Latest news with #LandasanLumayanSdnBhd


The Sun
an hour ago
- The Sun
Bodies, waste hinder Klang River flood project progress
SHAH ALAM: In addition to the challenge of removing 94,000 metric tonnes of waste from Sungai Klang, the flood mitigation project under the Selangor Maritime Gateway (SMG) initiative has also uncovered more than 10 bodies, including that of an infant, since its implementation began in November 2022. Landasan Lumayan Sdn Bhd (LLSB) managing director, Syaiful Azmen Nordin said three bodies were discovered over three consecutive days in the Kota Kemuning area in May, which forced excavation and river-deepening works to be temporarily halted. 'So far, we have handed over more than 10 bodies, including an infant, to the police and fire department for further investigation. 'Typically, the bodies are found in good condition and largely intact despite being unclothed, including the infant, who was discovered inside an interceptor designed to trap surface debris,' he said. Speaking to reporters after visiting the flood mitigation project site in Kota Kemuning on Monday (June 16), Syaiful Azmen said the company works closely with police and fire authorities to conduct site investigations, in part to ensure halted works can resume as soon as possible. He added that aside from the discovery of bodies, the project implementation team also faces the challenge of severe river pollution, having encountered various large discarded items such as refrigerators, lorry tyres, sofas, beds, mattresses and motorcycles at the bottom of Sungai Klang. He noted that these discoveries – both bodies and waste – have somewhat disrupted or slowed the ongoing dredging and river-deepening operations. 'Nonetheless, these findings will not break our spirit in completing the mission to widen and deepen Sungai Klang, with the aim of increasing water capacity by at least 40 per cent by the end of this year,' he said.


The Sun
an hour ago
- The Sun
SMG Project uncovers over 10 bodies in Sungai Klang, including infant
SHAH ALAM: In addition to the challenge of removing 94,000 metric tonnes of waste from Sungai Klang, the flood mitigation project under the Selangor Maritime Gateway (SMG) initiative has also uncovered more than 10 bodies, including that of an infant, since its implementation began in November 2022. Landasan Lumayan Sdn Bhd (LLSB) managing director, Syaiful Azmen Nordin said three bodies were discovered over three consecutive days in the Kota Kemuning area in May, which forced excavation and river-deepening works to be temporarily halted. 'So far, we have handed over more than 10 bodies, including an infant, to the police and fire department for further investigation. 'Typically, the bodies are found in good condition and largely intact despite being unclothed, including the infant, who was discovered inside an interceptor designed to trap surface debris,' he said. Speaking to reporters after visiting the flood mitigation project site in Kota Kemuning on Monday (June 16), Syaiful Azmen said the company works closely with police and fire authorities to conduct site investigations, in part to ensure halted works can resume as soon as possible. He added that aside from the discovery of bodies, the project implementation team also faces the challenge of severe river pollution, having encountered various large discarded items such as refrigerators, lorry tyres, sofas, beds, mattresses and motorcycles at the bottom of Sungai Klang. He noted that these discoveries – both bodies and waste – have somewhat disrupted or slowed the ongoing dredging and river-deepening operations. 'Nonetheless, these findings will not break our spirit in completing the mission to widen and deepen Sungai Klang, with the aim of increasing water capacity by at least 40 per cent by the end of this year,' he said.


The Star
2 hours ago
- Business
- The Star
Sg Klang rehabilitation project showing results
The cutter suction dredger cleaning the riverbed in Sungai Klang. More than 900,000 cubic metres of materials have been cleared away so far. —LOW BOON TAT/ The Star SINCE November 2022, approximately 918,937 cubic metres of materials have been dredged from the Sungai Klang riverbed as part of Selangor's flood mitigation project. These efforts have significantly improved water quality and increased the river's capacity, said the company spearheading the Selangor Maritime Gateway (SMG) project. Landasan Lumayan Sdn Bhd managing director Syaiful Azmen Nordin said the dredged materials comprised general waste, sedimentation and rocks. Landasan Lumayan is a subsidiary of Menteri Besar Selangor Incorporated. The Maritime Gateway project, spanning 56km, aims to revitalise Sungai Klang and its surroundings. It is a state government initiative to overcome floods in Selangor. Speaking at a press conference at the project site in Kota Kemuning, Syaiful said SMG involved deepening and widening the river, alongside reinforcing the embankment and riverbank. These actions are expected to enhance water flow, preserve the river's ecosystem and improve water quality. Syaiful says Sungai Klang water quality is now at Class 3. 'The main objective is to increase the river's capacity to manage more water during heavy rain,' he said. He noted that clearing efforts had increased the river's capacity by 18%. The target is 40%. According to Landasan Lumayan, the project is divided into four blocks, with current focus on Block 3 – a 21km stretch in high-risk areas of Shah Alam, including Alam Impian (Zone 6), Section 24 (Zone 7) and Kota Kemuning (Zone 8). Work on Block 1, covering a 10km stretch in Klang (Zones 1 and 2), had been completed. Work on blocks 2 and 4 have yet to commence. Syaiful said the river would be widened from 50m or 60m to 80m or 100m, depending on location needs for smooth water flow. Dredging has been extended to depths of up to three metres, compared to previous depths of one to two metres. 'With increased capacity and reinforced riverbanks, rainwater can flow efficiently, reducing the risk of overflow or flash floods in Shah Alam and surrounding areas,' he added. Syaiful said the project was showing results as Sungai Klang's water quality had improved. 'At the beginning of the project, the water was classified as Class 5 (indicates heavily polluted water). 'Now, based on our sensors along the river, we are recording Class 3 water quality at about 69% of the time, which is a great improvement. 'There are 25 industrial areas, 13 tributaries and 10 million people having direct access to the river. 'We have to be realistic in our expectations, so our target is to make sure that the water quality is at least Class 3, which is suitable for general use,' he said. Syaiful said some of the challenges faced at the site included high amounts of waste besides deep mud, which complicated dredging works. However, he said the work was on schedule and was expected to be completed by 2026.


New Straits Times
9 hours ago
- Business
- New Straits Times
SMG flood mitigation project increases Klang river capacity by 18pct
SHAH ALAM: A major flood mitigation initiative under the Selangor Maritime Gateway (SMG) project has successfully increased the Klang River's water capacity by 18 per cent, covering a 31km stretch from the river mouth to the Petaling Jaya-Kuala Lumpur border. Syaiful Azmen Nordin, managing director of Landasan Lumayan Sdn Bhd (LLSB), a wholly-owned subsidiary of Menteri Besar Selangor (Incorporated) appointed as the master developer of the SMG project, said the improved river section spans two of four key project blocks - from the Shah Alam-Klang border to the Shah Alam-Puchong border, and from the river mouth to Bandar Klang - identified as Blocks 3 and 1, respectively. He said the state government, through its agencies, is targeting a total increase of at least 40 per cent in river capacity by the end of this year after past data revealed that Klang River, especially in Selangor, could not accommodate upstream water overflow during heavy rains. "Block 3, which covers flood-prone areas such as Sri Muda, Kota Kemuning, Section 17, and Section 24, requires special attention, as these are the most affected zones in recent flood events," he told reporters after a site visit to the flood mitigation project in Kota Kemuning yesterday. The river widening and dredging works for the remaining two blocks - from Bandar Klang to Bandar Sultan Sulaiman (Block 2), and from the Shah Alam-Puchong border to Petaling Jaya-Kuala Lumpur (Block 4) - will begin next year, covering an additional 28.8km. Syaiful Azmen said construction on Blocks 1 and 3 is expected to be completed by year-end, after which a two-year enhancement and monitoring phase will begin, also managed by LLSB. To date, around 94,000 tonnes of waste have been extracted from the river, at an estimated handling cost of RM20 million, he said. "That RM20 million could've been used for other development initiatives, if only there was greater public awareness about river cleanliness," he added. — BERNAMA

Barnama
11 hours ago
- Barnama
SMG Project Uncovers Over 10 Bodies In Sungai Klang, Including Infant
SHAH ALAM, June 16 (Bernama) – In addition to the challenge of removing 94,000 metric tonnes of waste from Sungai Klang, the flood mitigation project under the Selangor Maritime Gateway (SMG) initiative has also uncovered more than 10 bodies, including that of an infant, since its implementation began in November 2022. Landasan Lumayan Sdn Bhd (LLSB) managing director, Syaiful Azmen Nordin said three bodies were discovered over three consecutive days in the Kota Kemuning area in May, which forced excavation and river-deepening works to be temporarily halted. 'So far, we have handed over more than 10 bodies, including an infant, to the police and fire department for further investigation. 'Typically, the bodies are found in good condition and largely intact despite being unclothed, including the infant, who was discovered inside an interceptor designed to trap surface debris,' he said. Speaking to reporters after visiting the flood mitigation project site in Kota Kemuning today, Syaiful Azmen said the company works closely with police and fire authorities to conduct site investigations, in part to ensure halted works can resume as soon as possible. He added that aside from the discovery of bodies, the project implementation team also faces the challenge of severe river pollution, having encountered various large discarded items such as refrigerators, lorry tyres, sofas, beds, mattresses and motorcycles at the bottom of Sungai Klang. He noted that these discoveries – both bodies and waste – have somewhat disrupted or slowed the ongoing dredging and river-deepening operations. 'Nonetheless, these findings will not break our spirit in completing the mission to widen and deepen Sungai Klang, with the aim of increasing water capacity by at least 40 per cent by the end of this year,' he said. -- BERNAMA