the casualties from several conflicts who originally hailed from Raploch. Six streets in a new housing development being built in Raploch are also being named after men from the area who died in World War Two. Brewster Crescent, Fairley Crescent, Hulston Road, Turner Street, Spencer Place and McDonald Court, will become lasting legacies of six of those who lost their lives in the conflict, and their fellow fallen comrades from the community. Private Robert Brewster of 21 Hawthorn Crescent, Pte John Fairley of 43D Raploch Road, Pte William Hulston of 8 Hawthorn Crescent, Pte James Turner of 23 Hawthorn Crescent, Pte Ian Spencer of 4 Haig Avenue, and Pte James McDonald of 64 Drip Road are amongst a list of 48 names compiled by Raploch man Mr Lowe. The formal planning application lodged last week states: 'Raploch Community Council wishes to erect a war memorial adjacent to the Raploch community campus building. 'The war memorial will be 2000mm x 1500m wide, will be set on a raised foundation, and then be 2860mm high; it will be made out of sandstone.'

Restoration work begins in Stirling on historic Victorian villa destroyed in fire
Restoration work begins in Stirling on historic Victorian villa destroyed in fire

Daily Record

time2 days ago

  • Daily Record

Restoration work begins in Stirling on historic Victorian villa destroyed in fire

The first phase of restoration works at the 19th century Victorian villa - which was gutted by fire back in March last year - is now underway. Efforts to restore a derelict 19th century Victorian villa within the grounds of Stirling Council's Old Viewforth headquarters have commenced, following its devastation by fire last year. The first phase of restoration works at Langgarth House are now underway following the fire back in March last year - which caused extensive damage to the building. ‌ The initial stage of works commenced in late May to secure and salvage key elements of the building while removing parts that have been damaged beyond repair. ‌ The works, being overseen by specialist advisors, will allow officers to fully assess the building to protect the remaining fabric of the building and structural elements. It's estimated that this phase of work will take place over 18 weeks and will be funded entirely by insurance monies. Langgarth House is included within the Viewforth Masterplan which is being marketed for future development following approval by Councillors which was granted in October last year. ‌ Stirling Council Leader, Cllr Gerry McGarvey said: "Everyone in Stirling cherishes our remarkable built heritage and I'm pleased to see work underway to preserve and make safe as much of the historic Lanngarth House building as possible. Every effort will be made to ensure that key features of the building are retained as part of the work. "It's entirely right that this building should be retained as part of the redevelopment of the Viewforth site and I look forward to seeing work progress in the coming weeks." ‌ The derelict category B-listed building was engulfed in flames as fiore crews battled through the night to bring it under control. Fortunately, nobody was injured in the incident, which caused extensive damage, including to part of the roof and upper floor. Two teenagers appeared in court in connection with the fire. The then Stirling MP Alyn Smith Stirlingdescribed the fire as a "sad sight" and also thanked police and firefighters who attended. ‌ The B-listed property, built in 1897, most recently was used as council offices along with the now demolished New Viewforth and Old Viewforth, the current headquarters of Stirling Council. However, forseveral yearsit has been included in the Buildings at Risk Register for Scotland, which highlights properties of architectural orhistoric meritthroughout the country that are considered to be at risk or under threat. ‌ Langgarth was vacated in 2009 and has been marketed for sale and lease by Stirling Council on various occasions since. Langgarth was labelled 'at risk' in 2012, but while monitored by the council since, the uncertainty of future use of the wider Viewforth site - including years discussing the controversial and now defunctViewforth Link Road - hinderedprogress in successfully securing any potential new owners or leaseholders. In the months before the fire, councillors had been reviewing detailed options for the disposal of the wider Viewforth site, which would see the authority retain and refurbish its headquarters at Old Viewforth. At a full council meeting a month prior, chief operating officer for infrastructure and environment Brian Roberts had confirmed that Langgarth would be part of a disposal strategy for the whole site being brought forward to a council meeting in June.

Historic Stirling bridge to reopen after nine months of £1.2m restoration works
Historic Stirling bridge to reopen after nine months of £1.2m restoration works

Daily Record

time2 days ago

  • Daily Record

Historic Stirling bridge to reopen after nine months of £1.2m restoration works

The overpass - which sits on the B8034, over the River Forth, between Port of Menteith and Arnprior, in Stirling - saw a £1.2million repair project begin, with work originally scheduled to be complete by mid-March. The historic Cardross Bridge is set to reopen next week after a nine-month-long restoration effort. Restoration works on the 250-year-old category B-listed structure began last September, with an initial completion date set for mid-March, but a series of setbacks has kept the bridge closed. ‌ Stirling Council has now confirmed that the bridge, which spans the River Forth on the B8034 between Port of Menteith and Arnprior, is expected to be accessible again next week following a £1.2million repair project. ‌ Motorists have been contending with a 12-mile diversion since the closure, which will persist until the works are finalised and the route re-opens. The B8034 has been fully closed since September, with an alternative route via Thornhill in operation. A council spokesperson this week said: "Based on the latest information from the contractor working on the bridge, it is expected to reopen next week (week commencing June 16). "We will provide another update to the local community tomorrow (11 June) on this following the completion of some critical activities at the site. "Once again, we would like to thank all local residents and businesses for their patience and understanding during these essential works and we continue to work with the contractor to re-open the bridge at the earliest opportunity." ‌ Stirling Council, with the guidance of a NatureScot, sanctioned a specialist ecologist to oversee the repairs. The original March completion date was postponed until May. After additional repair works were identified during excavation works, the repair was extended again in to mid-June. In September last year, a Stirling Council spokesperson said that the local community would be fully informed on progress with regular updates and confirmed that "regular engagement sessions" would be held throughout the work. ‌ Additionally, the spokesperson said: "We would like to thank all local residents and businesses for their patience and understanding during these essential works." This conservation effort stems from Stirling Council's hefty £6.6m investment into improving its road network. ‌ It is one of 72 projects taking place across the council area as part of its commitment to maintain and upgrade its road and footway network. During the works, contractors have removed and rebuilt the bridge walls and undertook a full repointing of the stone using traditional materials. Cracks have also been repaired, with works to protect the bridge from river erosion, as well as the installation of a new bridge deck. Once refurbishment is complete, the bridge will enforce a maximum load capacity of 10 tonnes. ‌ The closure of the key road has caused disruption for residents in both Port of Menteith and Arnprior, as well as businesses along the route. This includes holiday cottages, cabins and celebrity TV chef Nick Nairn's restaurant, Nick's at Port of Menteith. The bridge was originally constructed in 1774 using funds from forfeited lands.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into the world of global news and events? Download our app today from your preferred app store and start exploring.
app-storeplay-store