logo
#

Latest news with #GreaterKarachiBulkWaterSupplyScheme

K-IV project: A number of key targets achieved: Wapda chief
K-IV project: A number of key targets achieved: Wapda chief

Business Recorder

time3 days ago

  • Business
  • Business Recorder

K-IV project: A number of key targets achieved: Wapda chief

KARACHI: Wapda Chairman Engr Lt Gen Sajjad Ghani (Retd) has announced that Wapda has succeeded in achieving a number of key targets on Greater Karachi Bulk Water Supply Scheme (K-IV project) and concerted efforts are being made to complete Phase-I of the project in June 2026. During his visit to the Project here on Thursday, he further said that prompt availability of the required funds is the key for completion of the Project as per the schedule. The Chairman had a detailed visit of various work fronts to review construction progress. These work fronts included intake and pumping stations at Kinjhar Lake and water conveyance system comprising pressurized pipelines being laid from Kinjhar Lake to Karachi. The project team along with the Consultants and the Contractors briefed the Chairman about progress on all eight contracts including intake, pumping stations, pipelines, water reservoirs and filtration facilities. Two critical activities i.e. inserting two water carrier pipelines in sleeve pipes at main railways crossing and hydrostatic testing on the first 15 Km of the pipeline have recently been completed, while the second hydrostatic testing for another 25 Km single pipeline will be carried out in June. Timelines for the remaining works and plans to achieve the targets as well as financial progress and requirement of funds were also discussed during the briefing. Cumulative physical progress on the Project is 63 percent. Rs. 75.21 billion have so far been spent on the Project, while PC-I of the Project's Phase-I amounts to Rs. 126.4 billion. Underlining the importance of K-IV Project for Karachi, the Chairman directed the Project Team to excel construction activities to meet the timelines. He also directed them to maintain close liaison with other stakeholders for timely arrangement of power supply by the Government of Sindh and augmentation of the water distribution system by Karachi Water and Sewerage Corporation (KWSC). K-IV Project envisages providing 650 million gallon per day (MGD) water to Karachi from Kinjhar Lake. The Project is planned to be completed in two phases. At present, Wapda is constructing Phase-I to supply 260 MGD water to Karachi. Phase-II, when implemented, will also augment another 390 MGD water to the system for Karachi. Copyright Business Recorder, 2025

Water board asked to fast-track execution of K-IV project
Water board asked to fast-track execution of K-IV project

Business Recorder

time10-05-2025

  • Business
  • Business Recorder

Water board asked to fast-track execution of K-IV project

KARACHI: Sindh Chief Minister Syed Murad Ali Shah, while presiding over a meeting to review the progress of the K-IV Augmentation Project, expressed serious concern over a burst water line at Karachi University and instructed the water board to repair it and restore the water supply immediately. 'This is unacceptable, that every day one or the other water transmission line bursts, ultimately the citizens have to suffer, therefore it must be resolved once and for all,' he said. The meeting held at the CM House was attended by Energy Minister Nasir Shah, Local Government Minister Saeed Ghani, Karachi Mayor Murtaza Wahab, Chief Secretary Asif Hyder Shah, Principal Secretary to CM Agha Wasif, Planning and Development Chairman Najam Shah, Local Government Secretary Khalid Hyder Shah, MD Water Board Ahmad Ali Siddiqui, and Project Director KWSSIP. At the outset of the meeting, the Chief Minister expressed his dissatisfaction and directed the water board to conduct a comprehensive survey of all old lines and develop a five-year plan for their repair/replacement. 'The water board needs to strengthen its system,' he emphasised. K-IV Augmentation: Reviewing the progress on the Greater Karachi Bulk Water Supply Scheme (K-IV Augmentation Works, KWSSIP-II), the Chief Minister emphasised the strategic importance of the project in addressing Karachi's chronic water shortage and urged all relevant agencies to remove administrative bottlenecks immediately. The chief minister directed the Local Government Department to expedite the tendering process and secure all necessary No Objection Certificates (NOCS) to ensure that physical work on the Rs 71.8 billion K-IV Augmentation Project begins within the next three months. The K-IV Augmentation Project is being implemented by the Local Government Department with financial support from the Asian Infrastructure Investment Bank (AIIB), the World Bank, and the Sindh government. The project comprises multiple packages, including Package A: Water transmission main from Reservoir 1 to Y-Junction. Package B1: Transmission from Reservoir R2 to Federal Urdu University. Package B2: From Federal Urdu University to Gul Bai, and Package C: From R3 to Banaras, and a 2.7 km common corridor shared with the Karachi Bus Rapid Transit (KBRT) system The project's design, was finalised and reviewed by the international Austrian firm, in line with Planning Commission directives. Bid documents were prepared and are being updated by the supervision consultant. The process for hiring a Construction Supervision Consultant (CSC) has already begun. The Technical and Financial Proposals' Technical Evaluation Report (TER) was approved by the World Bank. The Financial Opening took place last month, and the Contract Evaluation Report (CER) was shared with the World Bank. Following No Objection Letter (NOL) clearance, the letter of award was issued on May 6, and the contract, v is expected to be signed on May 12, 2025. To facilitate the project, 18 different agencies were approached for NOCS. So far, NOCs have been secured from seven agencies. Chief Minister Shah reiterated his commitment to accelerating the delivery of the K-IV Augmentation Project to ensure equitable access to clean drinking water for Karachi's growing population. Copyright Business Recorder, 2025

35th National Games postponed till Dec
35th National Games postponed till Dec

Express Tribune

time09-05-2025

  • Sport
  • Express Tribune

35th National Games postponed till Dec

Most of the grounds and facilities at sports complexes in Karachi are far from ready to host 35th National Games. PHOTO: APP Chief Minister Sindh Syed Murad Ali Shah met with a delegation of the Pakistan Olympic Association (POA) to finalise preparations for the 35th National Games 2025, which the CM announced that Karachi would host from December 6 to 13. Sindh will host the National Games after a gap of 18 years. Earlier, the National Games were scheduled to start from May 1. after 18 years hosted by Sindh. However, due to extreme heat in the city and other reasons, it was decided to postpone National Games. The meeting was held at the CM House, and attended by the POA delegation led by its President, Arif Saeed, Senior Vice President Fatima Lahori, Secretary General Khalid Mehmood, and Sindh Secretary Ahmed Ali Rajput. Also present was Sports Secretary Aleem Laghari, who gave a briefing on the preparations, logistics, and planning for the games. CM Shah pledged full cooperation to ensure the games are organised to international standards, directing relevant departments to provide essential facilities to athletes, including training, medical care, transportation, and modern infrastructure. A Memorandum of Understanding (MoU) was signed between the POA, the Government of Sindh, and the Sindh Olympic Association (SOA) to establish a coordinated framework for organising the games. According to Organising Secretary Ahmed Ali Rajput, around 10,000 male and female athletes, officials and others from across the country will participate in National Games to be held at 21 different venues. A total of 2760 athletes from provincial teams and 5600 from departmental teams will participate, along with 1200 technical officials and 132 veteran athletes. Water pipelines CM Murad, while presiding over a meeting to review the progress of the K-IV Augmentation Project, expressed serious concern over a burst water line at Karachi University and instructed the water board to repair it and restore the water supply immediately."This is unacceptable, that every day one or the other water transmission line bursts, ultimately the citizens have to suffer, therefore it must be resolved once and for all," he said. At the outset of the meeting, the Chief Minister expressed his dissatisfaction and directed the water board to conduct a comprehensive survey of all old lines and develop a five-year plan for their repair/replacement. "The water board needs to strengthen its system," he emphasised. Reviewing the progress on the Greater Karachi Bulk Water Supply Scheme (K-IV Augmentation Works, KWSSIP-II), the Chief Minister emphasised the strategic importance of the project in addressing Karachi's chronic water shortage and urged all relevant agencies to remove administrative bottlenecks immediately.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into the world of global news and events? Download our app today from your preferred app store and start exploring.
app-storeplay-store