Oweninny Wind Farm is being built in three phases as a joint venture between the
ESB
and
Bord na Móna
at a cost to date of €320 million.
The second phase of the farm entered commercial operation in the spring of 2024, with an installed capacity now of 192mw which meets the power needs of some 140,000 homes a year.
With the third phase having received planning permission earlier this year, the Mullarkeys say an estate agent has told them their eight-bedroom house, which they extended in 2016 and once considered opening as a B&B, is now effectively worthless.
READ MORE
The couple saved hard in order to build their dream home, with Alan working in the UK before they were married. It is on a narrow road in the townland of Shanakilla, beside the once booming village of Bellacorick, on a plot of land next to the remote farmhouse where Eileen was reared and where her brother still lives.
The couple, in their early 50s, have five children, aged from 13 to 25, who are still living at home.
'We never had a problem with the original wind farm which has 'toy turbines', as we call them, and are further from the house,' Eileen says.
Built in 1992, this was Ireland's first commercial wind farm and it adjoins the new development. Due to be decommissioned in the coming months, 18 new turbines are scheduled to replace the original 21, completing the three phases of the Oweninny project and its 78 turbines.
Speaking last year after the opening of phase two, then minister for energy and Green Party TD Eamon Ryan called it 'a significant day for Ireland and for Mayo' in terms of delivering clean energy.
For decades anyone who travelled from Ballina to Belmullet would recall how this vast, bare and boggy landscape was once dominated by the 300ft high (88.82m) Bellacorick Generating Station's cooling tower.
Today, this landscape is dominated by wind turbines double the tower's size, standing 176m (577ft) high.
When the cooling tower was demolished by a controlled explosion in 2007, thousands watched from afar, comparing it to 'a wake' for the community.
It serviced Bord na Móna and the ESB's last old-style peat-fired electricity generating plant. Situated north of the N59 between Crossmolina and Bangor Erris, the station burned milled peat from 2,400 hectares (24sq km) of developed bogland which helped to power the national grid from 1962 until 2003.
For an area blighted by emigration driven by economics, the industry, when at peak production, provided employment for up to 500 locals.
'We feel we have been branded as troublemakers just because we didn't agree with everything'
'Back then I worked down in the pub,' Eileen says. 'It was full of life and there was loads of money around the area. Then, bang – it was gone. We lost the pub. We lost the post office. We lost the petrol pumps. We lost everything once the power station shut down.
'There is almost no direct employment from this project,' Alan says of the wind farm. 'Its contractors come in, do their maintenance work and disappear again.'
The lack of local employment is one of many criticisms the Mullarkeys have about living beside the project.
'When the turbines are running at a high speed, the swishing noise is going to be louder but then during the winter gales and storms you've got the clash of the wind with the blades,' says Alan.
The couple claim the project was rushed through the planning process before they realised what was happening.
'When the rumours became a reality, we did object on the grounds that the project was too close to our house, that there would be noise intrusion and our view would be blocked,' says Alan.
'At the time we didn't know about shadow flicker,' Eileen adds. 'That's when the blades are going around and they cast a moving shadow through the house that every now and then obstructs the sunlight ... darkening the rooms.
Eileen said theirs is the only house that has shadow flicker and it occurs in the mornings and the evenings.
'Even the first time we reported shadow flicker, they told us this wouldn't happen, saying there was a sensor on the turbine that shuts it down but I can assure you that is not the case.'
It is important to note, says Eileen, that none of their objections and queries were ever about money.
'We feel we have been branded as troublemakers just because we didn't agree with everything. We just want people to understand the realities of wind farms,' she says.
'After all, the only compensation households within the 1,000-metre zone get is €1,000 a year, for phase two only, and for 15 years. Ironically, it doesn't even pay our electricity bill for the year. Wouldn't it have been a positive community gesture to allow one of the turbines to generate local electricity?'
Accountant Tommy McHugh's home, in Ballymunnelly, is another of the 22 houses deemed 'near neighbours' of the project.
'There were a lot of promises made before the wind turbines were installed and we thought we would be able to negotiate for better compensation but the developer has hidden behind the legislation and has only been open to giving us the minimum amount,' says McHugh.
'Our properties have been devalued by at least 50 per cent while the developer has amassed multimillion euro profits.'
His neighbour, Madeleine Gallagher, who works as a nurse in Castlebar, has the same criticisms.
'I also understand we need green power and as I drive home from Castlebar at night I find all the lights in the sky from the turbines comforting, even if they look like great grey statues during the day,' she says. 'But the reality is that we have a very elderly population, no employment in the area and the company could have treated us better.'
Locals agree that a €600,000 community benefit fund and educational scholarship scheme have been welcome.
'In 2024 four scholarships were awarded to applicants who live within 5km of Oweninny Wind Farm Phase 2. The scheme may be used towards course fees, accommodation, tools and transport costs,' an ESB spokeswoman said.
Some 1,462 pupils from 34 schools have attended the educational programme at the visitor centre, which covers 'the history of power generation, peat production, wind energy development, the bog rehabilitation programme, ecological interests and the social history of the area'.
Adam and Eileen Mularkey live with the daily hum and flicker of Ireland's largest onshore wind farm
Addressing some of the criticisms made by locals, the spokeswoman stated that the developer was 'committed to and rigorously adhering to' all the planning conditions.
She said the wind farm supports 14 direct jobs, employed more than 100 people during construction and that local contractors and service providers 'continue to support the operation of the visitor centre on a weekly basis'.
For local Fianna Fáil councillor Michael Loftus, the bottom line is that the project has gone through the full planning process and been granted permission.
'The community made their feelings known at the time and some are for it and some are against it but the big win is the community gain fund,' he said. 'There will be more employment when phase three starts and there is huge potential for employment through the visitor centre.'
However, he agrees there should be free electricity for the project's 'near neighbours' under that scheme and their annual compensation should be greater than €1,000 per year.
Meanwhile, the Mullarkeys are concerned about practicalities such as their narrow roadway up to the N59 becoming flooded as a result of the huge construction project having involved deep excavation of the bog.
'A bog is like a sponge: they took the bog away to put stone and steel into it to build these monstrosities,' says Eileen.
'During the building of the turbines, the big machinery did so much damage to the bog and now they are telling us that people cutting a few yards of turf are damaging the environment,' Alan says.
With the construction of phase three of the wind farm in the offing, the Mullarkeys say they are too tired to continue asking questions and putting in queries about the project.
'Last year there was a major cable fault in the system and the turbines were shut down for 12 weeks,' says Eileen.
'It was like winning the lotto for us. The silence was just like heaven and most importantly, as we worked in our garden, we could hear the birds singing again.'
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Irish Times
2 hours ago
- Irish Times
Citroën's affordable electric e-C3 will have to keep watch on rivals
Citroën eC3 Year : 2025 Fuel : Electric Verdict : Well-priced, decent performance and range, and usefully practical. The e-C3 has some really sharp rivals, though. Well, you asked for more affordable electric cars (or at least complained about the current fleet being too expensive) so here they come. Citroën 's new e-C3 is now arriving in Ireland, quite some time after going on sale in the rest of Europe. Blame high demand in those other countries, apparently – Citroën Ireland's factory slots just kept getting pushed back. It is here now, and it's coming in three forms. There's a basic 100hp 1.2-litre petrol model, which even has the rarity of being a six-speed manual gearbox; there's a 110hp hybrid; and there's this, the all-electric e-C3. Prices start from €23,400 and, impressively, that's the same whether you want petrol or electric power. That doesn't make the Citroën e-C3 the cheapest EV on the market, not by a long shot when the likes of the Hyundai Inster are around, but it is certainly affordable, and doubly so when you consider the generous standard equipment of the basic Plus model (17-inch alloys, 10.25-inch touchscreen, cruise control, air conditioning and parking sensors among much else, including lots of standard safety kit). READ MORE Citroën eC3: Prices start from €23,400 The electric pricing gets even better when you move up to the top-spec Max version (heated seats and steering wheel, wireless phone charging, automatic aircon, heated windscreen). Now, if you want a hybrid (the basic petrol model isn't available in this spec), that's going to be €29,000, but the electric Max model is just €25,650. That's a chunky €4,000 saving, which you could spend on getting a home charger installed, and maybe then a nice holiday. It's not as if this is the bargain-bucket e-C3 either. That model will come next year, with a tiny 30kWh battery and a range of only 200km, but this version that we're testing has a 44kWh battery and a claimed range of 320km. Realistic? Broadly. On mostly motorway miles we were getting a range of 220km-250km, and if you mixed in more town mileage or used some slower country roads, that would probably be more like 270km or 290km. Enough, in other words. Citroën eC3: Hydraulic bump-stop suspension is meant to give a softer, comfier ride The e-C3 will charge from a fast DC charging point at up to 100kW, allowing a 20-80 per cent charge in 26 minutes, but the more significant figure is what it would cost you to charge at home – 44kWh on a night rate of 15c per kWh is just €6.60 for a full battery. You would struggle to get 250km out of €6 worth of diesel. In one sense it's a bit of a shame that the e-C3's battery is as small as it is, as the car has enough comfort to make a long journey painless. [ How much does an EV charger cost to install? Opens in new window ] Citroën is fitting the e-C3 as standard with its 'Advanced Comfort' seats, which have 10mm extra foam than before and are gloriously soft and comfy; and its matching hydraulic bump-stop suspension. This is meant to give a softer, comfier ride over bumps and lumps, but it's only partially successful. Big bumps – speed ramps and the like – are ironed out nicely, but the shorter, sharper ripples that you get on Irish country roads are more easily felt. There's a good bit of tyre and wind noise at a motorway cruise, but nothing excessive. Is the e-C3 fun to drive? A bit, but mostly only because it's a relatively compact car and the combo of small size (it's only 1.76m wide and a fraction over 4m long) always helps. The steering – accessed by a slightly odd-looking flattened oblong wheel – is too light to be fun, but the e-C3 darts happily about the place, and feels nimble right until the point where the weight of the battery shoves it into bland understeer. Citroën eC3: The cabin is better than you might expect for the price The cabin is better than you might think for a car that's built down to a price. The slim digital instrument display, set high up by the base of the windscreen so you don't need an expensive projected head-up display, works well and is refreshingly simple. The 10.25-inch touchscreen is also simple, and easy enough to use, primarily because there are also physical buttons for the air conditioning, which really makes life a lot easier. [ We decided to drive the new EV across the country. It wasn't long before things became tense Opens in new window ] The seats we've already mentioned (glorious) but overall cabin fit and finish is good. There's cheap plastic aplenty, but the fabric covering on the dash's centre section looks and feels a bit more upmarket, so you won't feel short-changed by the interior design. Space is adequate for a car this size. Up front, there's plenty of legroom and headroom, and good storage space too, but in the back, space for knees is tight if there are tall people in the front. Citroën eC3: The 312-litre boot is fine Four full-sized adults will fit, but they may not be able to lounge about the place. The 312-litre boot is fine, but nothing special and there's no 'frunk' storage area in the nose, so you'll have to save space back there for charging cables. As an affordable car proposition, the e-C3 seems rather good. It's a little ordinary to look at, but pleasantly chunky, and it's useful enough inside to serve as sole transport. The range isn't spectacular, but it should be enough for most people, most of the time. However, there are two problems for the e-C3. One is the Hyundai Inster, which is currently running away with the Irish EV market and is fractionally cheaper for a comparable range (albeit the Inster is strictly a four seater – the e-C3 has a third rear seat belt if you have skinny friends and family). Citroën eC3: As an affordable car proposition, the e-C3 seems rather good The other is the incoming Fiat Grande Panda, which takes the exact same mechanical package as the Citroën and clothes it in body possessed of more visual funkiness, and which comes with a vacuum-cleaner style charging plug that retracts back behind a flap in the bonnet. A third problem, if one is needed, is the base version of the super-stylish and fun-to-drive Renault 5, which has comparable range and is only slightly more expensive. Taken in isolation, then, the e-C3 is pleasantly sensible, compact, affordable and efficient. But it'll need eyes in the back of its metaphorical head with competition such as that. Lowdown: Citroën e-C3 Max Power 83kW e-motor developing 113hp and 124Nm of torque, powering the front wheels via a single-speed automatic transmission. CO2 emissions (annual motor tax) 0g/km (€120). Electric consumption 17.6 kWh/100km (WLTP). Electric range 320km (WLTP) 0-100km/h 10.4 seconds. Price €25,650 as tested, C3 starts from €23,400.


Irish Times
2 hours ago
- Irish Times
AI tools to help improve infrastructure, says Deloitte
A powerful set of available AI tools will help improve the resilience of much of Ireland ageing infrastructure , which is increasingly exposed due to increased floods, storms and other climate-related disasters, according to Deloitte consultancy firm. The newly reviewed National Development Plan (NDP) 'offers a once-in-a-generation opportunity to future-proof Ireland's infrastructure' but AI needs to be widely deployed, said Stephen Prendiville, Deloitte Ireland's infrastructure and sustainability lead. Kevin O'Sullivan has the details. The Oasis double-header in Croke Park at the weekend has been credited with a more than 9 per cent increase in consumer spend by fintech platform Revolut. The sold-out gigs on Saturday and Sunday marked the first time the band had played in Ireland since Slane in 2009, resulting in spending not seen since American singer-songwriter Taylor Swift played at the Aviva Stadium in June last year. READ MORE Revolut said card spend climbed by more than 9 per cent in Dublin when compared with the previous weekend, while the volume of transactions rose by over 8 per cent. Colin Gleeson reports. Have you been asked your current salary at a job interview , but not been told what the new role pays? Do you suspect the guy sitting next to you is earning more? What about a colleague's swish new car – is he getting a sneaky car allowance? Secrecy around pay in companies is rife, and it often disadvantages women. New European Union (EU) pay transparency rules will lift the lid on practices that unfairly reward some employees over others. So what will it mean for you? Joanne Hunt has some answers. 'I don't think the Department of Finance have any respect for the tourism industry' Listen | 41:44 The maker of Drumshanbo Gunpowder Irish Gin plans to double down on its investment in the United States in spite of the impact of US President Donald Trump's 15 per cent tariff on imported EU goods. Speaking to The Irish Times, Pat Rigney, co-founder of the Shed Distillery in Co Leitrim with his wife Denise, said the company will invest heavily to grow its position in the US market. 'We'll be increasing our investment in marketing, we'll be increasing our innovation and we'll be spending more time in the marketplace here. This is not a time for armchair marketing, you have to be on the streets and you have to support your partners,' he said. Ciarán Hancock reports. What does talk of the US government taking a direct stake in Intel mean for its Leixlip plant , wonders John McManus in his Wednesday column. It looks likely that it will, at best, be left to wither on the vine as future investment is focused on boosting manufacturing capacity in the US. Alternatively, Donald Trump could change his mind in the morning. Around 130 jobs could be lost after the Leprino Foods Company said it will close its manufacturing plant in Portlaoise in the second half of next year. The Co Laois factory produces mozzarella and string cheese. Siptu representatives are due to meet senior management at Leprino Foods in Portlaoise on Wednesday, writes Órla Ryan. If you'd like to read more about the issues that affect your finances try signing up to On the Money , the weekly newsletter from our personal finance team, which will be issued every Friday to Irish Times subscribers.


Irish Times
2 hours ago
- Irish Times
Unite dispute with Jones Engineering goes to mediation
A dispute between Unite and builder Jones Engineering sparked by legal action against three of the union's members will go to mediation after the Organisation for Economic Co-operation and Development 's (OECD) intervention. HA O'Neill, part of the Jones group, recently dropped High Court action against Unite and three shop stewards following a one-day strike in March 2023 over travel allowances. Both sides accepted an offer of mediation on Tuesday from the OECD, which got involved after Unite and the Builders and Woodworkers International (BWI) filed a complaint with it against Jones and its US owner Cathexis. The OECD's national contact point for the Republic, part of the Department of Enterprise, Tourism and Employment, ruled that the issues raised required further consideration. READ MORE Unite general secretary Sharon Graham dubbed the decision a 'vindication' of its members in Jones, adding that it sent a clear signal to other employers. The union and BWI claimed the company breached the OECD's Guidelines for Multinational Enterprises on Ethical Business Conduct by taking action against the shop stewards. Jones said on Tuesday that it rejected the union's allegations and added that the OECD had not found that the company had 'acted inconsistently with the guidelines'. 'Facilitated mediation does not imply wrongdoing, but rather that all parties wish a resolution to the matter,' Jones Engineering added. Failure to comply with OECD guidelines can affect companies bidding for state or publicly funded contracts in member countries. Along with dropping the court action, which the company has done, Unite wants Jones to compensate its three shop stewards and to enter a facilities agreement with the union, meant to allow greater co-operation between the pair. Unite also seeks the restoration of the travel allowance, which originally prompted the dispute. The union and the Mechanical Engineering and Building Services Contractors' Association, of which Jones is a member, have taken this issue to the Workplace Relations Commission and Labour Court in a bid to resolve it across the industry. Unite members held a one-day strike on March 10th, 2023, at Jones Engineering's sites in Pfizer in Grange Castle, Dublin, and Intel in Leixlip, Co Kildare. They were demanding the restoration of a travel allowance to building workers of one hour's pay, which the industry had dropped with unions' agreement following the financial crash in 2008. HA O'Neill sought a High Court injunction restraining Unite and the shop stewards from engaging in further industrial action pending a final hearing of the dispute. The company maintained that the industrial action was unlawful and that there was no valid dispute between it and Unite. The Supreme Court subsequently ruled that the High Court was wrong to grant the injunction as Unite had followed procedures laid down in the Industrial Relations Act, 1990. However, HA O'Neill subsequently took a separate High Court action against the union and its officials, which it halted in June this year. In their complaint to the OECD, Unite and BWI claimed that the court proceedings were meant to financially punish the three shop stewards. However, the company has always rejected that it acted improperly. Jones said it continued to recognise all unions and to operate within frameworks that have guided industrial relations in its industry for decades.