logo
#

Latest news with #KedahPublicWorksDepartment

Northern region blood centre to complete mid-October, Ahmad says
Northern region blood centre to complete mid-October, Ahmad says

The Sun

time26-07-2025

  • Health
  • The Sun

Northern region blood centre to complete mid-October, Ahmad says

SUNGAI PETANI: The Northern Region Blood Centre is on track for completion by mid-October, according to Deputy Works Minister Datuk Seri Ahmad Maslan. The RM49.866 million project, supervised by the Kedah Public Works Department (JKR), began construction on August 2, 2021. Ahmad stated that the facility will include a main blood centre block, mechanical and electrical sections, parking spaces, a cafeteria, and a guardhouse. 'The physical progress has reached 93 per cent, with no major issues reported,' he said after inspecting the site. The centre will feature a modern laboratory, donor-friendly rooms, and an integrated logistics system to ensure safe and sufficient blood supply. It will serve Kedah, Perlis, Penang, and northern Perak, centralising blood collection, processing, and storage. 'Previously, blood was stored only in hospitals, many of which lacked sufficient space,' Ahmad explained. The new facility will house 20 donor beds and store blood at minus 40 degrees Celsius after screening and verification. - Bernama

Aim to complete public projects ahead of time
Aim to complete public projects ahead of time

New Straits Times

time29-04-2025

  • Business
  • New Straits Times

Aim to complete public projects ahead of time

ALOR STAR: Contractors should aim to complete public projects ahead of time, setting a new benchmark for efficiency, said Deputy Works Minister Datuk Seri Ahmad Maslan. He pointed to several successful cases, including a school in Sarawak completed a year early and the SK Taman Scientex project in Johor finished six months ahead. "Completing works ahead of schedule (AOT – Ahead of Time) is achievable and saves costs for both contractors and the government," Ahmad told reporters after visiting the Kedah Public Works Department (PWD) office here today. Ahmad said that achieving AOT benefits contractors, the government, and the public alike. "If they can complete works ahead of schedule — for example, three months earlier — the cost savings could be substantial. "Additionally, the public would benefit from the services much earlier," he added. Ahmad said that although the number of sick projects under the ministry nationwide remains relatively low at below four per cent, contractors must avoid applying for extensions of time or, worse, failing to complete government projects. "When a project is terminated, additional costs must be requested through the Ministry of Economy, creating unnecessary financial burdens to the government. "We want zero sick projects, because when a project becomes sick, retendering is usually required, leading to requests for additional funding — a loss for the government," he said, adding that 75 per cent of sick projects are due to contractors' shortcomings. Previously, Ahmad was reported as saying that only 29 projects, or 3.62 per cent of the Ministry's 801 projects nationwide, had been categorised as sick projects. Of the 29 sick projects, Ahmad said 75.86 per cent were due to contractor-related issues, while one project involved a change of scope, and six projects were delayed for various other reasons. Therefore, he urged Public Works Department (PWD) officers responsible for supervising projects to diligently monitor and ensure work progress. Meanwhile, Ahmad said the Kedah PWD is currently implementing 68 federal projects worth RM1.424 billion and 12 state projects worth RM852.39 million.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store