HS2's structures should have been ‘largely completed' by now

HS2's structures should have been ‘largely completed' by now

Mark Wild, HS2 Ltd chief executive, said one of the main causes of the delays was starting construction work before designs were finalised and local planning consents were in place.
Notice to proceed was granted by the government in April 2020.
This is a huge, considerable, maybe the biggest civil engineering project ever undertaken in this country. The facts are, in the first two years of effort, we simply didn't make enough progress Mark Wild, HS2 Ltd
Mr Wild blamed cost overruns on the awarding of contracts which meant the government held all the risk in case of problems, and failings of HS2 Ltd.
He said the coronavirus pandemic and the rise in inflation caused by Russia's invasion of Ukraine had also had an impact.
Phase One of HS2 between London and Birmingham was initially planned to open by the end of 2026.
This was later pushed back to between 2029 and 2033, but Transport Secretary Heidi Alexander said last month there was 'no route' to meeting that timeframe.
In 2013, HS2 was estimated to cost £37.5 billion (at 2009 prices) for the entire planned network, including the now-scrapped extensions from Birmingham to Manchester and Leeds.
In June last year, HS2 Ltd assessed the cost for the line between London and Birmingham would be up to £66 billion.
HS2 workers gather to observe boring machine Mary Ann breaking through at Washwood Heath depot near Birmingham city centre (Jacob King/PA)
Mr Wild, who was appointed late last year, told the Commons Transport Select Committee: 'The construction of the civil engineering should have been largely completed by now.
'The reality is we're about 60% complete.'
He added: 'The whole scheme, which includes, of course, the tracks, the overhead lines, the trains, the system integration, we're about a third complete.'
Mr Wild described the project as 'a unique challenge in this country'.
He went on: 'A third of this route is actually underground or in cuttings.
'This is a huge, considerable, maybe the biggest civil engineering project ever undertaken in this country.
'The facts are, in the first two years of effort, we simply didn't make enough progress.'
Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

The little-known area of ‘bohemian Birmingham' where house prices are booming
The little-known area of ‘bohemian Birmingham' where house prices are booming

Telegraph

timea day ago

  • Telegraph

The little-known area of ‘bohemian Birmingham' where house prices are booming

As Jana Walter poured more and more cash into her money pit of a fixer-upper house, she took comfort in one thing. The sprawling Victorian property is in the south Birmingham suburb of Moseley where, by the end of the year, a new railway station will open linking it to the city centre. 'I knew it was coming and it made me a bit more courageous in terms of the renovation,' says Walter. 'I think the street will come up in time and it will be a good investment.' Certainly, new train lines have a habit of triggering outperforming house price growth, the most obvious example being London's Elizabeth line. Between 2009, when work began on the new cross-London line, and 2021, a year before it finally opened, prices had more than doubled in many of the areas the new service would pass through, according to a study by Knight Frank. Birmingham's Camp Hill line is a much smaller project, which will reopen the train line between the city centre and Moseley, King's Heath and Stirchley. Services last ran in 1941 before becoming a victim of wartime cuts. Journey times to New Street will be a maximum of 14 minutes, turning these three neighbourhoods into prime commuter suburbs. And, when the new HS2 line eventually opens at Curzon Street, half a mile from New Street, it will be possible to reach London in 49 minutes. Walter, 44, a former management consultant who is currently working as a chef, bought her fixer-upper house back in 2020 for just £285,000. 'Yes, it was cheap,' she laughs. 'But there is a reason for that.' Restoring the house has taken five years and counting. Walter, along with her sons Noah, three and Isaac, one, and Evie the cocker spaniel, finally moved in earlier this year, having spent comfortably more on the work than the house cost to buy. The motive for the move, from Ladywood, in west Birmingham, was partly space, since Walter had previously lived in a smaller end-of-terrace house. 'The other reason was that Ladywood doesn't really have a high street,' she says. 'Everything was a drive away or a 30 to 40-minute walk. Moseley was at the top of my list because it is a very pretty place, it has good shops and cafes, and a diverse community. There are some real characters, which is fantastic.' Defying the house price slump Price growth around Crossrail stations began almost as soon as funding for the new line was announced. The Camp Hill Line was confirmed in March 2021 with an opening date expected in 2023 and the news, says Ashley Lowe, of Rice Chamberlain estate agents, generated plenty of buzz. 'But because it got pushed back and pushed back, many people are waiting until there are actually trains on the platform [to buy],' he says. Despite the delays to the line, research by Hamptons suggests that price growth along the line in the past five years has been impressively healthy. Average sale prices in Moseley and Stirchley have increased 20pc, to £326,000 and £282,000 respectively. King's Heath prices rose 16pc to an average £262,000 in the same period. This growth looks particularly impressive when compared to trendy Harborne, four miles away. Prices there are up just 5pc to £347,000. Three miles away, affluent Edgbaston's prices have fallen 7pc to £377,000. The past year has been a tough one for the UK's property market, with April's stamp duty threshold changes, stiff interest rates and global insecurity. Despite these headwinds, Moseley saw prices grow 4.5pc, King's Heath 2.4pc and Stirchley 1pc over the past 12 months, according to Hamptons. By comparison, Harborne's prices are also up 1pc, but Edgbaston's have fallen by 5.8pc. In Moseley, James Brain, of Robert Oulsnam Estate Agents, says the key driver of the area's market is its good stock of large family homes which attract buyers like Walter. 'The vast majority of buyers are moving very locally, they tend to move up here from smaller homes as family size increases, and then they tend to stay,' he says. The area itself is also a selling point. 'It is quite a vibrant place, a very diverse location, and it is considered to be the bohemian part of Birmingham,' explains Brain. 'You have got good nightlife and restaurants, you are surrounded by parkland and you are only 2.5 miles from the city centre.' If Moseley is family territory, then King's Heath, which will be one stop down the new line, is all about first-time buyers. Lowe says many young professionals come to him after a spell renting in the city centre. Often, he says, they are priced out of Moseley, but in King's Heath, they can pick up an average three-bedroom terrace for around £300,000 to £320,000. As well as its value for money, King's Heath has acquired a reputation for being one to watch. Certainly its high street is filling up with new coffee shops and bars, there are artisan markets and live music events, and every summer, thousands attend the annual Queen's Heath Pride event. Stirchley has also seen its fortunes change in the past five or so years, says Lucy Carter, a valuer and senior negotiator at Nicholas George estate agents. 'There are a lot more independent shops and restaurants, there is a lot happening now which there wasn't in the past,' she says. Carter believes that the changes in Stirchley are more likely to be gentrification as buyers spill over from more expensive neighbours. However, now that the train line is months from completion, she notes that demand for homes close to all three stations is increasing as buyers finally believe the service will really happen. 'I definitely think it will add more value now,' she says.

South Yorkshire residents' relief at end of HS2 restrictions
South Yorkshire residents' relief at end of HS2 restrictions

BBC News

time3 days ago

  • BBC News

South Yorkshire residents' relief at end of HS2 restrictions

People living on land previously earmarked for the scrapped HS2 route in South Yorkshire have spoken of their relief that planning protections affecting their homes have been eastern leg of the project linking Birmingham and Leeds, which was cancelled in 2021, was meant to pass through Bramley, near Rotherham, and as a result the route was "safeguarded" by the safeguarding protections, ended by Transport Minister Heidi Alexander last month, meant it was harder for residents to change or sell their properties as HS2 had to first Haith, from Bramley HS2 Action Group, said there was "relief and elation as a community as people have got their homes back". In a statement, the transport minister said the legal removal of the safeguarding directions for the eastern leg would take away the "uncertainty" that had affected people living near the proposed route. In Bramley, the proposed high-speed HS2 route would have passed between housing and the M18, with owner of nearby properties facing the possibility of their homes being compulsorily purchased by the government and the celebrations, Ms Haith said the nine-year battle had "taken its toll" on members of the action group and local residents."I've just turned 72. I have better things to do with my time than fight HS2," she explained."For nine years people haven't been able to do what they want with their own properties."Meanwhile, David Hatfield, another campaigner and a photographer who captured images of the route and of public meetings about HS2, said he felt a "sense of relief and finalisation" knowing the safeguarding protections had finally been lifted and the development would not be he said his relief was certainly also tempered by the memories of the last nine years."I can still remember people coming out of meetings crying because their property was safeguarded, which meant it would be knocked down or taken off them." On the Shimmer estate in Mexborough, a housing development where construction work got under way in 2011, the mood among people remained sombre following the transport secretary's confirmation that safeguarding protections had five years after work started on the estate, the homes were put under threat when proposals for the eastern leg of the HS2 route were original plans for the route called for the demolition of 16 properties on the estate to make way for a railway the end, a large number of homeowners on the new estate sold their houses to the government and moved felt they had little choice after being told the value of the homes had declined to zero and potential new buyers were unable to get a mortgage.A former local councillor said that today only "two or three" of the original buyers remained on the Shimmer remainder of the 212 units there are rented out by the government, often at below market rate. Former residents declined to talk about the transport secretary's announcement to the BBC, but Sean Gibbons, deputy leader of the Mexborough First party, said: "The damage is done here.""Most went into negotiation with HS2 and sold their homes. Many felt they didn't get a fair deal," he transport minister's statement confirming the lifting of safeguarding along the scrapped eastern leg of HS2 referred to a programme to "dispose of" 550 properties no longer required, with the sales of those properties expected to begin in also confirmed that former owners would have the opportunity to buy back their homes at their current Mr Gibbons said it was "very unlikely" anyone would want to take up the offer."If you've been through all the turmoil, you're not going to come back," he said. Listen to highlights from South Yorkshire on BBC Sounds, catch up with the latest episode of Look North

First look inside UK's new £2bn high speed trains with underseat luggage storage and the ‘most comfortable seats ever'
First look inside UK's new £2bn high speed trains with underseat luggage storage and the ‘most comfortable seats ever'

Scottish Sun

time01-08-2025

  • Scottish Sun

First look inside UK's new £2bn high speed trains with underseat luggage storage and the ‘most comfortable seats ever'

Packed with hidden comforts and one clever fix passengers have begged for ON TRACK First look inside UK's new £2bn high speed trains with underseat luggage storage and the 'most comfortable seats ever' Click to share on X/Twitter (Opens in new window) Click to share on Facebook (Opens in new window) THE public is getting a first look inside Britain's new £2billion high-speed trains, featuring underseat luggage storage. In Derby, this weekend, train enthusiasts will be able to step aboard a full-size model of HS2's new Class 895 train at Alstom's Litchurch Lane Works. Sign up for Scottish Sun newsletter Sign up 3 The full contract to design and build 54 trains is worth around £2billion Credit: HS2 The replica carriage is part of 'The Greatest Gathering', a landmark event celebrating 200 years of the British railway, offering visitors a first-hand look at what the future of rail travel might look like. The sleek new interiors have been developed by HS2 Ltd, the West Coast Partnership and the Hitachi-Alstom High Speed team. The full contract to design and build 54 trains is worth around £2billion. These trains are expected to run at speeds of up to 360 km/h, and will be able to continue beyond the HS2 line on existing tracks to Manchester, Liverpool and Glasgow. Each one is designed to be among the fastest, quietest and greenest trains in the world. Inside the carriage, the standard class seats promise what HS2 calls 'market-leading' legroom at 87 centimetres. Passengers will also get USB-C and 3-pin charging sockets, dropdown tables, small shelves for devices, and handy coat hooks. The seats recline without tipping backwards, thanks to a clever sliding mechanism, a much-needed upgrade for passengers fed up with stiff, upright seating on older UK services. This public unveiling marks the first time people can physically experience the carriage design after concept images were released in late 2024. It comes at a crucial time for HS2, which has faced rising public pressure and political scrutiny over its soaring costs and long delays. Officials hope the new trains will help restore some excitement around a project that has often struggled to win hearts or headlines for the right reasons. Recent HS2 stories have highlighted both progress and pain. In London, major milestones have been reached at Old Oak Common, the capital's new £2billion 'super station'. New 400-metre platforms have been laid and work is ramping up to prepare the site for up to 250,000 passengers a day. But in stark contrast, residents in places like Burton Green, Warwickshire, say the rail line has brought nothing but chaos. A 700-metre tunnel has sliced the village in half, and locals complain of years of noise, disruption and falling house prices, many say the project no longer benefits them in any way. Earlier this summer, The Sun revealed that HS2 bosses were blowing £1,200 a month on tropical office plants while project costs continued to climb. The London to Birmingham section alone is now expected to cost between £49bn and £67bn, with £27bn already spent. 3 The line itself is now far behind schedule It's just one of several recent examples that have drawn criticism over how taxpayer money is being used. The line itself is now far behind schedule. Originally pitched as a Y-shaped high-speed network linking London, Birmingham, Manchester and Leeds, the project has been scaled back to a single leg between London and Birmingham. Even this stretch isn't expected to open until at least 2033 — more than ten years behind its original target. HS2 Ltd CEO Mark Wild recently told MPs that early mistakes, including awarding major civil engineering contracts before final designs were ready, led to ballooning costs. The price of civil works has risen from £19.5bn to £26bn. Wild says the project is now in a full reset phase, with delivery teams being rebuilt and construction work only moving forward when designs are fully mature. Still, there are bright spots. The 3.4km Colne Valley Viaduct, one of the project's most visible feats, is nearing completion after years of careful work. The twin-bore Chiltern Tunnel was completed earlier this year, and the enormous Northolt Tunnel under west London broke through in June 2025 after four giant boring machines worked for months to finish the job. So while passengers can now glimpse the inside of HS2's trains — and enjoy a seat that might finally deliver comfort at speed — the reality is that the journeys they're built for are still a long way off. 3 Each one is designed to be among the fastest, quietest and greenest trains in the world Credit: HS2 The trains may be ready, but the track ahead remains far from clear.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store