Key projects put on ice for another year
Over the past 12 months, the Rawalpindi Development Authority (RDA), Water and Sanitation Agency (WASA), the District Council, District Administration, and Municipal Corporation have all failed entirely to initiate a single one of these projects.
The projects have been pending for 17 years, and continuous delays have caused their estimated costs to surge by 100 to 300%, with a further 25% increase expected after budget approvals.
Among these mega projects are the Lai Expressway, sewerage water tunnel and treatment plant, Ghazi Brotha water project, new large-diameter steel pipeline from Rawal Dam for additional water supply, Mother and Child Hospital, Ring Road, three large commercial parking plazas, underpasses from Mareer Chowk to Liaqat Bagh Chowk, Doodhcha Dam, and Chehan Dam water supply scheme. All these projects were initially prepared between 2008 and 2012 but were sidelined due to frequent changes in political governments.
The 22-kilometer Lai Expressway was launched in 2008, with its foundation stone laid by then-President General Pervez Musharraf. However, despite 17 years having passed, it remains incomplete. Its initial estimated cost of 1.7 billion rupees has now escalated to 11 billion rupees.
The Mother and Child Hospital is a 12-year-old project. Although the state-of-the-art building housing 13 operation theaters was completed, the project has been shut down for the last three years. Originally costing Rs900 million, the building was completed with an OPD inauguration planned for April 30, 2022.
However, the government was dissolved on April 10, and the project stalled. Since then, windows, cabinets, doors, iron grills, and machinery have been stolen, and the expansive building has become a shelter for bats, dogs, cats, and snakes. While an additional Rs25m was allocated, work stoppage has caused losses to soar to approximately Rs150m.
The sewerage water tunnel and treatment plant, originally estimated at Rs3b and now costing over Rs6b, has been stalled for four years. Similarly, the Chehan Dam water supply scheme has been repeatedly promised throughout the year, but as the fiscal year ended, it too was pushed into the new budget. Its cost has risen from Rs600m to 650m.
The Rawal Dam new pipeline and commercial parking plaza projects have proved to be mere publicity stunts. The Ghazi Brotha water project, crucial to meeting the twin cities of Rawalpindi and Islamabad's water needs for 100 years, was also neglected again this year. Without Ghazi Brotha, the water crisis of the twin cities cannot be resolved. The project cost has inflated from Rs8.7b to Rs20b over 10 years.
The Doodhcha Dam and Ring Road projects have become deadlocked due to extreme delays. Their completion deadlines have expired repeatedly, and now they too have been pushed into the new fiscal year.
Because of the severe financial crisis, the District Municipal Corporation failed to launch any significant development scheme during the outgoing fiscal year 2024-25.
However, District Development Committee convener and MNA Engineer Qamar-ul-Islam claims that record-breaking roads have been constructed this year, and with a record development budget in the new fiscal year, all mega projects will finally be initiated.
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Express Tribune
7 hours ago
- Express Tribune
Rawalpindi plans Leh revamp
esidents of Dhoke Chirag Din continue to dump garbage along Nullah Leh's banks in Rawalpindi, defying Section 144 imposed by the city administration. PHOTO: ONLINE Authorities have decided to widen the 16-kilometre-long Nullah Leh drain, install barbed fencing on both sides, and divide it into 16 sections to expedite rehabilitation work. The Rawalpindi Development Authority (RDA) has requested proposals from the Municipal Corporation to formulate a permanent flood prevention strategy. An important meeting on Nullah Leh was chaired by Deputy Commissioner Dr Hassan Waqar Cheema on Wednesday. The meeting reviewed long-term solutions to the recurring flood problem. Participants included Additional Deputy Commissioners Abdullah Khan and Shehryar Shirazi, RDA Director General Kinza Murtaza, and officials from other concerned departments. Officials suggested assigning each segment to a separate construction company to ensure speedy work. Plans for fencing, construction, and an effective monitoring system were discussed to not only address the flooding issue but also beautify the surrounding areas. The meeting also reviewed the original 2003 Nullah Leh widening plan. Dr Cheema directed the RDA, WASA, Municipal Corporation, and other departments to finalise their recommendations promptly so the project can move into the execution phase. Encroachers warned On the other hand, the Capital Development Authority (CDA) has intensified its crackdown on illegal encroachments in Islamabad, particularly structures built over natural stormwater drains (nullahs). They have issued warnings that such constructions pose severe flooding risks and will be demolished without exception. The announcement came during a high-level meeting held at the CDA Headquarters, chaired by Chairman CDA and Islamabad Chief Commissioner, Muhammad Ali Randhawa on Friday. According to the briefing, enforcement teams have already begun sealing and demolishing illegal structures built over nullahs, in accordance with directives from Federal Interior Minister Mohsin Naqvi. The campaign aims to reclaim government land from illegal occupants and prevent life-threatening scenarios during Islamabad's increasingly intense monsoon rains. "Buildings constructed over nullahs without a hydraulic study or CDA approval are not only illegal but highly dangerous. These structures could collapse during a major flood," said Chairman Randhawa, citing heavy rainfall this monsoon season-the highest since 2001-as a serious wake-up call. Residents and commercial property owners have been urged to voluntarily remove all encroachments from stormwater channels. "If not removed voluntarily, these structures will be sealed, declared hazardous and legal action will be initiated. The responsibility will lie entirely with the encroachers," Randhawa warned. In addition to enforcement, the CDA is implementing preventive measures to stop future encroachments. A permanent monitoring system will be established, utilising drone surveillance and Google Earth mapping to track reclaimed land. The authority also announced the digitisation of layout plans, the No Objection Certificate (NOC) process and fee payments for map approvals through a new cashless system. "We are digitising our One Window Facilitation Centre and computerising land records to enhance transparency and service delivery," said the Chairman, adding that these reforms will also help curb fraudulent construction practices and improve public access to services. The citywide anti-encroachment drive has been initiated following repeated flooding incidents in Islamabad's residential and commercial sectors. Experts have warned that unregulated construction over nullahs obstructs natural water flow, leading to urban flooding and potential loss of life. The CDA reiterated its commitment to carry out indiscriminate operations across all sectors of the city and urged citizens to cooperate in maintaining lawful development and environmental safety.


Express Tribune
5 days ago
- Express Tribune
RDA inflows rise to $10.56b; rupee stable
Listen to article Foreign investors repatriated profits worth $2.22 billion in FY25, mirroring the amount recorded in FY24. The power sector led all categories with outflows totalling $399 million, marking a 1.6-time increase from the previous fiscal year, according to data compiled by AKD Securities. The financial sector followed with repatriation of $385 million, though it represented a 40% decline from FY24. The food sector also posted a notable outflow of $306 million, up two times year-on-year. AKD report attributes the high FY24 figure largely to a backlog from FY23, when repatriations had dropped significantly to $331 million. The 20-year average now stands at $1.4 billion, indicating a strong recovery in the past two years. June 2025 saw a sharp 72% year-on-year (YoY) drop in monthly repatriation, totalling $114 million compared to $414 million in June 2024. Sector-wise, communications, financial services and transport witnessed significant YoY declines, while personal services and oil & gas exploration saw increases. On the other hand, the inflow of remittances under the Roshan Digital Account (RDA) rose to $10.563 billion by the end of June 2025 as compared to $10.381 billion by May-end, according to APP. The arrival of remittances during May was recorded at $182 million as compared to $201 million in May 2024 and $177 million in April 2025, according to the latest data released by the State Bank of Pakistan (SBP). The number of accounts registered under the programme rose 8,739 to 831,963 in June 2025 from 823,224 accounts in May 2025. By the end of June, overseas Pakistanis invested $466 million in the Naya Pakistan Certificates, $926 million in the Naya Pakistan Islamic Certificates and $70 million in Roshan Equity Investment. Furthermore, the Pakistani rupee held steady against the US dollar on Tuesday, recording a marginal depreciation of 0.01% in the inter-bank market. By the end of trading, the rupee closed at 284.97, slipping just two paisa compared to Monday's close at 284.95. Meanwhile, gold prices in Pakistan remained unchanged, despite a rally in the international market, where the precious metal climbed to a five-week high amid growing global uncertainty. According to the All Pakistan Sarafa Gems and Jewellers Association, the price of gold per tola stood firm at Rs361,200, while the rate for 10 grams also held steady at Rs309,671. This stability follows a sharp increase on Monday, when the price per tola rose Rs3,600. Internationally, gold gained momentum as concerns over trade tensions and weak US bond yields lifted safe-haven demand. Investors continue to monitor the August 1 tariff deadline set by US President Donald Trump, alongside developments surrounding the Federal Reserve's interest rate outlook. Spot gold rose 0.6% to $3,415.61 per ounce by 1414 GMT, hitting its highest since June 16, according to Reuters. US gold futures were up 0.6% at $3,428.10. The yield on benchmark US 10-year notes fell to a near two-week low, making non-yielding bullion more attractive. Interactive Commodities Director Adnan Agar noted that gold remained on an upward trend globally, with the market touching a high of $3,430 per ounce. "The market is hot right now," he said, citing geopolitical uncertainty, Trump's repeated tariff threats and speculation surrounding a potential US interest rate cut in September. "There's a strong chance gold could test the $3,450-55 range before correcting down to $3,400 or even $3,380," Agar added. With multiple geopolitical triggers on the horizon, including potential tariffs on Europe and continued pressure on the Fed, global gold prices are expected to remain volatile in the days ahead.


Express Tribune
19-07-2025
- Express Tribune
Several illegal commercial units sealed
The Enforcement Squad of the Rawalpindi Development Authority (RDA) launched a robust operation against illegal constructions, sealing 17 unauthorised commercial properties located at Mid City Apartments, Service Road, Mouza Gangal. The operation was carried out with the support of the Old Airport police and led by the RDA Enforcement Squad. The team comprised the Assistant Director of Building Control, building inspectors, and other relevant officials. Among the sealed properties were 10 offices, two apartments, one restaurant, and four hotels. Noteworthy establishments included the Overseas Recruitment Agency, Ghauri Town offices, WB Centres, JD Aviation, and others. According to an RDA spokesperson, the owners had constructed commercial buildings without securing the required No Objection Certificates (NOCs) and in violation of approved building plansactions that contravene the Punjab Development of Cities Act, 1976, and the RDA Building and Zoning Regulations, 2020. RDA director-general Kinza Murtaza has also directed the Building Control Wing to conduct a detailed survey of all unauthorised residential and commercial structures. This includes reviewing approvals, commercialisation status, completion plans, and associated fees and charges. The directive further emphasises that all illegal constructions within the RDA-controlled area must be regularised in accordance with existing regulations.