Drainage to Sukhna Choe to keep Chandigarh's first underpass flood-free

Drainage to Sukhna Choe to keep Chandigarh's first underpass flood-free

Time of India4 days ago
Chandigarh: As a major component of the first flyover project at the Sector 29/31/Industrial Area Phase 1 and 2 rotary on National Highway (NH) 5 is a four-lane underpass, the Chandigarh administration has planned a new dedicated drainage line from the said rotary to Sukhna Choe.
The line will drain out water from the rotary and roads linked to the underpass.
The approximately 2.4 kilometre drainage line will be laid to prevent waterlogging and flooding of the underpass. "Since the current storm line is small and narrow, the authority inspected the area and found the requirement for a big drainage line to be connected with Sukhna Choe. A detailed plan was worked out. This will be one of the key components of the flyover work, which will be financed from the Rs 240 crore approved by the ministry of road transport and highways (MoRTH).
With this project, the planned underpass will be completely free of any major waterlogging and flooding," a senior officer of the Chandigarh administration told TOI.
Besides the new drainage line, Chandigarh administration also plans to shift all other key utility services from the sector 29/31/Industrial Area Phase 1 and 2 rotary site, where the 1.6-kilometre flyover is to be constructed. The cost of this exercise is yet to be worked out, but sources said that the initial assessment was pegged at around Rs 30 crore.
by Taboola
by Taboola
Sponsored Links
Sponsored Links
Promoted Links
Promoted Links
You May Like
Is this legal? Access all TV channels without a subscription!
Techno Mag
Learn More
Undo
Work on shifting will also be financed from the Rs 240 crore approved by the ministry of road transport and highways for the flyover project.
"All other utility services like existing water supply lines, existing storm lines, 66 KV electricity line and tertiary treated water lines will be shifted before the construction of the project starts. The shifting will be planned in a way that the general public is not affected in any manner," sources in the UT told TOI.
Flyover Box: The flyover project
1: Initially, the UT prepared a financial estimate of Rs 183 crore for the first flyover project in 2019
2: UT received the lowest bid of Rs 137 crore
3: The project was stalled due to the Covid pandemic
4: The rates of the project escalated
5: A revised estimate of Rs 203 crore was prepared with deliberation of the previously selected bidder, but it could not work out
6: Now, MoRTH has approved Rs 240 crore to construct the first flyover in the city. The fresh tender exercise will be undertaken to hire a contractor
Box:
The Chandigarh administration has clarified that since 472 trees were to be axed for the project, 2,799 trees have been planted at four different locations to compensate for the same.
Permission for felling of 472 trees was accorded subject to the condition that five saplings would be planted in lieu of one axed tree. Keeping this in view, the administration decided to plant 2,799 saplings in lieu of 472 trees.
Details of trees planted
Location---------------------------------------------------------Number of planted trees
1: Palm Garden, Sector 42, Chandigarh--------------------958 trees
2: Spring Garden, Sector 53, Chandigarh------------------411 trees
3: Leisure Valley, Sector 51, Chandigarh-------------------787 trees
4: Purv Marg, Sector 31 to 47, Chandigarh-----------------643 trees
MSID:: 123077027 413 |
Get the latest lifestyle updates on Times of India, along with
Friendship Day wishes
,
messages
and
quotes
!
Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Reliance unveils four tech-driven growth engines for future expansion
Reliance unveils four tech-driven growth engines for future expansion

Business Standard

time19 minutes ago

  • Business Standard

Reliance unveils four tech-driven growth engines for future expansion

Reliance Industries has built four high-powered growth engines of retail, digital services, media and entertainment, and new energy to propel the conglomerate's next phase of expansion, Chairman Mukesh Ambani said. Parallelly, Reliance is reshaping itself into a new-age deep-tech enterprise, he said in a message to shareholders in the firm's latest annual report. The firm, which traditionally had oil and petrochemicals as the growth drivers, has in the last few years ventured into retail - both online and physical stores - telecom and digital services, built a media empire around news and entertainment channels, and laid the foundation for giga factories for its clean energy foray. "Each of these (four) platforms is technology-first, innovation-led, and positioned to disrupt industries while delivering massive value to Indian consumers and the global market," Ambani said. On its mainstay cash-cow oil-to-chemicals (O2C) business, which houses the world's largest single location oil refinery complex and petrochemical plants, and oil and gas production business, he said these will continue to grow while catering to India's rising energy and materials demand. "We are not just scaling businesses - we are building platforms that empower people, reduce inequality, drive sustainability, and elevate India's position in the global economy. "Whether it's transforming the way Indians shop, consume data, watch content, or power their homes and businesses - Reliance is shaping the future with purpose and conviction," he said. Ambani, the richest man in Asia, said the world is changing at breakneck speed - reshaped by digital disruption, global shifts, and technological breakthroughs. "At Reliance, we see this not as a challenge but as an opportunity. We are reimagining our future and reshaping our businesses to become a new-age deep-tech enterprise," he said, adding that next-generation technologies are being integrated in every business vertical - from energy to entertainment, from retail to digital services. The conglomerate has over 1,000 in-house scientists who are leading cutting-edge research in areas like AI, renewable energy, advanced materials, and digital platforms. "Our manufacturing infrastructure is being future-proofed to support India's aspiration to become a global manufacturing powerhouse," he said. Giving performance highlights of each of the businesses, Ambani said while retail crossed Rs 3.3 lakh crore in turnover and expanded its footprint to 19,340 stores, Jio emerged as the world's largest data network with 488 million users, including 191 million on 5G. In the media space, Reliance built a large and distinctive media institution, in partnership with Disney, across genres, and has delivered record viewership and engagement metrics within the first few months of commencing operations. While O2C demonstrated resilience through disciplined cost management and strong domestic placement, oil and gas delivered record EBITDA, with increased output from KG-D6 and CBM blocks, he said. New energy transitioned from vision to execution - operationalising giga-scale solar and battery energy projects, he said. "At the heart of Reliance's success is a foundation built on values, trust, and talent. Our strong balance sheet, relentless focus on productivity, and unwavering commitment to excellence give us the confidence to embrace bold ambitions," he added.

Bosch gets over Rs 140 crore demand from customs authority for differential duty on oxygen sensors
Bosch gets over Rs 140 crore demand from customs authority for differential duty on oxygen sensors

Economic Times

time19 minutes ago

  • Economic Times

Bosch gets over Rs 140 crore demand from customs authority for differential duty on oxygen sensors

Bosch Ltd on Thursday said it has received demand of over Rs 140 crore, along with interest, from the customs authority for differential duty on account of the interpretation of the classification of oxygen sensors. The company has received an order passed by the Principal Commissioner of Customs (Import) Air Cargo Complex, New Delhi, in respect of interpretation on classification of oxygen sensors, Bosch Ltd said in a regulatory filing. The order is on account of interpretation on classification of oxygen sensors from one category to another, resulting in differential duty of Rs 70,41,16,516, interest and penalty of Rs 70,45,59,538, amounting to a total demand of Rs 1,40,86,76,054 plus interest, it added. The company will file an appeal before the tribunal in Delhi, by making a mandatory pre-deposit at the rate of 7.5 per cent on differential duty demanded, Bosch said, adding it is in the process of representing this issue before the Central Board of Indirect Taxes & Customs to get clarification on the matter pertaining to oxygen sensors.

Big win for Gautam Adani, this company gets approval for Rs 262981420500 project from…, to set up 2400 MW…
Big win for Gautam Adani, this company gets approval for Rs 262981420500 project from…, to set up 2400 MW…

India.com

time19 minutes ago

  • India.com

Big win for Gautam Adani, this company gets approval for Rs 262981420500 project from…, to set up 2400 MW…

Gautam Adani (File) Adani Power announced that it has received a Letter of Intent (LoI) from the Bihar State Power Generation Company to build and operate a 2,400-megawatt greenfield thermal power plant in Bihar's Bhagalpur district. The project involves an investment of USD 3 billion. The company expects to receive the LoA (Letter of Award) in due course and subsequently the Power Supply Agreement (PSA) will be executed with the state utilities. What Work Adani Power Will Do? The LoI has been awarded from Bihar State Power Generation Company Ltd (BSPGCL) to supply 2,274 MW energy North Bihar Power Distribution Company Ltd (NBPDCL) and South Bihar Power Distribution Company Ltd (SBPDCL), the Adani Group company said in a statement on Thursday. Adani Power was the lowest bidder in the tightly-contested tender process, with the final supply price of Rs 6.075 per KWh. As part of the contract, the company will supply power from a greenfield 3×800 MW Ultra-supercritical power plant, to be set up under the Design, Build, Finance, Own, and Operate (DBFOO) model. The first unit will be commissioned within 48 months of the appointed date, and the last one within 60 months of the appointed date. 'We have won the bid to develop and operate a 2,400 MW thermal power project in Bihar. We will set up a new greenfield plant with an investment of USD 3 billion, which is expected to further aid industrialization in the state,' said S B Khyalia, Chief Executive Officer of Adani Power. Adani Power To Generate 10,000-12,000 Jobs He said the new plant will be an advanced, low-emission ultra-supercritical and will supply dependable, competitively priced, and high-quality power to the state. The plant will receive fuel from the allocated coal linkage under the SHAKTI Policy of Government of India. The project is expected to generate direct and indirect employment of 10,000-12,000 personnel during the construction phase and 3,000 once in operation. The company has an installed thermal power capacity of 18,110 MW spread across twelve power plants in Gujarat, Maharashtra, Karnataka, Rajasthan, Chhattisgarh, Madhya Pradesh, Jharkhand, and Tamil Nadu, apart from a 40 MW solar power plant in Gujarat.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store