Bullet train project: How a 12-storey high bridge is coming about, segment by segment, over Sabarmati River in Ahmedabad

Bullet train project: How a 12-storey high bridge is coming about, segment by segment, over Sabarmati River in Ahmedabad

Indian Express2 days ago
An under-construction bridge over the Sabarmati River in Ahmedabad, which is part of the Mumbai-Ahmedabad High Speed Rail Corridor (MAHSR) or Bullet Train Project, is being built with the advanced Balance Cantilever Technique — where the superstructure is built segment by segment, without deploying support structures needed in the scaffolding style of bridges. When complete, the bridge, spanning 480 metres, will be 36-metre-high from the riverbed — equivalent to a 12-storey building.
Located adjacent to the Western Railway's Ahmedabad-Delhi main line, which is about 14.8 meter high, the Sabarmati Bridge on the Bullet Train corridor will stand on a total of eight circular piers, four of which will be located in the riverbed.
The National High Speed Rail Corporation Limited (NHSRCL) on Friday said, 'A total of eight circular piers with diameters of 6 to 6.5 meters are constructed; four are located within the river bed, two are placed on the river banks on each side and two are outside the river bank. The bridge has been designed with strategic placement of piers to minimize obstruction in the river waterway… Once completed, the bridge will not only stand as a symbol of modern connectivity but also exemplify harmony between high-speed infrastructure and existing rail network.'
In Ahmedabad district, the Bullet Train alignment crosses multiple structures, including flyovers, bridges, railway lines, and Metro corridors. 'To maintain the mandatory vertical clearance of 5.5 meters from the topmost construction point as per IRC (Indian Roads Congress) guidelines, the piers of the Sabarmati River bridge have been designed with increased height,' NHSRCL said.
The advanced Balanced Cantilever Method has been deployed to construct the bridge across the Sabarmati river, which has a width of 360 metres. 'Balanced Cantilever Method is a specialised construction technique ideal for long span bridges over deep waters and rivers. The concept of this method is to construct a bridge without installing scaffolding systems under the bridge and complete the superstructure by sequentially joining the segments to form a span by post-tensioning and balancing the left and right from each pier using special erection equipment. This creates a continuous and stable bridge deck,' NHSRCL said.
While most river bridges on the Mumbai-Ahmedabad Bullet Train corridor typically have shorter spans of around 40 meters, the Sabarmati River bridge uses longer spans, ranging from 50 to 80 meters, to reduce the number of piers within the riverbed. 'The bridge comprises five spans of 76 meters each and two spans of 50 meters each. Each span consists of 23 segments being cast in-situ (construction at site). The casting of these segments requires meticulous precision, highly skilled workforce and dedicated team at every stage to ensure structural strength and quality… all foundation and substructure works have been successfully completed, the superstructure activities including pier head construction and segment casting are currently underway,' NHSRCL said.
To ensure the highest standards of safety during the bridge construction, a robust set of safety protocols have been put in place particularly for activities involving working at a height. 'A structured work permit system has been implemented to ensure strict accountability and discipline at site. All workers are strictly required to wear Personal Protective Equipment (PPE) including full-body harnesses at all times. To mitigate fall-related risks, catch nets have been installed below the Form Traveler/Bridge Builder structures. CCTV cameras have been installed for real-time monitoring of the construction process,' NHSRCL said.
The Sabarmati bridge is among the 21 river bridges in Gujarat. A total of 25 bridges are part of the MAHSR corridor from Ahmedabad to Mumbai.
Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

JAL insolvency: Jaiprakash Infratech to challenge bid rejection in court
JAL insolvency: Jaiprakash Infratech to challenge bid rejection in court

Business Standard

time9 hours ago

  • Business Standard

JAL insolvency: Jaiprakash Infratech to challenge bid rejection in court

Jaiprakash Infratech Ltd, the New Delhi-based real estate firm, is preparing to challenge in court the rejection of its bid to acquire Jaiprakash Associates Ltd (JAL), potentially dragging the bankrupt cement and infrastructure major's resolution into further delay. Lenders of JAL had turned down Jaiprakash Infratech's offer, citing an insufficient earnest money deposit (EMD), according to people familiar with the matter. The company had proposed a lien over fixed deposits in lieu of the ₹100 crore deposit, but the bid was rejected for not submitting the amount in the prescribed format and for delays in filing the offer. 'The lien over the fixed deposits was legally valid and submitted on time,' said a person close to the company, who asked not to be named as the discussions were private. 'We have no option but to move the court and remain in the race.' Jaiprakash Infratech, which was taken over by Mumbai-based Suraksha Group in June 2024, is currently focused on completing long-pending housing projects for customers who have waited over a decade. JAL, on the other hand, was sent for debt resolution after the company defaulted on loans worth ₹57,000 crore to Indian lenders. In March this year, the lenders transferred their outstanding dues to National Asset Reconstruction Company. The fresh legal dispute threatens to complicate the resolution process, with Gautam Adani's group emerging as the frontrunner to acquire the company after submitting an unconditional bid. Other suitors, including Dalmia Bharat, Vedanta Group, Jindal Power and PNC Infratech, have submitted offers with conditions attached. Lenders have now asked all bidders to submit revised proposals without conditions. Several of the conditional offers hinge on the fate of JAL's 1,000-hectare Sports City project in Greater Noida. In March, the Allahabad High Court upheld the cancellation of land allotment for the project by the Yamuna Expressway Industrial Development Authority. That decision is currently under appeal in the Supreme Court.

Mumbai to Ahmedabad in just 127 minutes: India's first bullet train service to begin soon, says Ashwini Vaishnaw
Mumbai to Ahmedabad in just 127 minutes: India's first bullet train service to begin soon, says Ashwini Vaishnaw

Indian Express

time9 hours ago

  • Indian Express

Mumbai to Ahmedabad in just 127 minutes: India's first bullet train service to begin soon, says Ashwini Vaishnaw

Mumbai-Ahmedabad Bullet Train Launch: India's first bullet train service on Mumbai-Ahmedabad route will commence soon. Speaking at an event in Gujarat's Bhavnagar, Railway Minister Ashwini Vaishnaw announced that the Mumbai-Ahmedabad bullet train service will begin very soon. Once operational, it will reduce travel time between the two cities to just 2 hours and 7 minutes (127 minutes), he said. 'The first bullet train from Mumbai to Ahmedabad will start very soon, and the work on the project is going on at a fast pace. When it starts running, the journey from Mumbai to Ahmedabad will take only two hours and seven minutes,' Vaishnaw said. बुलेट ट्रेन, मुंबई से अहमदाबाद वाली पहली ट्रेन, वह भी बहुत जल्दी चालू होने वाली है। तेजी से काम चल रहा है और जब यह ट्रेन चालू हो जाएगी। मुंबई से अहमदाबाद मात्र 2 घंटे 7 मिनट की जर्नी रहेगीः माननीय रेल मंत्री श्री @AshwiniVaishnaw जी — Ministry of Railways (@RailMinIndia) August 3, 2025 The Railway Minister was at Bhavnagar terminus from where he virtually flagged off three trains: the Bhavnagar Terminus–Ayodhya Cantt Express, the Rewa–Pune Express, and a new train connecting Jabalpur to Raipur. The 508-km long Mumbai-Ahmedabad High Speed Rail (MAHSR) project will have 12 stations namely – Mumbai, Thane, Virar, Boisar, Vapi, Billimora, Surat, Bharuch, Vadodara, Anand, Ahmedabad and Sabarmati. The total estimated cost of MAHSR project is Rs 1,08,000 crore (approximately). Of these, Japan International Cooperation Agency (JICA) is funding 81% of the project cost i.e. Rs. 88,000 crores. Last year, Chennai-based Integral Coach Factory (ICF) awarded a contract to design, manufacture, and commission of two high-speed trains to BEML Limited. Both the trainsets will be developed on Japanese Shinkansen technology. According to BEML, the price of each high-speed car is Rs 27.86 crore and the total contract value is Rs 866.87 crore. Recently, in a written reply to Lok Sabha, Railway Minister Ashwini Vaishnaw stated that the Gujarat portion of the corridor between Vapi and Sabarmati is planned to be completed by December, 2027. 'The entire project (Maharashtra to Sabarmati section) is expected to be completed by Dec, 2029. However, Bullet train project is a very complex and technology intensive Project,' he noted. Anish Mondal is a business journalist with over nine years of experience. He writes on diverse subjects such as Infrastructure, Railways, Roadways, Aviation, Politics, Market, Parliamentary affairs, Corporate earnings, General and International news etc. ... Read More

Lodha Developers expects to conclude one or more land deals this year, ahead of its Delhi-NCR foray: Abhishek Lodha
Lodha Developers expects to conclude one or more land deals this year, ahead of its Delhi-NCR foray: Abhishek Lodha

Hindustan Times

time10 hours ago

  • Hindustan Times

Lodha Developers expects to conclude one or more land deals this year, ahead of its Delhi-NCR foray: Abhishek Lodha

Mumbai-based listed real estate developer Lodha Developers expects to conclude one or more land deals in Delhi-NCR this fiscal, paving the way for its first project launch in the region in the next financial year, Managing Director and CEO Abhishek Lodha said during the Q1FY26 earnings call on July 28. Lodha Developers' market share is expected to be more than double by the end of the decade in MMR, Pune and Bengaluru, according to the company''s investor presentation for the Q1FY26.(Macrotech Developers) Looking to expand into the Delhi-NCR housing market, Lodha said the company aims to acquire at least one land parcel this year to develop its first residential project in the region. The foray will begin with a pilot phase, involving a limited number of projects and a moderate level of investment. Lodha Developers plans to enter the Delhi-NCR real estate market within the next year and aims to launch its first project in the region in the next financial year, the company said. "We expect to enter Delhi NCR in the next 12 months and hope to launch in fiscal 2027. The Delhi NCR is an important market for us to get into. We obviously, as we have done in Pune and Bengaluru, will only enter in a gradual manner. We will be starting off with a pilot phase with a moderate number of projects and a moderate level of investment with a view to understanding better how the market operates and how we build out the supply chain for operations as well as sales," Lodha said during a recent investors' call. "Our focus in this period is, first and foremost, on building our local operating team. We expect that we will conclude one or more land transactions either on a joint development basis or otherwise in the course of this financial year, and hope to launch in the next financial year. But obviously, at this stage, the details are limited. We will provide a more detailed update once the first land transaction is concluded," Lodha said. Also Read: DLF's Rajiv Singh is the richest real estate developer, followed by Mangalprabhat Lodha and family: Grohe-Hurun India Location strategy for Delhi-NCR Responding to a question on which micro-markets Lodha Developers has zeroed in on for launching its first project in Delhi-NCR, he said that 'I think we are looking across the Delhi NCR to make sure that locations fit with our brand's premium positioning.' "At the same time, have attractive dynamics when it comes to supply-demand and also profitability for us. So, we are looking across the board, and we will be able to provide a little bit more specific detail once the first land transaction is concluded. I think at this stage it's just a directional thing that, yes, we expect to be entering the NCR in the next 12 months," Lodha said during the call. Also Read: Lodha versus Lodha: Real estate tycoons settle trademark dispute through mediation Lodha Developers' market share is expected to be more than double by the end of the decade in MMR, Pune and Bengaluru According to the investor presentation shared with the stock exchanges as part of the Q1FY26 quarterly financial results, Lodha Developers' market share will more than double in the Mumbai Metropolitan Region, Pune, and Bengaluru real estate markets by the end of the decade. The company said in the Mumbai Metropolitan Region, its market share as of FY24 is 10%, which is likely to go up to 20% by the end of the decade, followed by 15% in Pune from its existing 5%, and 12% in Bengaluru from 2% currently, the investor's presentation revealed. Also Read: Buying a property is better than renting one: Abhishek Lodha Q1FY26 results The company's sales bookings increased 10% during the April-June period of this fiscal year to ₹4,450 crore. The company's total income increased to ₹3,624.7 crore in Q1FY26 from ₹2,918.3 crore during the same time last year. Lodha Developers has delivered 110 million sq ft of real estate and is currently developing more than 130 million sq ft under its ongoing and planned portfolio.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store