Green Bag roundabouts tied up in court
West Virginia Division of Highways District 4 Manager Earl Gaskins explained as much during a recent conversation with members of the Morgantown Monongalia Metropolitan Planning Organization.
"The Green Bag Road, as you guys can imagine, we're fighting with right of way on that. Right now we currently have eight parcels we have not acquired. We're moving for eminent domain on that, so we're waiting on the court system, " he said. "One of the things I'm seeing is we're overwhelming the court system. Everybody's busy, and by throwing these eminent domains in, we're overburdening the court system itself, but we're moving forward with that. Everything's looking good. Looks like we'll be able to get these knocked out here pretty soon and we'll get moving on the actual project."
Eminent domain is the power of the government to pay fair market value to take private property for public use — even if the property owner doesn't want to sell.
Conversation about Green Bag and its potential as a sort of Morgantown bypass for heavy trucks has been going on more than a decade. The discussion took on a different tone starting in 2018-2019 when it became clear the DOH was prescribing roundabouts to address backups at its intersections with Kingwood Pike and Mississippi Street intersections.
But roundabouts require land.
Notably, some of the land required is owned by the Hastings family and the site of a community garden. The family was outspoken in opposing the plan and ultimately pressured the DOH to conduct an environmental study for a project it initially said was exempt from such consideration.
In early 2022, the DOH issued its findings of no significant environmental impact.
Even so, a requirement to fund community gardens was attached to the project as a means of addressing the loss of the garden property. The MPO has recently distributed a total of up to $15, 000 to support the establishment of three community gardens.
The Green Bag Road project bid was awarded to Mountaineer Contractors on Dec. 6 for $18, 332, 804.40 in December.
The DOH previously said work on the project was likely to begin this spring and conclude in the fall of 2027.
The Dominion Post reached out to the DOH to ask if work would commence despite the right-of-way delays, but did not receive a response in time for this report.
Morgantown Industrial Park access bridge Much like Green Bag Road, Gaskins said the DOH is still working through right-of-way issues for the $59.7 million effort to span the Monongahela River to connect the Morgantown Industrial Park directly to U.S. 119 (Grafton Road).
"There are still two parcels we're fighting with. One is the railroad and the other one is a property we'll have to take through eminent domain, " he said.
According to Gaskings, Triton Construction has submitted a value engineering plan that would lower the cost to the contractor to build the project. Those plans are currently being reviewed by a third party.
"I don't want to be in a position where we can save money and we don't, and I also don't want to be in a position where this engineer and that engineer feel like they're just fighting back and forth, so we requested a third party to take a look at it."
As of the end of April, the DOH said steel should start being erected in early next year with completion forecasted for winter 2026.
Holland Avenue According to Gaskins, the DOH intends to award a contract to resurface Fairmont Road / Holland Avenue in the 2026 fiscal year, which begins July 1.
The project will run from a point near the Wes Mon Plaza to the Joseph Bartolo Memorial Bridge, more commonly known as the Westover Bridge.
Gaskins said the DOH is currently waiting on Westover's Holland Avenue stormwater and sewer line replacement project to wrap up. That project is expected to be completed in late June and will leave the road with an asphalt base.
Gaskins said the DOH will follow with a full-width overlay.
"We also have a project on the Joseph Bartolo Bridge that's being let as we speak. That will involve a deck overlay, drainage corrections, new expansion joints and all that, " he said. "So, you're going to get new pavement on 19 and the bridge will be redecked about that same time. So, hopefully you guys get some long-needed relief over there because I know you've been in pretty rough shape."
Other projects In addition to those mentioned above, Gaskins ran through a list of projects and provided their current anticipated completion dates.
— Every pothole in Monongalia County: Filled by the end of May. "You've got my word on that, " Gaskins said.
— Traffic lights at I-79 Exit 155: August 2025 — Walnut Street Streetscape: August 2025 — University Avenue / Collins Ferry Roundabout: August 15, 2026 — West Run Road between Stewartstown and Point Marion Road: May 10, 2027
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles
Yahoo
14 minutes ago
- Yahoo
Evercore Highlights Amazon (AMZN) Grocery Strategy and Prime Stickiness
Inc. (NASDAQ:AMZN) ranks among the . Evercore ISI highlighted Inc. (NASDAQ:AMZN)'s strategic actions in the grocery industry on August 13, reaffirming its Outperform rating and $280 price target on the company. The firm noted that by strengthening customer engagement through a high-frequency purchase category, Amazon's tighter integration of groceries into the Prime ecosystem raises customer lifetime value and stickiness. Amazon's $25 free delivery threshold, according to Evercore ISI, puts pressure on rivals like Walmart and Instacart to lower their prices. The approach is in line with Amazon's previously declared $4 billion commitment to use the country's current logistics infrastructure to extend its same-day and next-day delivery network to over 4,000 smaller and rural U.S. communities by 2026. According to Evercore's 13th Annual Amazon Survey, Prime Same-Day delivery multiplies the frequency of purchases, the expansion of categories, and the total amount spent by customers on Inc. (NASDAQ:AMZN). The firm refers to this as 'Shipping Elasticity', which suggests that faster shipping results in more frequent and larger purchases. Inc. (NASDAQ:AMZN), is an American multinational technology company that offers a wide range of commercial interests that include digital streaming, online advertising, e-commerce, cloud computing through Amazon Web Services (AWS), and artificial intelligence. While we acknowledge the potential of AMZN to grow, our conviction lies in the belief that some AI stocks hold greater promise for delivering higher returns and have limited downside risk. If you are looking for an AI stock that is more promising than AMZN and that has 100x upside potential, check out our report about this cheapest AI stock. READ NEXT: and . Disclosure: None. This article is originally published at Insider Monkey. Error while retrieving data Sign in to access your portfolio Error while retrieving data Error while retrieving data Error while retrieving data Error while retrieving data
Yahoo
14 minutes ago
- Yahoo
KeyBanc Raises Dycom Industries (DY) Price Target to $295 on Telecom Growth
Dycom Industries, Inc. (NYSE:DY) is one of the best Russell 2000 stocks to buy now. On July 16, KeyBanc Capital Markets increased its price target for Dycom stock to $295, up from $255. The firm maintained its 'Overweight' rating on Dycom's shares, citing the company's strong sector positioning and the expectation that telecom infrastructure investments will remain high in the years to come. Photo by Scott Blake on Unsplash Specifically, KeyBanc highlighted Dycom's position at the start of a multi-year telecom investment expansion. Dycom, the analysts stated, has made robust private investments in fiber. Add to that the ongoing federal and state-funded rural broadband programs, as well as aggressive data center-led fiber builds. KeyBanc expects these initiatives to drive elevated spending in the industry for several years. The analysts also noted Dycom's national reach and scale in wireline construction. They stated that this fact gives the company an advantage in competing for contracts and capturing incremental growth opportunities. In that regard, KeyBanc noted that Dycom, as a 'telecom pure-play trading at approximately 11.3x FY27 estimates,' does not have its longer-than-usual growth cycle fully reflected in its current valuation. Dycom Industries, Inc. (NYSE:DY) is a specialty contracting company. It provides engineering, construction, maintenance, and installation services for telecommunications and utility infrastructure. The company operates across the United States, serving major telecommunications providers, cable operators, and utility companies through a network of field offices staffed by over 15,000 employees. While we acknowledge the potential of DY as an investment, we believe certain AI stocks offer greater upside potential and carry less downside risk. If you're looking for an extremely undervalued AI stock that also stands to benefit significantly from Trump-era tariffs and the onshoring trend, see our free report on the best short-term AI stock. READ NEXT: 10 Best Energy Stocks to Buy For the Long Term and Top 10 Industrial Stocks to Buy Amid Easing Tariff Uncertainties. Disclosure: None. This article is originally published at Insider Monkey. Sign in to access your portfolio

Yahoo
4 hours ago
- Yahoo
Fulton businesses adapt as downtown construction enters final stretch
Aug. 19—Fourth Street in downtown Fulton is in the middle of a transformation that is reshaping both the street's infrastructure and the way local businesses operate. A major overhaul that began in July is expected to wrap up by Nov. 1, about a month later than planned after the project was extended by one block. Work now runs from 10th Avenue to 13th Avenue and includes replacing water service lines with copper, installing new electrical systems and streetlights, replacing curbs and gutters, and pouring new Americans with Disabilities Act-compliant sidewalks. "All the water services have been upgraded. They just finished that up yesterday," City Administrator Eric Sikkema said, adding that crews would soon start forming the new sidewalks and work half a block at a time, with each section reopening a few days later. City officials are also weighing whether Fourth Street should remain a two-way or revert to a one-way configuration, a change that would add 16 parking spaces, improve intersection visibility and make it easier for drivers to back out of angled spots. Video models of both traffic patterns were presented in March. "As it's planned right now, Fourth Street will go to a one-way heading north, but that can always change," Sikkema said. Funding for the $1.8 million project includes a $107,000 U.S. Department of Agriculture grant for sidewalks and lighting, about $550,000 from federal American Rescue Plan Act funds, and the remainder from city reserves. Planning began in 2021 after failed attempts to secure other grants. "The road itself is only two inches of asphalt, and then it's brick underneath... that brick had started to fail, and that was starting to cause a lot of potholes through our downtown," Sikkema said. "None of our downtown met any ADA compliance... our street lighting was starting to fail. Seemed like every other bulb was starting to have issues, and it was time." The construction, combined with the Iowa Department of Transportation's ongoing resurfacing of the North Bridge just a few blocks south, has posed challenges for downtown businesses. Lori Shear, owner of Country Orchids, said street work has slowed walk-in customers, though most of her business comes through phone orders. Jackie Wilkin, owner of Rooted Boutique and a member of the Fulton City Council, said the upgrades are overdue. "I've owned this business for five years... and in my five years, I've seen three people fall on the streets and sidewalks because they're in such bad shape. So it is a necessary evil," Wilkin said. "There's never going to be a good time to do this work, but I commend our city for investing the 2 to $3 million that it's going to take to do it and make it better." However, Krumpets, a bakery and cafe on Fourth Street, told customers in a Facebook post that the overlapping bridge and street work has cut their daily revenue nearly in half. To adapt, the business is temporarily focusing on best-selling menu items, shortening hours and shifting mostly to take-out service while using the slowdown to renovate its dining area. "Even with all of your loving support, the unfortunate circumstance of both of these projects coinciding has left us with a 45% drop in daily revenue. That's unsustainable in our current format," the post read. A second phase of the Fourth Street work is planned for spring 2026, pending the outcome of a $3.1 million Illinois Department of Transportation Local Roads grant application. That phase would include downtown water main upgrades, repainting the city's water tower and rebuilding the road from Ninth Avenue to 13th Avenue. Work on the North Bridge, which carries motorists traveling Iowa 136 into Fulton, was originally expected to finish in early October. It has been delayed by material shortages and is now slated for completion in November. "We're just excited that we can finally move forward on this project and start making some necessary upgrades around town," Sikkema said. Solve the daily Crossword