ISLAMABAD: The Ministry of Housing and Works and its executing agency, Pakistan Public Works Department (Pak PWD), have come under scrutiny after the Audit Report 2024–25 flagged financial mismanagement, unauthorised payments, non-recoveries, and procedural violations amounting to over Rs3.63 billion.
The report highlights that Rs1.1 billion was paid to contractors for various civil works without following the required approval processes or verification protocols.
While names of contractors are not mentioned, audit officials noted that the payments were made without completion certificates or evidence of actual progress. Performance guarantees were often not obtained, and there were serious deviations from standard public procurement procedures.
An additional Rs225.9 million in public funds was lost due to inordinate delays in the construction of the Islamabad Model College for Boys, Margalla Town.
The project, originally approved in 2008 and revised multiple times until 2023, suffered from delayed land possession by CDA and slow disbursement. Audit held the project management responsible for this delay and cost escalation.
Another audit para revealed that Rs5.18 million was paid in advance to the CDA for the renovation of bathrooms in the Planning Commission's P Block, but the work remained incomplete even after 18 months. The CDA failed to submit any completion report or provide an account of the funds spent.
In a separate finding, encroachment and unauthorised allotment of over 29 kanals of land belonging to International Islamic University Islamabad (IIUI) was traced back to CDA's actions, which had allotted portions of the university's land to private individuals and retained heavy machinery within the university premises despite court orders and environmental concerns.
The report also identifies systemic issues in financial management and tenant oversight. Pak PWD failed to recover rent and utility bills from allottees of government residences, despite multiple reminders and audit observations in past years. The dues had accumulated over time, and neither eviction actions nor late payment penalties were enforced. Audit also noted the lack of updated tenancy records, making accountability more difficult.
Despite the scale of observations, no response was submitted by the Ministry or Pak PWD to most audit objections, and Departmental Accounts Committee (DAC) meetings were not convened in time. The report recommends fixing responsibility, recovery of outstanding dues, and strict enforcement of financial controls.
Copyright Business Recorder, 2025
Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

CDA chief orders third-party audit of uplift projects
CDA chief orders third-party audit of uplift projects

Business Recorder

time14 hours ago

  • Business Recorder

CDA chief orders third-party audit of uplift projects

ISLAMABAD: Chairman Capital Development Authority (CDA) and Chief Commissioner Islamabad Muhammad Ali Randhawa on Monday directed third-party audits for all ongoing development projects, and ordered expedited completion of Islamabad Model Jail, IT Facilitation Centres, electric tram feasibility, and the operationalisation of the Blue Area Food Street. The directives came during a review meeting at the CDA headquarters. The meeting was attended by senior CDA and ICT Administration officials, including Member Administration and Estate Talat Mehmood, Member Engineering Syed Nafasat Raza, Member Environment Esfandyar Baloch, and others. The meeting reviewed progress on critical infrastructure and urban uplift projects such as Shaheen Chowk, Kashmir Chowk, Faizabad Interchange, Gardenia Hub (CDA Model Nursery), Pak Secretariat uplift, modern streetlight installation, police station upgrades, Safari Park, Theme Park, cable car, ferris wheel, and dancing fountain initiatives. Randhawa also instructed a detailed financial study of all projects recently transferred from PWD to CDA, including cost assessments, fund utilisation, and quality evaluation. He tasked the Planning and Engineering Wings to develop a strategy for the timely and efficient completion of these projects. In addition, directives were issued to accelerate the rollout of electric buses, establish charging stations, enhance the solid waste management system, improve water supply across sectors, and upgrade all 279 parks in Islamabad. Funds from CDA's commercial plot auctions will be channelled into these initiatives. Copyright Business Recorder, 2025

Rs3bn financial mismanagement identified in Aviation Ministry
Rs3bn financial mismanagement identified in Aviation Ministry

Business Recorder

time16 hours ago

  • Business Recorder

Rs3bn financial mismanagement identified in Aviation Ministry

ISLAMABAD: Financial mismanagement exceeding Rs 3 billion has been identified in the Ministry of Aviation and its attached organisations, including the Pakistan Civil Aviation Authority (PCAA) and Airport Security Force (ASF), according to the Audit Report 2024–25. The report points to irregular contract awards, unauthorised payments, poor recordkeeping, and weak internal controls across several operations. A major portion of the losses, Rs 2.3 billion, arose from the PCAA's failure to recover long-standing dues from airlines and other stakeholders. Despite repeated audit observations in prior years, the outstanding receivables remained unpaid, highlighting ineffective enforcement mechanisms and weak follow-up from the authority. Another Rs313.6 million was noted as an irregular expenditure on account of consultancy contracts awarded without following the prescribed Public Procurement Rules (PPRA). The audit found that the PCAA hired consultants for design and supervision tasks without competitive bidding or proper approval, raising concerns about transparency and value for money. Separately, PCAA spent Rs154.6 million on procurement of equipment and services without the required sanction from the competent authority. The report also flagged unapproved advance payments and missing documentation, calling into question the compliance culture within the organisation. The ASF was also found in violation of financial rules. An expenditure of Rs45.8 million was incurred on procurement of vehicles and uniform items without proper tendering procedures. Moreover, ASF did not maintain inventory records, making physical verification and accountability difficult. In another para, Rs125 million was paid as rent to a private landlord for an ASF camp without documentation to prove space utilisation or rental agreement terms. The auditors noted that the lease extension and increased payments lacked legal vetting. The audit also noted issues in asset management. Several properties and pieces of equipment purchased by the PCAA and the ASF were not recorded in fixed asset registers, increasing the risk of misuse or loss without traceability. Despite the repeated nature of such audit findings over the years, the concerned departments failed to provide adequate responses or rectification plans. In many cases, Departmental Accounts Committee (DAC) meetings were not held, and no accountability measures were initiated. The audit report calls for strict adherence to financial regulations, recovery of outstanding dues, and fixing responsibility on officials involved in bypassing procurement and approval procedures. It also recommends enhancing internal audit functions within the ministry and its entities to prevent recurrence. Copyright Business Recorder, 2025

7th NFC Award: ‘Centre deducts Rs87.87bn annually without AGP certification'
7th NFC Award: ‘Centre deducts Rs87.87bn annually without AGP certification'

Business Recorder

time2 days ago

  • Business Recorder

7th NFC Award: ‘Centre deducts Rs87.87bn annually without AGP certification'

ISLAMABAD: Despite the passage of over 15 years since the 7th NFC Award was enacted, the federal government continues to deduct Rs 87.871 billion annually in collection charges on notional basis without the legally required certification from the Auditor-General of Pakistan (AGP), according to the Audit Report 2024–25. Audit report on the accounts of federal government (civil) audit year 2024-25 cited Clause 2(a) of the Distribution of Revenues and grants in-aid order, 2010: that the net proceeds mean, in relation to any tax, duty or levy, the proceeds thereof reduced by the cost of collection as ascertained and certified by the AGP. The management of the Finance Division distributed an amount of Rs 4.928 trillion as National Commission Award to the provinces and deducted Rs. 87.871 billion as one percent collection charges during 2023-24. Finance minister urges population as key criterion in NFC Award formula Finance Division was deducting one percent as collection charges amounting to Rs87.871 billion on national basis and did not have actual amount of collection charges, which was against clause 2(a). No proof for ascertaining and certifying the collection charges from the AGP was produced to audit. Sources within the Ministry of Finance admit that since the NFC Award was implemented in 2010, the issue of uncertified deductions has remained unresolved. 'It's been 15 years, yet the Finance Division has failed to obtain the AGP's certification, and the Public Accounts Committee (PAC) has not taken decisive action to enforce compliance,' a senior official acknowledged. The management replied that the Finance Division deducted one percent of the divisible pool of taxes as collection charges pursuant to the recommendation of the 7th NFC Award. The accounts of the Federation are submitted to the Auditor General of Pakistan for certification by the AGPR. During certification of collection charges so determined by the Auditor General it would be adjusted accordingly. Furthermore, the NFC transfers for the fiscal year 2023-24 have already been reconciled with the provincial finance departments, AGPR sub offices and AG offices. The Provincial governments have no objection on this account. The reply of the management is not tenable because collection charges need to be deducted after determination and certification of the AGP. Afterwards, the amount needs to be disbursed to the provinces, which was not done by the Finance Division. Audit maintained that non-deduction of actual collection charges was irregular, besides, it was an essential requirement of the Order to get the collection charges determined and certified by the AGP. Auditors flagged this deduction as irregular and unsupported, noting that no certified cost breakdown or approval from the AGP was provided for verification. Despite repeated observations in past audit cycles, this critical requirement remains unfulfilled. The DAC in its meeting held on 13th January 2025, directed the Finance Division to take up the matter with the AGP for the purpose. Audit recommended that necessary requirement of the Distribution of Revenues and Grants–in-aid Order, 2010 regarding certification and ascertainment of deduction charges by AGP, be complied with. Further, record of collection charges be provided to Audit for verification. Copyright Business Recorder, 2025

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store