Manitoba Hydro embarks on $7-billion overhaul of two main transmission lines

Manitoba Hydro embarks on $7-billion overhaul of two main transmission lines

Manitoba Hydro has launched a historic and long overdue overhaul of its two main transmission lines that will cost at least $7 billion and require up to 15 years of electricity rate hikes, the Free Press has learned.
The HVDC (high-voltage direct current) Reliability Project involves the replacement of the converter stations and other equipment at both ends of Bipoles I and II, the two main transmission lines that each run nearly 1,000 kilometres from northern Manitoba through the Interlake to Winnipeg. The two lines carry more than 70 per cent of Hydro's total generated electricity.
WAYNE GLOWACKI / FREE PRESS FILES
Manitoba Hydro has launched a historic and long overdue overhaul of its two main transmission lines that will cost at least $7 billion.
WAYNE GLOWACKI / FREE PRESS FILES
Manitoba Hydro has launched a historic and long overdue overhaul of its two main transmission lines that will cost at least $7 billion.
Hydro has estimated the project will cost at least $7 billion, although because it is still at a very early stage, officials at the utility concede the final price tag will be higher.
A Hydro spokesman confirmed the utility has started a procurement process that will establish a precise cost to replace the converter stations and is conducting a search for contractors to oversee the work. A more accurate estimate of the total cost will not be available until 'the full scope of work' is identified, the spokesman said.
Even at $7 billion, this would be the most expensive capital project undertaken by the Crown corporation, exceeding the investments made in any single generating station. It's significantly more than the cost of Bipole III, the politically controversial transmission line that runs from the north along the west side of Lake Manitoba. Bipole III was completed in 2018 at a cost of just over $5 billion.
Hydro's 2026-28 rate application, which has been filed with the Public Utilities Board, said the project would take more than a decade to complete and based on Hydro's latest calculations, require 15 years of annual rate increases of 3.5 per cent.
Although electricity rate increases are politically unpopular, Hydro will argue before the PUB that the viability of the transmission system is at stake if the work is not done.
'This is not just about meeting new energy needs in the future,' said Ben Graham, chairman of the Hydro board of directors. 'It's about ensuring a reliable grid now so that Manitobans will have the power they need when they need it.'
MIKE DEAL / FREE PRESS FILES
Manitoba Finance Minister Adrien Sala, the minister responsible for Hydro, says the NDP government approved the HVDC project as part of its process of reviewing the utility's 2025-26 budget.
MIKE DEAL / FREE PRESS FILES
Manitoba Finance Minister Adrien Sala, the minister responsible for Hydro, says the NDP government approved the HVDC project as part of its process of reviewing the utility's 2025-26 budget.
Finance Minister Adrien Sala, the minister responsible for Hydro, said the NDP government approved the HVDC project as part of its process of reviewing the utility's 2025-26 budget. He said that despite urgings from Hydro, the previous Tory government ignored the state of the transmission line converters and deferred a formal decision about starting the HVDC project.
'We know for many years, the former government failed to make necessary investments to ensure continued reliability at Hydro, and also ensure that we would have the energy we needed to support Manitobans and our businesses,' Sala said. 'So, I think we're making sure that we keep that all important balance between preserving affordability while ensuring Manitobans have access to the energy they need to power their homes and their businesses.'
'For many years, the former government failed to make necessary investments to ensure continued reliability at Hydro.'–Finance Minister Adrien Sala
Peggy Barker, board member with the Manitoba branch of the Consumers' Association of Canada, which monitors Hydro rate applications to the PUB, said she's concerned about the size and speed of the project given Hydro's poor performance in forecasting the cost of capital projects.
'For over 10 years, the Public Utilities Board and independent experts have said that Manitoba Hydro's process for deciding on the pacing and prioritization of asset management was not mature or adequate,' the association's statement said. 'While Hydro has made modest progress in recent years, there is still an absence of a mature, standardized methodology for ranking investments based on asset risk, customer value, and cost-effectiveness.'
MARC GALLANT / FREE PRESS FILES
Manitoba is known throughout the energy world for technology that has allowed electricity to be transmitted via high-voltage direct current lines over extremely long distances.
MARC GALLANT / FREE PRESS FILES
Manitoba is known throughout the energy world for technology that has allowed electricity to be transmitted via high-voltage direct current lines over extremely long distances.
Bipole I went into operation in 1971 and underwent a major upgrade in 1993. Bipole II was fully completed in 1985. Currently, the converter stations that are essential for the transmission of power to the south are well past their life expectancy.
Given the long distances the electricity must travel, converter stations are needed to convert alternating current (AC) that comes from the generating stations to direct current (DC) for transmission to reduce the amount of electricity lost during transmission. When the electricity reaches the other end of the transmission line, it is converted back to AC.
In most instances, the converter stations are more expensive than the cost of erecting hundreds of kilometres of transmission lines.
According to Hydro, the converter equipment normally has a life span of 35 years. Hydro currently estimates the earliest it could acquire and install new converters and connectors is between 2032 and 2037. By that time, the Bipole I converters will be 44 years old and its control mechanisms will be 65 years old, while Bipole II converters and controls will be 57 years old.
Although the cost estimate and electricity rate hikes could be a source of political controversy, the need for the refurbishment project should not be a cause for much disagreement between the NDP government and opposition parties.
The distance between northern generating stations and the southern region of the province, where most of the electricity is consumed, has always been a major source of concern for Hydro and the government of the day.
MIKE DEAL / FREE PRESS FILES
Former Tory premier Brian Pallister called Bipole III the worst political scandal in the province's history and spent $1 million on an in-depth review of the project.
MIKE DEAL / FREE PRESS FILES
Former Tory premier Brian Pallister called Bipole III the worst political scandal in the province's history and spent $1 million on an in-depth review of the project.
In 1996, a huge wind storm damaged both Bipole I and II and nearly resulted in a blackout of Winnipeg. Hydro was forced to import electricity from Minnesota while both transmission lines were being repaired.
Ultimately, that event became the motivation for the construction of Bipole III. Again, the need for the project was never really questioned; the cost and management of it by the then-NDP government of Gary Doer sparked years of political conflict.
The final cost was nearly three times the initial estimate and the project was afflicted by numerous delays and mismanagement.
Former Tory premier Brian Pallister called Bipole III the worst political scandal in the province's history, and spent $1 million to have former Saskatchewan premier Brad Wall, a Tory, conduct an in-depth review. The Wall review did not reveal new details about the project.
The big question facing Hydro, and successive provincial governments of both political stripes, is why the HVDC project was delayed.
By all accounts, Hydro has been planning for decades to replace essential equipment at both ends of the transmission lines. However, documents available at the PUB and legislative committee meetings show it was not discussed in detail until about 2016. An engineering report released by Hydro in 2019 fully explored the danger of pushing the equipment too far beyond its normal life span.
The 2026-28 general rate application, now before the PUB, is the most detailed description yet of the need for, and cost of, replacing transmission converters and connectors.
Tuesdays
A weekly look at politics close to home and around the world.
Manitoba is known throughout the energy world for technology that has allowed electricity to be transmitted via high-voltage direct current lines over extremely long distances. Bipole I (895 kilometres) and II (937 kilometres) run from the northern Radisson and Henday converter stations near Gillam, down to the Dorsey converter station just northwest of Winnipeg.
Bipole III is much longer at 1,400 kilometres, starting at the Keewatinohk converter station near Gillam and ending at the Riel converter station east of Winnipeg.
However, in its most recent submission, Hydro noted that Manitoba currently operates the oldest HVDC transmission system in the world.
dan.lett@freepress.mb.ca
Dan LettColumnist
Dan Lett is a columnist for the Free Press, providing opinion and commentary on politics in Winnipeg and beyond. Born and raised in Toronto, Dan joined the Free Press in 1986. Read more about Dan.
Dan's columns are built on facts and reactions, but offer his personal views through arguments and analysis. The Free Press' editing team reviews Dan's columns before they are posted online or published in print — part of the our tradition, since 1872, of producing reliable independent journalism. Read more about Free Press's history and mandate, and learn how our newsroom operates.
Our newsroom depends on a growing audience of readers to power our journalism. If you are not a paid reader, please consider becoming a subscriber.
Our newsroom depends on its audience of readers to power our journalism. Thank you for your support.
Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

B.C. eyes drug panel changes after Charleigh Pollock controversy
B.C. eyes drug panel changes after Charleigh Pollock controversy

CTV News

time11 hours ago

  • CTV News

B.C. eyes drug panel changes after Charleigh Pollock controversy

The premier is now openly talking about overhauling the secretive drug panel which cut off medication funding for a young Vancouver Island girl with a rare condition. The story of Charleigh Pollock – a 10-year-old Langford girl with a rare brain condition – has pushed B.C. Premier David Eby to vow major changes to the government drug approval process. Pollock's case sparked public outrage after provincial funding for her medication was stopped. The NDP government then reversed its decision earlier this month. Eby says there must be changes to the Expensive Drugs for Rare Diseases committee. 'We need to make sure that it works in a way that it's the experts that are making those decisions, and that is taking place in a way that's transparent and understandable to the public,' Eby said Monday. 'It did not work that way in the Charleigh case. We had two groups of experts fighting it out. One very publicly. One a secret committee within the ministry of health, speaking only through politicians. That doesn't work.' A doctor who resigned after chairing a subcommittee on Expensive Drugs for Rare Diseases spoke with CFAX 1070 on Monday. 'I have spent my whole career working in this area and I would be willing to do anything that might actually make it better,' Dr. Sandra Sirrs said during the radio interview. 'In my opinion, however, that means that the decision making has to be taken away from the ministry of health and put in the hands of the physicians.' While Dr. Sirrs disagreed with the province's decision to step in – she did agree on the need for more transparency. 'It is my personal opinion that the reason that there has been concern about transparency about the EDRD process is because the expenses are very large, and the number of people who benefit is very small,' Sirrs said. Regardless, based on Eby's comments, it seems more transparency is likely to come. 'We'll have to find a path forward,' Eby said. 'I am supportive of the health minister's decision to not let this child get caught between a battle between two experts, and I hope that the experts who are on the committee and who have left the committee are willing to work with us to identify a structure that's going to work for them.' Ten experts have resigned from the drug panel since the government's reversal, with Sirrs claiming the decision amounted to political interference.

York Factory First Nation 'essentially stranded' after low water levels ground ferry: grand chief
York Factory First Nation 'essentially stranded' after low water levels ground ferry: grand chief

CBC

time16 hours ago

  • CBC

York Factory First Nation 'essentially stranded' after low water levels ground ferry: grand chief

Indigenous leaders in Manitoba want an all-season road for a northern Manitoba First Nation that's been "essentially stranded" after low water levels left its ferry grounded for more than two weeks. York Factory First Nation Chief Darryl Wastesicoot said his community of about 300 is located between two Manitoba Hydro dams, and that the Crown corporation controls the water levels on the lake. Unprecedented low water levels this year have left his community "basically stuck," Wastesicoot said. York Factory, about 900 kilometres north of Winnipeg, declared a state of emergency earlier this week, because the ferry has been inoperable for more than two weeks. "It's not the first year that's been like this and it continues to happen, so we are looking for solutions here with Manitoba Hydro, but we're falling on deaf ears," he said. At a news conference on Tuesday, Wastesicoot and several other First Nations chiefs and grand chiefs demanded that the federal and provincial governments fast track an all-season road for York Factory. Assembly of Manitoba Chiefs Grand Chief Kyra Wilson said the issue boils down to Manitoba Hydro's control of water levels within First Nations communities, leaving places like York Factory "essentially stranded." "What we're seeing right now is dams surrounding our First Nations communities, and they're controlling the flow through and the water levels, and it's negatively impacting our First Nations communities," she said at the news conference. However, Infrastructure Minister Lisa Naylor said ongoing drought conditions are to blame for the unusually low water levels that left York Factory's ferry inoperable. The province is watching the water levels and precipitation to determine when the ferry can resume service, she said. "In the meantime, we are working closely with York Factory First Nation and the federal government to ensure that families have access to the essential supplies and resources they need," she said in a statement to CBC News on Monday. Manitoba Hydro spokesperson Peter Chura said the low water levels that docked the ferry are not because of operations at the nearby Keeyask Generating Station. He also blamed drought, saying both the Churchill River and Lake Winnipeg basins are much drier than normal. "As a result, water levels and flows are low on lakes and rivers throughout Manitoba," he said in a statement. Chura also said there are "open lines of communication" between Manitoba Hydro and York Factory. 'Can't afford to wait' Wastesicoot said the ferry is a critical part of York Factory's survival because winter roads are "not reliable anymore." "We used to get three months out of it, but now we're lucky to get 30 days," he said. Manitoba's current wildfire season has also threatened the ferry's viability, preventing the ferry from docking a few times already this year, Wastesicoot said. "Sometimes the planes couldn't land because of the smoke," he said. "It would be devastating if we couldn't get out." Two external studies recently commissioned by York Factory found that a 60-kilometre, all-season road for the community would cost around $150 million, Wastesicoot said. York Factory would ideally like to return to its traditional lands, he said. The First Nation was forced to relocate to its current location in 1957. But such a return would be costly, with an estimated $5 billion price tag, according to Wastesicoot. "I don't think that's going to happen anytime soon." Wastesicoot has spoken with Naylor and Premier Wab Kinew about the situation, and while both promised to meet with the chief, he said York Factory can't wait for that to happen any longer. He expects the ferry to be out of commission until September at the latest. "We can't afford to wait to meet with the officials who have the power to do something about it," he said.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store