Water board asked to fast-track execution of K-IV project
'This is unacceptable, that every day one or the other water transmission line bursts, ultimately the citizens have to suffer, therefore it must be resolved once and for all,' he said.
The meeting held at the CM House was attended by Energy Minister Nasir Shah, Local Government Minister Saeed Ghani, Karachi Mayor Murtaza Wahab, Chief Secretary Asif Hyder Shah, Principal Secretary to CM Agha Wasif, Planning and Development Chairman Najam Shah, Local Government Secretary Khalid Hyder Shah, MD Water Board Ahmad Ali Siddiqui, and Project Director KWSSIP.
At the outset of the meeting, the Chief Minister expressed his dissatisfaction and directed the water board to conduct a comprehensive survey of all old lines and develop a five-year plan for their repair/replacement. 'The water board needs to strengthen its system,' he emphasised.
K-IV Augmentation: Reviewing the progress on the Greater Karachi Bulk Water Supply Scheme (K-IV Augmentation Works, KWSSIP-II), the Chief Minister emphasised the strategic importance of the project in addressing Karachi's chronic water shortage and urged all relevant agencies to remove administrative bottlenecks immediately.
The chief minister directed the Local Government Department to expedite the tendering process and secure all necessary No Objection Certificates (NOCS) to ensure that physical work on the Rs 71.8 billion K-IV Augmentation Project begins within the next three months.
The K-IV Augmentation Project is being implemented by the Local Government Department with financial support from the Asian Infrastructure Investment Bank (AIIB), the World Bank, and the Sindh government.
The project comprises multiple packages, including Package A: Water transmission main from Reservoir 1 to Y-Junction. Package B1: Transmission from Reservoir R2 to Federal Urdu University. Package B2: From Federal Urdu University to Gul Bai, and Package C: From R3 to Banaras, and a 2.7 km common corridor shared with the Karachi Bus Rapid Transit (KBRT) system
The project's design, was finalised and reviewed by the international Austrian firm, in line with Planning Commission directives. Bid documents were prepared and are being updated by the supervision consultant.
The process for hiring a Construction Supervision Consultant (CSC) has already begun. The Technical and Financial Proposals' Technical Evaluation Report (TER) was approved by the World Bank. The Financial Opening took place last month, and the Contract Evaluation Report (CER) was shared with the World Bank. Following No Objection Letter (NOL) clearance, the letter of award was issued on May 6, and the contract, v is expected to be signed on May 12, 2025.
To facilitate the project, 18 different agencies were approached for NOCS. So far, NOCs have been secured from seven agencies.
Chief Minister Shah reiterated his commitment to accelerating the delivery of the K-IV Augmentation Project to ensure equitable access to clean drinking water for Karachi's growing population.
Copyright Business Recorder, 2025
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Business Recorder
5 hours ago
- Business Recorder
Digital Economy Enhancement Project: MoUs between MoITT, provincial govts still pending: World Bank
ISLAMABAD: The World Bank has pointed out that the memorandum of understandings (MoUs) between the Ministry of Information Technology and Telecommunication (MoITT) and the provincial governments, as laid down in the financing agreement of 'Digital Economy Enhancement Project' (DEEP) of $78 million, are still pending. Official documents of the Bank also stressed on stronger coordination among the project implementation entities and service providers in the federal and provincial governments for on-boarding of provincial and local government services. The project has made good progress in implementation status and results report (ISR) period. The three designated accounts have been opened, disbursements have begun, project staff has been recruited, and procurement processes for key consultancies and IT infrastructure are under way. The establishment of the national data exchange layer and digital identification ecosystem has been affirmed as a priority for the federal government. However, stronger coordination is needed among the project implementation entities and service providers in the federal and provincial governments for on-boarding of provincial and local government services. The MoUs between the MoITT and the provincial governments, as laid down in the Financing Agreement, are still pending. The Ministry of Information Technology and Telecommunication in collaboration with the World Bank is implementing DEEP. The main objective of the programme is 'to enhance the government's capacity for digitally enabled public services delivery for citizens and businesses.' The DEEP proposes a whole of government approach to develop the framework and technology that will increase access to and promote the use of digital services across Pakistan. The project will develop Pakistan Digital Government Enterprise Architecture, which will create a government ecosystem transcending existing processes, including by mapping roles and responsibilities and setting key principles across technology, business, information, and service design. This digitalisation will not only provide ease to citizens and businesses but would also enable higher degree of transparency, lower the cost of processing, and increase the tax collection capabilities of the federal and provincial governments, which is one of the priority focus areas of the government. Copyright Business Recorder, 2025


Business Recorder
a day ago
- Business Recorder
World Bank approves $650 million Istanbul Resilience Project
The World Bank said on Friday it had approved a $650 million loan to support the Istanbul Resilience Project, an investment to strengthen the city's emergency preparedness and response capacities for disasters and climate risks. Focused on protecting lives, livelihoods and economic activity in Turkiye's largest city, the project aims to improve Istanbul's resilience, the World Bank said in a statement.


Express Tribune
a day ago
- Express Tribune
IMF social spending goal missed
Listen to article Pakistan narrowly missed the International Monetary Fund's (IMF) target to spend at least Rs2.86 trillion on improving poor health and education standards, as Sindh, Khyber- Pakhtunkhwa (K-P), and Punjab fell short of their commitments. Education spending appeared to be a low priority, despite one in four children being out of school and half of grade-five students unable to read grade-two Urdu stories. Against the target of Rs2.863 trillion, the federal and four provincial governments spent Rs2.84 trillion in the last fiscal year, missing the mark by Rs27 billion, according to government sources. Compared to the targets in the memorandums of understanding (MOUs) signed by all five governments, expenditures were Rs240 billion lower than commitments. Sindh, Khyber-Pakhtunkhwa, and Punjab missed their targets by wide margins, while the federal and Balochistan governments exceeded theirs. Poor administrative structures and low absorption capacity were cited as major reasons for the shortfall. The IMF set quarterly and annual ceilings to ensure health and education spending was not sacrificed for meeting other conditions such as cash surpluses and budget balances. In May, Pakistani authorities assured the IMF they would work to improve provincial capacity in these sectors. The IMF's staff report stated that Pakistan's health and education spending has declined since 2018. All governments had aimed for a modest increase in spending to 2.4% of GDP, but execution fell short, particularly in Sindh and Khyber-Pakhtunkhwa, due to absorption issues. The IMF's annual target was missed despite higher spending in the last quarter. Against a quarterly target of Rs713 billion, the five governments spent Rs937 billion in April-June, which was nearly one-third more than planned. However, this late surge failed to offset shortfalls from the first three quarters. Authorities had acknowledged the decline in non-Benazir Income Support Programme (BISP) health and education spending in recent years and committed to gradually increasing it as a share of GDP over the three-year IMF programme. Compared to internal budgetary targets, the federal government spent Rs261 billion on health and education against a Rs248 billion target. Punjab fell Rs35 billion short, spending Rs1.15 trillion in total. Provincial Information Minister Azma Bukhari said Punjab's health budget was Rs524.8 billion, with Rs505 billion actually spent — 96% of the target. Education spending was targeted at Rs664 billion but stood at Rs649 billion, or 98% of the goal. Sindh, under the government of Chief Minister Syed Murad Ali Shah, fell Rs153 billion short, spending Rs670 billion against a target of Rs853 billion, said the sources. Provincial governments often favour large infrastructure projects with more visibility to voters over softer social spending targets. Khyber-Pakhtunkhwa spent Rs545 billion on health and education compared to the Rs600 billion target, missing by Rs55 billion. Balochistan, however, exceeded its target by Rs25 billion, spending Rs206 billion. A recent World Bank report for the "Actions to Strengthen Performance for Inclusive and Responsive Education" programme said Pakistan still struggles with equitable access to education, with significant disparities across levels and genders. The gross intake ratio in grade one is 91%, with disparities between males and females. Transition rates from primary to middle school are 83%, and from middle to secondary school, 92%, according to the World Bank. However, the gross enrollment rate drops sharply from 78% at primary level to 22% in higher secondary education, highlighting retention issues. Out-of-school children remain a major concern, with 26.1 million, or 38% of the school-age population, not attending school in 2022-23. Gender disparities worsen at higher education levels, and rural areas are hardest hit, accounting for 74% of out-of-school children. For girls, lack of access is a critical barrier. Despite progress in enrolment, earning outcomes remain low, with national assessments showing a decline in foundational literacy and numeracy (FLN). In 2023, only 50% of grade-five students could read a grade-two story in Urdu or Sindhi, down from 55% in 2021. English literacy also slipped, with just 54% of grade-five students able to read simple sentences, compared to 56% in 2021. Numeracy skills also worsened. World Bank publications on health sector loans show a similarly troubling picture. Although Pakistan has seen improvements in health outcomes over the past decade, it is unlikely to meet most 2030 health-related Sustainable Development Goals (SDGs) at the current pace. Life expectancy has improved but remains among the lowest in South Asia. Progress in reproductive, maternal, and child health is also inadequate, and Pakistan remains one of only two countries where polio is endemic.