Department seeks to ‘reset the role and place of nuclear', boosts SA regulation budget

Department seeks to ‘reset the role and place of nuclear', boosts SA regulation budget

Daily Maverick23-04-2025
The Department of Electricity and Energy is laying the groundwork for a future with a lot more activity in South Africa's nuclear sector, according to its most recent strategic plan.
Languishing in the wake of the controversial 2015 Russian nuclear deal, South Africa's nuclear sector prospects have largely remained inert. That is all set to change according to the newly formed Department of Electricity and Energy's (DEE) most recent strategy that seeks to conclusively revitalise an increasingly energised sector.
Not everyone is convinced or on board, however.
Presenting the strategy to Parliament's Portfolio Committee on Electricity and Energy on Wednesday, 23 April, DEE acting Director-General Subesh Pillay explained that one of the Department's strategic priorities is to 'reset the role and place of nuclear'.
In November 2024, Minister of Energy and Electricity Dr Kgosientsho Ramokgopa stressed that nuclear energy would be a crucial part of South Africa's energy mix in the future and that activity was under way to re-energise the country's nuclear capacities.
'We think that we need to exploit our skills, exploit the accumulated knowledge with regard to nuclear technology over a period of time, and that's the case we're making to Cabinet,' he said at the time.
The path to making that happen became a bit clearer on Wednesday when the DEE told MPs that it intended to spend at least 23% of its R20.7-billion budget over the Medium‐Term Expenditure Framework (MTEF) on 'Nuclear Energy Regulation and Management'.
This amounts to roughly R1.543-billion for the 2025/2026 period, which is a 41% increase over the previous year.
This would be for nuclear regulation and management, including oversight of existing facilities, nuclear safety and feasibility planning for future builds – not direct investment in nuclear power plants.
Speaking to Daily Maverick in a committee meeting room on Wednesday, Pillay confirmed that this could be read as the department laying the groundwork for much more activity in the nuclear space. He qualified this by saying that a part of this large jump had to do with developments at the Nuclear Energy Corporation of South Africa (Necsa).
Research generator
'There's a research reactor [ at Necsa, called Safari ] and it's reached end of life. It's got about 10 years left so they're moving to closing Safari down and simultaneously, we're now building the next iteration of research generator, and that's why you had this big jump, because National Treasury has allocated R1.2-billion for that build programme over three years.'
This, he explained, formed the bulk of that jump in spending. But it was not the entire story.
Pillay agreed that the department was also laying the groundwork for a future with more electricity generated by nuclear energy.
'It's essentially that because at two levels, you must build the capability to increase your nuclear stock. When you do that, you must build the capability to regulate, so there has to be a correlation between the growth of nuclear use and the ability to regulate the nuclear sector,' said the acting DG.
Not everyone was pleased with the broad strokes outlined about the nuclear component in the department's strategy.
DA MP Kevin Mileham asked, in reference to the outdated 2019 Integrated Resource Plan (IRP 2019), 'What analysis has been done about the scale and pace of nuclear procurements that South Africa can afford?'
'What analysis has been done on 'pace and scale' because I'm not seeing anything about that. I haven't seen feasibility studies. I haven't seen any demand profiles – nothing.'
Mileham also pointed out that the strategy had assumptions that were based on some documents that don't yet exist.
'You talk about Nuclear Master Plan. You talk about Gas Master Plan. You talk about IRP 2025. Throughout this document, you're basing targets for this financial year on those three documents. But not one of those documents actually exists at this point.'
'They have not been approved by Cabinet; they have not been approved by the minister. So how are you determining a target that's based on a document that doesn't exist?' he asked, pointedly.
ANC MP Fasiha Hassan also pointed out some gaps in the information. 'We need an update on the Nuclear Master Plan… We also need to see the progress on the nuclear new build – where are we with that?'
Daily Maverick previously reported that at the end of 2023, Ramokgopa announced that all the 'suspensive conditions' to start procuring 2,500MW of new nuclear power 'immediately' had been met. However, in August 2024, he temporarily withdrew plans to procure new nuclear power, following a 'substantive' legal challenge by the Southern African Faith Communities' Environment Institute and Earthlife Africa Johannesburg.
Feasibility report
Lerato Makgae, Chief Director of Nuclear Policy at the department, provided an update and a response to members' questions.
'In terms of progress on the new nuclear build, as mentioned, we are working on the feasibility report for the nuclear build programme, which is encompassing a lot of information. Issues around the licensing, issues about skills development, looking at different technologies, whether it's large conventional plants that are being built in other countries, as well as SMRs (small modular reactors).'
'Right now, we noted that there are more than 80 designs of SMRs, which are in different stages of being commissioned. So we are monitoring that. The construction times would be in our feasibility report at the department, together with the nuclear entities and other government departments. Issues of 'pace and scale' would also be addressed in that feasibility report,' Makgae said.
On the mooted Nuclear Master Plan, Makgae said the department was at an 'early phase of the development' and promised to report on it quarterly.
Not everyone welcomed the news.
One of the people who shed light on the opaque and allegedly corrupt Russian-South African nuclear deal pushed under the Zuma administration was Makoma Lekalakala. She is the director of Earthlife Africa JHB, an environmental justice activist anti-nuclear organisation and one of the organisations that forced Ramokgopa to pause the more recent plans for nuclear procurement.
Also noting the language in the IRP 2019, committing the government to only pursuing nuclear energy 'on a scale and pace the country can afford', she asked, 'Is the country at an economic state to afford nuclear energy reactor construction?'
'We can't lock the country in any debt we cannot afford. Eskom's Medupi and Kusile costs have escalated more than threefold – the nuclear build might even be tenfold.' DM
Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

I want a three-way with Putin and Zelensky, says Trump on pending meeting
I want a three-way with Putin and Zelensky, says Trump on pending meeting

The South African

timean hour ago

  • The South African

I want a three-way with Putin and Zelensky, says Trump on pending meeting

US President Donald Trump said Wednesday he was planning a second meeting with Russian counterpart Vladimir Putin soon after Friday's Alaska summit – this time with Ukraine leader Volodymyr Zelensky included. Trump is due to sit down with Putin in Anchorage on Friday, the first meeting between the Russian leader and a sitting US president since 2021. 'If the first one goes okay, we'll have a quick second one,' he told reporters. 'I would like to do it almost immediately, and we'll have a quick second meeting between president Putin and president Zelensky and myself, if they'd like to have me there.' The high-stakes talks come with Trump seeking to broker an end to Russia's nearly three-and-a-half year war in Ukraine, and Zelensky and his European allies have urged the Republican to push for a ceasefire. A stepped-up Russian offensive, and the fact Zelensky has not been invited to the Anchorage meeting Friday, have heightened fears that Trump and Putin could strike a deal that forces painful concessions on Ukraine. Trump said Russia would face 'very severe consequences' if Putin did not agree to end the war after Friday's meeting, without elaborating. The US leader promised dozens of times during his 2024 election campaign to end the war on his first day in office but has made scant progress towards brokering a peace deal. He threatened 'secondary sanctions' on Russia's trading partners over its invasion of Ukraine but his deadline for action came and went last week with no action announced. Trump told reporters he'd had a 'very good call' with European leaders including Zelensky as he took questions from reporters at an arts event at Washington's Kennedy Center. 'I would rate it at 10. You know – very, very friendly,' he said. Let us know by leaving a comment below, or send a WhatsApp to 060 011 021 1. Subscribe to The South African website's newsletters and follow us on WhatsApp, Facebook, X and Bluesky for the latest news. © Agence France-Presse

Ukraine successfully tests Starlink's direct-to-cell technology
Ukraine successfully tests Starlink's direct-to-cell technology

TimesLIVE

time6 hours ago

  • TimesLIVE

Ukraine successfully tests Starlink's direct-to-cell technology

Ukraine's largest mobile operator Kyivstar has successfully conducted the first field test of Elon Musk's Starlink direct-to-cell satellite technology in Eastern Europe, the company said on Tuesday. The pilot test took place in the Zhytomyr region using Starlink's direct-to-cell technology, Kyivstar said, with its CEO Oleksandr Komarov and Ukraine's digital transformation minister Mykhailo Fedorov exchanging messages via regular smartphones. Direct-to-cell satellite technology aims to provide reliable connectivity when terrestrial networks are unavailable, a critical asset for war-torn Ukraine where Russian attacks on infrastructure regularly disrupt communications. Satellites used for this service are equipped with advanced cellular modems that function like cell towers in space, beaming signals directly to smartphones on the ground. Telecom providers around the world are turning to satellite technology in an effort to erase dead zones, particularly in remote areas where terrestrial networks are either too expensive to deploy or face significant geographical challenges.

Grid recovery brings hope for load shedding-free summer
Grid recovery brings hope for load shedding-free summer

The Star

time6 hours ago

  • The Star

Grid recovery brings hope for load shedding-free summer

Thabo Makwakwa | Published 4 hours ago South Africa's state of power grid shows real momentum after years of disruption, with unplanned outages shrinking, reliability rising, and a clear path toward a stable summer. During a media briefing in Pretoria on Wednesday, Minister of Electricity and Energy Dr Kgosientsho Ramokgopa framed the August briefing as evidence that disciplined maintenance, unit returns, and strategic upgrades finally translate into tangible, near-term resilience for households and businesses. The briefing, which draws on the Department of Electricity and Energy's August 2025 State of Electricity briefing, outlined a landscape in which unplanned outages are trending down and the grid shows signs of strengthened resilience ahead of the coming summer. Ramokgopa opened by acknowledging the progress while tempering expectations. 'What we're seeing is a recovery trajectory delivering real results - lower unplanned losses, higher reliability metrics, and a clearer path to secure generation capacity for the 2025/26 summer,' the minister said. 'We are not claiming victory, but we are confident that the combination of disciplined maintenance, returning units to service, and strategic upgrades will continue to strengthen the grid's resilience.' Key numbers presented in the briefing portray a sector moving away from the worst days of load shedding toward a more stable operating envelope. There has been no load shedding since 15 May 2025, with only 26 hours recorded between 1 April and 31 July 2025. Between 1 April and 7 August 2025, the Unplanned Capacity Loss Factor (UCLF) fell to 28.35%, a week-on-week improvement of about 0.23%. The ministry cautioned that the system remains sensitive to external pressures and the realities of operating a large, aging fleet - still, the data point to meaningful gains. Ramokgopa stated that the year-to-date Energy Availability Factor (EAF) stood at 60.14% by 8 August 2025 , up roughly 4.4 percentage points from April 2025. The weekly EAF oscillated between 62% and 70%, with a month-to-date average of 65.38%, signalling growing fleet stability and reliability. On the fuel side, he stated that the Open Cycle Gas Turbine (OCGT) performance showed a notable uptick in activity. The OCGT load factor reached 5.99% for the week, up from 0.31% the prior week. He stated that from 1 April to 7 August 2025 (the winter period), Eskom spent about R5.842 billion on fuel for its OCGT plants, generating 988.56 GWh. 'The year-to-date OCGT load factor stood at 9.35%, a slight week-on-week decrease but still higher than the 4.82% recorded during the same period last year.' The briefing highlighted a broad set of initiatives under the Operational Reliability and Sustainability Plan, designed to push long-term reliability and safety. These efforts include reducing the number of trips, improving outage planning and execution, and accelerating the implementation of strategic projects. The plan also emphasised a strengthened people-plant-process mindset, with root-cause analysis, trip reduction directives, and expanded partnerships with original equipment manufacturers and other utilities to improve availability of spares, technology, and maintenance capability. Beyond maintenance, the minister emphasised capacity additions and returns from units brought back from long-term outages. Since late 2023, several key units have returned online or been upgraded, contributing to approximately 2,500 MW of added capacity. Ramokgopa added that notable milestones include Koeberg Unit 1 returning to service, Kusile units coming back online, and Medupi Unit 4 synchronising in July 2025, all of which aim to reinforce security of supply as the grid moves through a transition period. The minister said that the improvements are about short-term numbers and longer-term stability. 'The focus on Koeberg, Medupi, Kusile, Tutuka, and other critical stations is about more than today's metrics. It's about maintaining a stable, predictable power system that supports households, industry, and the broader economy,' Ramokgopa said. [email protected] IOL Politics

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store