$500 million lost in Dasu project irregularities

$500 million lost in Dasu project irregularities

Express Tribune15-05-2025

The Senate Standing Committee on Economic Affairs was informed Wednesday that the national exchequer has suffered a loss of $500 million due to large-scale irregularities in the Dasu Transmission Line project.
The panel raised questions over non-transparent tendering practices and the awarding of the contract to an inexperienced company for the plan.
The committee meeting was chaired by Senator Saifullah Abro.
The body expressed serious concerns over the sidelining of the lowest bidder without substantial justification, and awarding the contract to a company that reportedly lacked the necessary experience in manufacturing bundling conductors.
Senator Abro noted that favouritism towards an inexperienced firm led to a massive financial loss, and strongly criticized relevant authorities for failing to uphold transparency in the procurement process.
Officials from NESPAK and the National Transmission and Despatch Company (NTDC) were unable to provide satisfactory answers, drawing sharp criticism from committee members. The chairman directed that a full investigation be launched into the matter and called for action against those found responsible. The committee chairman directed that a thorough investigation be conducted and action taken against those responsible.
The committee decided to refer the matter to the Public Accounts Committee for further scrutiny.
The Dasu Transmission Line Project aims to transmit electricity from the Dasu Hydropower Plant to Islamabad. It involves a 765 kV double-circuit transmission line, spanning approximately 250 kilometers, with a Mansehra and Islamabad West grid stations along the route.

Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Rs500m loss inflicted on national exchequer? Senate body raises questions over role of Nespak, NTDC
Rs500m loss inflicted on national exchequer? Senate body raises questions over role of Nespak, NTDC

Business Recorder

time5 days ago

  • Business Recorder

Rs500m loss inflicted on national exchequer? Senate body raises questions over role of Nespak, NTDC

ISLAMABAD: The Senate Standing Committee on Economic Affairs raised serious questions over the role of National Engineering Services Pakistan (Pvt) Limited (Nespak) and National Transmission and Dispatch Company (NTDC) in awarding the bid to the third lowest, causing Rs500 million loss to the national exchequer. The committee met with Saifullah Abro in the chair here on Thursday for further discussion on the recommendation made after detailed deliberations in the committee's previous meetings concerning the EAD and its related departments (NTDC projects including 765Kv Dasu-Islamabad Transmission Line project (LoT-I-LoT-IV) upto date progress, expenditure and briefing through MD, Nespak on ADB 401B-2022 LoT-II A(ACSR Bunting Conductor) regarding inquiries reports. The committee's chairman remarked that it was a matter of great embarrassment that Nespak, a national institution responsible for technical evaluations, failed to prevent such a decision. It was Nespak's responsibility to ensure proper verification, because Nespak's role is to scrutinise the document, he stated. Senator Abro highlighted that the 'contract is not awarded to the deserving by which the Rs500 million of the country could have saved.' He noted that 'the company to which the project was awarded Newage, Lahore, lacked the relevant experience, while expressing serious concern that this type of negligence cannot be ignored.' Senator Abro stated that the matter will be pursued through the relevant forums like, the Federal Investigation Agency (FIA), the Public Accounts Committee (PAC), and the National Accountability Bureau (NAB) to ensure that the public funds are recovered. He also recommended that strict action should also be taken against the involved officers. Referring to legal inconsistencies, he questioned 'if Public Procurement Regulatory Authority (PPRA) laws are not applicable in the case of domestic preference, and how can a letter from the Asian Development Bank (ADB) be considered valid?' He recalled that during the previous meeting, three written letters were presented by the caretaker minister, which further raised serious questions regarding the transparency of the process. When the committee sought further details, it was informed that all relevant data from the Engineering Development Board (EDB) had been destroyed in a fire, and only one verified letter was presented before the committee. Senator Kamal Ali Agha inquired whether an inquiry was conducted following the fire incident. The concerned department stated that no inquiry had been carried out. The chairman committee, recommended that a formal inquiry be conducted into the fire incident and that strict action be taken against those found responsible, including officers from the Power Division. During the committee meeting, a discussion was held regarding where the department conducts testing, which institutions are responsible, and where laboratories are located in Pakistan. The department informed the committee that type testing is conducted internationally and not within Pakistan. It was further stated that the type test for the current year, 2024, was conducted in Hungary. The chairman inquired about who the witness to the test? The department told that the witness was not verified. They also stated that, according to a 2023 policy, having a witness was not a mandatory requirement by the consultant. However, after detailed discussion, it was revealed that no such policy had been formulated. The chairman committee strongly remarked that no valid testing had been conducted and an attempt was made to mislead the committee, which amounted to fraud. The chairman asked whether any recovery of the misused funds had been made, to which the department responded that a letter had been written to NTDC regarding the matter. The chairman committee recommended that all the involved companies be blacklisted, the misappropriated funds be recovered, and that the officers involved be terminated from service. Furthermore, he recommended that the recovered amount should be deducted from the salaries of the responsible officers. The committee also inquired about the report and minutes of the 282nd Board meeting, as well as the letter issued by the NTDC Board. It was noted that while the minutes of the committee meeting were dated 24th December 2024, the Board was required to submit its report within 15 days. However, the BOD has submitted after six months. Meanwhile, the committee remarked that the Board itself is violating its own letter and treating the amount of Rs1.28 billion as insignificant. The chairman recommended that strict action be taken against the Board and that the amount be recovered within two weeks. Copyright Business Recorder, 2025

Shahid Nazir made NGC managing director
Shahid Nazir made NGC managing director

Business Recorder

time5 days ago

  • Business Recorder

Shahid Nazir made NGC managing director

LAHORE: The Board of Directors of the National Grid Company (NGC) of Pakistan Limited (formerly NTDC), in its 297th meeting, has approved the appointment of Engr Muhammad Shahid Nazir as the Managing Director of NGC. A formal notification has been issued in this regard. Prior to this appointment, Engr Shahid Nazir was serving as the General Manager Project Delivery (North) at NGC. He brings over 32 years of experience in the power transmission sector and has been instrumental in the execution of several key power transmission projects. Engr. Shahid Nazir holds a Bachelor's degree in Electrical Power Engineering from the University of Engineering and Technology (UET) Lahore, a Master's degree in Electrical and Electronic Engineering from the University of South Asia, Lahore and an MBA in Finance from the University of the Punjab, Lahore. Throughout his distinguished career, he has played leading roles in major projects such as the Matiari-Lahore Transmission Line under the China-Pakistan Economic Corridor (CPEC) and the Dasu Transmission Line Project, where he served as Chief Engineer. He has also represented Pakistan abroad on deputation. His appointment follows the retirement of Engr. Muhammad Waseem Younas, who completed his term as Managing Director yesterday (Thursday). On his final day, Engr Waseem Younas met with NGC officers and staff, expressing his best wishes and appreciation for their support. Engr Shahid Nazir has been assigned with the role of Managing Director on stop-gap basis and will serve in this capacity until a permanent appointment is made. On appointment, talking to the officers and employees, Engr Shahid Nazir expressed his gratitude to the Board of Directors for their trust. He reaffirmed his commitment to ensuring timely completion of ongoing NGC projects. Copyright Business Recorder, 2025

Rs600m corruption unearthed in Dasu project
Rs600m corruption unearthed in Dasu project

Express Tribune

time5 days ago

  • Express Tribune

Rs600m corruption unearthed in Dasu project

The Senate Standing Committee on Economic Affairs on Thursday detected mega corruption in Dasu Hydropower Transmission Line project, calling for a thorough investigation by the relevant authorities, including the Federal Investigation Agency (FIA) and the National Accountability Bureau (NAB). The committee which met with its chairman Senator Saifullah Abro in the chair, was informed that that the project contract was awarded on the basis of a letter from the Engineering Development Board (EDB) in 2015, while the National Engineering Services Pakistan (Nespak) presented wrong figures. The chair expressed anger over the alleged corruption in the project, amounted to Rs600 million. "How could the project be given to a company based on a letter," he raised the question. "It is the responsibility of all institutions to investigate it." The committee was informed that Nespak presented wrong figures during the scrutiny of the bidder, and the Nespak managing director confessed to the wrong figures. The committee directed action against the wrong figures presented by Nespak officials. "The negligence of the Power Division [in this issue] should be investigated. This matter should be investigated by NAB and FIA," Abro told the committee. "The officials who gave wrong figures should be terminated," he added.

DOWNLOAD THE APP