Work for India-funded Thilamale Bridge reaches 60%
Work for the Thilamale' Bridge, financed by India, is 60 per cent complete with the conclusion of
piling works
under the project, Maldives' Infrastructure Minister
Abdulla Muthalib
revealed on Tuesday.
The 6.7 km
Thilamale Bridge
-- that links
capital
Male with Vilimale, Thilafushi and
Gulhifalhu
on its west -- is financed under an Indian grant of USD 100 million and a USD 400 concessional credit line from India's Exim Bank.
"The piling work for the Thilamale Bridge has been successfully completed, marking the most challenging phase of the project. A total of 263 piles were installed across 68 onshore and offshore locations," Muthalib said in a post on X.
by Taboola
by Taboola
Sponsored Links
Sponsored Links
Promoted Links
Promoted Links
You May Like
Belly Fat Removal Without Surgery in Iraq: The Price Might Surprise You
Belly Fat Removal | Search Ads
Get Info
Undo
"With this milestone achieved, the project has now reached 60.84 per cent completion," he added.
The Thilamale' Bridge project is one of the biggest projects initiated by the former president
Ibrahim Mohamed Solih
's administration, news portal said.
Live Events
The bridge will feature the tallest precast segments to be produced in the world at 8.2 meters, it added.
The project was awarded to India's
Afcons Infrastructure
in August 2021.
The initial deadline to complete Thilamale' Bridge was set for last year but it has been given revised deadlines on multiple occasions, added.