logo
#

Latest news with #HeartofPembrokeshire

Haverfordwest's new Riverside footbridge takes shape
Haverfordwest's new Riverside footbridge takes shape

Western Telegraph

time4 days ago

  • Business
  • Western Telegraph

Haverfordwest's new Riverside footbridge takes shape

The bridge will span the water between the Riverside and Western Quay, and delivery of its sections began last Tuesday, May 27. The structure has been described as 'signature' and, subsequently, 'Instagrammable'. The cost of the Pembrokeshire County Council-driven bridge project and associated works is £5.7million. The bridge has been delivered in sections. (Image: Peter Thomas) It's part of the £25.4 million Heart of Pembrokeshire project to revitalise Haverfordwest. Sparks fly as welding work takes place. (Image: Peter Thomas) Since earlier this week, the bridge has been delivered in sections to the site from the fabricator's workshop in Cardiff, with a 220-ton crane also on site. The delivery work has spanned four days this week. (Image: The final delivery was due to take place on the afternoon of Friday May 29. An impression of how the installed bridge will look. (Image: Atkins Ltd) Pembrokeshire County Council said: "The bridge will be assembled and final finishing applied for installation in mid-August." It's certainly a distinctive design. (Image: Peter Thomas) The authority has been contacted for further information about the progress of the work.

Haverfordwest 'Instagram' bridge delivery begins tomorrow
Haverfordwest 'Instagram' bridge delivery begins tomorrow

Western Telegraph

time27-05-2025

  • Business
  • Western Telegraph

Haverfordwest 'Instagram' bridge delivery begins tomorrow

A 220-ton crane will also be arriving on site at the Riverside, Haverfordwest to enable the delivery of sections of the bridge, which will span the water between the Riverside and Western Quay. The bridge has been described as 'signature' and subsequently 'Instagrammable', and the cost of the Pembrokeshire County Council-driven bridge project and associated works is £5.7million. The bridge and its associated works have a £5.7m price tag. (Image: Atkins Ltd) This includes a 'plaza' public realm reconfiguration and enhancement; and repair, renewal and refurbishment of the former Cleddau Foundry building. Of this, 90 per cent has been secured from external funding, leaving £600,000 to be met from council funds. It is part of the £25.4 million Heart of Pembrokeshire project to revitalise Haverfordwest. Pembrokeshire County Council posted on Facbeook today, Monday May 26: "The new footbridge will be delivered to site at Riverside, Haverfordwest from the fabricator's workshop in Cardiff starting 27th May 2025." The council has detailed the week's schedule as follows: Tuesday May 27: 220 ton crane with support vehicle with additional ballast and 1-2 articulated vehicle deliveries of temporary works Wednesday May 28 – 1 large delivery of east section of bridge Thursday May 29 - Two deliveries of middle sections of bridge Friday May 30 -Two deliveries of west sections of bridge and crane demobilisation The council added: "To accommodate the deliveries, the delivery vehicle will drive into the bus station from the A40/Cartlett Road at the existing temporary bus station exit and then reverse into the service yard. The bridge delivery route is shown here by the council. (Image: Pembrokeshire County Council) "Traffic marshals will be on site to control pedestrians during the delivery. "Bus services will operate as normal. Deliveries will be sequenced to avoid bus times; however, some disruptions will be unavoidable when the deliveries enter the site. "The bridge will be assembled and final finishing applied for installation in mid-August. "We apologise for any inconvenience caused by the traffic disruption during the delivery of the bridge to the site."

Haverfordwest town centre regeneration given multi-million pound funding boost
Haverfordwest town centre regeneration given multi-million pound funding boost

Pembrokeshire Herald

time05-05-2025

  • Business
  • Pembrokeshire Herald

Haverfordwest town centre regeneration given multi-million pound funding boost

EXTRA funding has been secured for two regeneration projects in Haverfordwest, and increases in costs will see no additional burden to the council, senior Pembrokeshire councillors heard. At the April meeting of Pembrokeshire County Council's Cabinet, members received an update on both the budget position and latest funding received for the Heart of Pembrokeshire (HoP) and Western Quayside schemes. The approved capital budget for delivery of the HoP scheme is £26,277,487, while the Western Quayside scheme approved budget is £11,624,000, a report for members, presented by Deputy Leader Cllr Paul Miller said. 'Additional external funding has been obtained to undertake green infrastructure works at Western Quayside and to allow the physical linkages between the key town centre locations of Haverfordwest Castle and the town centre, via Castle Square, to be enhanced in order to widen the town centre offer under a discrete Shared Prosperity Fund 2 (2025-26) work package to a value of £1,261,512,' the report said. An additional £2,700,000 funding for Western Quayside has also been secured through the Transforming Towns Fund, to support the Western Quayside Fit Out and phase 2 elements, including Foundry and Public Realm space. It also said fundraising consultants were preparing a separate Transforming Towns application for funding for further enhancement to the castle link and town centre wayfinding elements of the HoP scheme and funding to the post-HoP fitout scheme. This would not increase PCC's capital contribution to either scheme. It said costs had risen, but would be covered by the extra funding: 'Since the capital bid was approved by Cabinet, a number of variations have been experienced during project delivery. 'Currently, provision is required for £2,224,667 of anticipated costs and risk allowances. This is made up largely of costs associated with the gaol building due to its worse than anticipated condition, and restrictions imposed by archaeology, together with addressing the challenges realised at Castle Back and the associated work to address the safety issues in this area (risk of landslip). 'With regards to Western Quayside, there have been a number of changes to the extent of the works within the public realm and the works associated with the Foundry Warehouse. These changes will bring the foundry building into productive commercial use and fully link the Western Quayside building, foundry building, bridge and Library into a fully integrated public realm. 'Achieving these outputs, compliant with planning consent, has necessitated an increase to the budget of £1,736,845. These costs are fully covered by the recently received uplift to the Welsh Government Transforming Towns grant.' Members agreed to increase and reallocate the budget associated with the two schemes, to accommodate the additional external grant funding, and also, subject to securing additional external funding, delegate authority to the Director of Resources to increase the HoP and post-HoP fitout project budgets on condition that PCC's contribution does not increase.

Extra funding secured for Haverfordwest regeneration
Extra funding secured for Haverfordwest regeneration

Western Telegraph

time02-05-2025

  • Business
  • Western Telegraph

Extra funding secured for Haverfordwest regeneration

At the April meeting of Pembrokeshire County Council's Cabinet, members received an update on both the budget position and latest funding received for the Heart of Pembrokeshire (HoP) and Western Quayside schemes. The approved capital budget for delivery of the HoP scheme is £26,277,487, while the Western Quayside scheme approved budget is £11,624,000, a report for members, presented by Deputy Leader Cllr Paul Miller said. 'Additional external funding has been obtained to undertake green infrastructure works at Western Quayside and to allow the physical linkages between the key town centre locations of Haverfordwest Castle and the town centre, via Castle Square, to be enhanced in order to widen the town centre offer under a discrete Shared Prosperity Fund 2 (2025-26) work package to a value of £1,261,512,' the report said. An additional £2,700,000 funding for Western Quayside has also been secured through the Transforming Towns Fund, to support the Western Quayside Fit Out and phase 2 elements, including Foundry and Public Realm space. It also said fundraising consultants were preparing a separate Transforming Towns application for funding for further enhancement to the castle link and town centre wayfinding elements of the HoP scheme and funding to the post-HoP fitout scheme. This would not increase PCC's capital contribution to either scheme. It said costs had risen, but would be covered by the extra funding: 'Since the capital bid was approved by Cabinet, a number of variations have been experienced during project delivery. 'Currently, provision is required for £2,224,667 of anticipated costs and risk allowances. This is made up largely of costs associated with the gaol building due to its worse than anticipated condition, and restrictions imposed by archaeology, together with addressing the challenges realised at Castle Back and the associated work to address the safety issues in this area (risk of landslip). 'With regards to Western Quayside, there have been a number of changes to the extent of the works within the public realm and the works associated with the Foundry Warehouse. These changes will bring the foundry building into productive commercial use and fully link the Western Quayside building, foundry building, bridge and Library into a fully integrated public realm. 'Achieving these outputs, compliant with planning consent, has necessitated an increase to the budget of £1,736,845. These costs are fully covered by the recently received uplift to the Welsh Government Transforming Towns grant.' Members agreed to increase and reallocate the budget associated with the two schemes, to accommodate the additional external grant funding, and also, subject to securing additional external funding, delegate authority to the Director of Resources to increase the HoP and post-HoP fitout project budgets on condition that PCC's contribution does not increase.

Major housing, play and regeneration projects on the agenda for council cabinet
Major housing, play and regeneration projects on the agenda for council cabinet

Pembrokeshire Herald

time24-04-2025

  • Business
  • Pembrokeshire Herald

Major housing, play and regeneration projects on the agenda for council cabinet

Council secures grants to cover project overruns without increasing taxpayer burden TWO major regeneration projects in Haverfordwest are set to progress without additional cost to the taxpayer, following Pembrokeshire County Council's successful acquisition of external funding.​ A report scheduled for Cabinet review on Monday (April 28) outlines that the Heart of Pembrokeshire (HoP) and Western Quayside schemes will benefit from new grants, allowing the projects to continue despite unforeseen challenges and increased costs.​ The HoP project, with an approved capital budget of £26.27 million, and the Western Quayside scheme, budgeted at £11.62 million, faced combined overruns nearing £4 million. These overruns were primarily due to the deteriorated condition of the historic Gaol building and archaeological constraints. However, additional support from the Welsh Government and the UK Shared Prosperity Fund will cover these costs without increasing the Council's financial contribution.​ Significant new grants secured The Council has secured an extra £2.7 million from the Welsh Government's Transforming Towns Fund and £1.26 million via the UK Shared Prosperity Fund. These funds will facilitate green infrastructure works at Western Quayside and enhance pedestrian links between Haverfordwest Castle and the town centre.​ To meet grant requirements and streamline project accounting, some elements initially delivered under the HoP scheme—such as public realm work around the Foundry—will be reallocated to the Western Quayside project.​ Further applications are being prepared to secure additional funding from the Transforming Towns programme. If successful, these would support a post-HoP 'fit-out' of the castle site, improve town centre wayfinding, and enhance visitor experiences, all without extra cost to the Council.​ Castle and Gaol restoration separated While the HoP scheme is well underway, the Council plans to separate the later-stage restoration of the Gaol and Governor's House into a distinct project. This £2 million fit-out scheme has already received £368,525 in National Lottery Heritage funding, with further bids in progress. The Council aims to reduce its match funding requirement significantly.​ Separating the HoP and the Castle Fit-out projects within the capital programme is expected to provide clearer financial transparency.​ Criticism over project management Despite the financial boost, the Council faces criticism for initiating restoration work on the Gaol without secured funding for its completion. Critics argue that this approach was premature and risky, especially given the building's deteriorated condition and archaeological complexities. This has raised questions about project management and financial planning.​ The broader context includes significant funding cuts to Pembrokeshire County Council, with a reported reduction of over 40% in Shared Prosperity Scheme funding. Such cuts have intensified scrutiny over the Council's allocation of resources, particularly in light of other pressing needs across the county.​ Council Leader Jon Harvey, who succeeded David Simpson in May 2024, has pledged to bring 'compassion and transparency' to the role and to work collaboratively with other political groups. However, the decision to proceed with the Gaol's restoration without secured funding for its completion remains a contentious issue, highlighting the need for transparent and comprehensive financial planning in public projects.​ Two options on the table Cabinet members will consider two options. The preferred route is to accept the new external funding and reallocate budgets accordingly, delivering the full vision of both regeneration schemes while keeping the Council's capital contribution unchanged.​Pembrokeshire Herald Alternatively, councillors could reduce their capital spending by using the new grants to offset current commitments. However, this would render the HoP project unviable, potentially forcing the permanent closure of Castle Back and risking clawback of up to £17.7 million from UK Government and National Lottery funders.​ A separate recommendation would grant senior officers the authority to adjust the budget if further external funding becomes available, provided the Council's own contribution does not increase.​ No legal or HR issues raised The report confirms there are no legal or human resources concerns linked to the proposed changes. While the Director of Resources supports the plan, they caution that efforts must continue to reduce the Council's overall borrowing levels.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into the world of global news and events? Download our app today from your preferred app store and start exploring.
app-storeplay-store