
Electric ‘superhighway' delayed in blow to Miliband's net zero plans
Eastern Green Link 1 risks missing its target completion date because of global equipment shortages. The project involves a 120-mile cable being built between Scotland and north-east England that is capable of transmitting enough power for 2m homes.
The upgrade is meant to ease grid bottlenecks and is seen as one of the most vital enablers of plans laid out by Mr Miliband, the Energy Secretary, for a 'clean' power system in 2030.
Without it, officials have warned that the cost of 'constraint' payments to wind farm owners – where turbines are paid to switch off because the grid is too congested – risk ballooning by almost £900m per year.
The project has been granted fast-track status by Ofgem, the energy regulator, and given a target delivery of Dec 31 2028 at the latest.
After that point, developers SP Energy Networks and National Grid Electricity Transmission would face fines.
However, the companies have warned that the scheme has been hit by delays and are pleading for relief from fines until at least April 2030 – suggesting there is a risk the project will be severely late.
SP Energy and National Grid blamed global shortages of key pieces of equipment, including high-voltage cables and converters, which countries around the world are racing to buy as part of the switch to green energy.
That has led to years-long wait times, with manufacturers racing to expand their capacity but struggling to keep up with demand.
The problem highlights the risk posed to Mr Miliband's clean power plans by a lack of available parts.
Kathryn Porter, an independent energy analyst, said: 'To achieve the Clean Power 2030 target we must build twice as much grid infrastructure in the next five years as we delivered in the past decade.
'But supply chain constraints make this an unachievable goal, particularly when we note that the lead time for some transformers is now four years.'
In November, the National Energy System Operator (Neso) – the quango responsible for managing the operation of Britain's power grid – highlighted Eastern Green Link 1 as one of four upgrades that would have 'the highest impact on the country's ability' to hit Mr Miliband's target.
It has warned that some 80 infrastructure upgrades must all be delivered by the end of this decade in order for Mr Miliband's plan to succeed.
At the time, the Neso said Eastern Green Link 1 was expected to be complete by 2030. However, the Government said the latest estimate was April 2029.
According to Ofgem, the project is running at least six months later than previously expected.
The regulator has said it is 'minded' to reject the application for relief from fines, arguing that SP Energy Networks and National Grid Electricity Transmission knew about global supply chain issues and that the delays are the companies' own fault.
A Department for Energy Security and Net Zero spokesman said: 'Our Clean Power Action Plan sets out how we will deliver a new era of clean electricity, with the most ambitious reforms to the country's energy system in a generation.
'As shown by the National Energy System Operator's independent report, clean power by 2030 is achievable and will deliver a more secure energy system, which could see a lower cost of electricity and lower bills.
'We support Ofgem in ensuring projects are delivered by 2030, to protect bill payers on our journey to clean home-grown power.'
The spokesman added that state-owned Great British Energy and the National Wealth Fund would invest in UK supply chains.
They also pointed to a £350m investment by Sumitomo Electric Industries in a new high-voltage cable manufacturing facility at the Port of Nigg, Highland, Scotland.
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Telegraph
2 hours ago
- Telegraph
Miliband refuses to publish details of green energy deal with China
Following the decision, the Ministry of Defence raised concerns that the Chinese could use the turbines as spy sensors – but the Treasury was said to be resisting attempts to block the deal because of a desire to encourage inward investment. In Freedom of Information disclosures, the Government revealed that while Mr Miliband had been in China from March 13 to 17, Ofgem officials stayed until March 21. The officials, including Mr Brearley, used four temporary 'burner' phones while in the country, a standard security precaution government visitors are advised to take while in China. An Ofgem spokesman said: 'We always seek to keep expenditure as low as possible to deliver the best value for money and we regularly review our business travel and expenses policy in order to minimise the number of flights Ofgem staff take.' The group's food, local transport, and accommodation costs were paid for by the Foreign Office, the British embassy in China and the UK Integrated Security Fund, they added. The Department for Energy Security and Net Zero insisted it was 'misleading' to suggest memorandums signed with other countries are made 'publicly available'. A spokesman said: 'The MoU is not about encouraging Chinese investment or involvement in the UK critical national infrastructure. 'Instead, it renews a partnership that has been in place for over ten years, and which facilitates the sharing of research and ideas to support the global clean energy transition.'


Telegraph
15 hours ago
- Telegraph
Network Rail cuts maintenance spending after net zero increases electricity costs
Network Rail has slashed its maintenance budgets after the Government's net zero targets pushed up electricity prices. Sir Andrew Haines, the chief executive of Network Rail, said rising electricity prices had forced the organisation, which looks after train tracks and stations, to 'focus more on refurbishment than renewal' in the coming years. He said the change in focus meant more money had to be spent buying power for trains instead of replacing worn-out railway infrastructure. A rail trade body chief described this as a 'consequence of Britain's broken energy policy'. Writing in Network Rail's annual financial accounts, published this week, Sir Andrew said: 'We've seen our spend on traction power rise by 40 per cent, squeezing what we have left further. 'Our Control Period 7 plans reflected that, setting out that we are expecting to focus more on refurbishment than renewals, but with a continued focus on safety and performance.' Control Period 7 is the name for Network Rail's £43.1bn operations and maintenance budget over the next four years. It covers everything from electricity for trains to buying new rails and revamping stations. It comes as the country struggles with soaring electricity prices caused by net zero policies. Ed Miliband, the energy secretary, has previously claimed bills are rising because of the price of gas used in some power stations. Others point to the number of wind and solar farms being built, with Government officials guaranteeing to developers that high prices will be paid for the electricity those sites generate. Steven Mulholland, the chief executive of the Rail Plant Association, which represents railway maintenance vehicle companies, condemned the shrinking maintenance budget. He said: 'Network Rail's decision to cut back renewals and rely on patch-up repairs is a direct consequence of Britain's broken energy policy. 'Track renewal isn't optional. It underpins safety, reliability and growth. If the Government allows short-term costs to dictate strategy, it risks dismantling the supply chain we'll need to rebuild later at far greater cost.' Freight firms fading In July, The Telegraph revealed an electric freight train company was on the brink of collapse, partly because of high power prices. Varamis Rail has suspended all operations and stopped paying its staff after finding it too difficult to compete against road freight, although it hopes to restart in mid-September. Among the high costs it has faced are those for traction electricity used to power its trains, which, according to Telegraph analysis of Network Rail figures, doubled in price between 2020 and 2024. Other rail freight companies have invested in ' bi-mode ' locomotives, which can run on either electricity from the overhead lines or an onboard diesel engine. Operators of such engines, including GB Railfreight, which is currently introducing its bi-mode Class 99 locomotives into service, can therefore run them on whichever propulsion method is the cheapest, depending on diesel and electricity prices. A Network Rail spokesman said power costs had increased by 50 per cent between the 2022-23 financial year and now. He said: 'Although utility costs represent a larger share of our spending in this control period compared with the previous five years, they still represent a relatively small portion of our overall expenditure. 'It is true to say that wider inflationary pressures are having an impact, however. While a third of our income comes from Track Access Charges, which are subject to inflation, the remainder is fixed for the control period and the increase in costs from our supply chain and across the board over the past year means there is increased pressure on funding and therefore the amount of work we can deliver.'


The Sun
19 hours ago
- The Sun
British Gas to give hard-up households up to £1,700 to pay off debts – and you don't even have to be a customer
BRITISH Gas is to give thousands of hard-up households up to £1,700 to pay off their debts - and you don't even need to be a customer. The British Gas Energy Trust's Individual and Families Fund is now accepting applications from those struggling with energy debt. 1 The scheme was set up in 2021 to help households struggling with energy debt. However, unlike other energy supplier grants, the support is available to both British Gas and non-British Gas customers. Energy customers could previously get up to £1,500 in help from the fund, but it recently increased this to £1,700 last winter to help an increasing number of households in debt. Ofgem figures show that energy debt rose to a new high of £4.15billion in the first quarter of 2025. While you don't need to be a British Gas customer to get the grant, not everyone is eligible. There are certain criteria that you need to meet to be considered for the Individual and Families Fund, including: Pre-payment meter customers must have between £50 and £1,700 of energy debt Credit customers must have between £250 and £1,700 of energy debt You live in England, Scotland, or Wales You have not received a grant from the British Gas Energy Trust within the last 2 years You must be seeking a grant to clear an outstanding debt on a current or open gas, electricity or dual fuel energy account. The account must be in your name and relate to your main residence You have received help from a money advice agency within the last six months Customers with energy debts worth more than £1,700 will not be eligible for support through the fund. British Gas Energy Trust boss Jessica Taplin said, 'We're pleased to announce the reopening of our Individuals and Families Fund to both credit and prepayment meter account holders, as we know just how important it is. 'Many households across Britain continue to struggle with high energy costs alongside other financial challenges, and this means we can once again provide vital support, regardless of which energy supplier they're with. Families can get FREE washing machines, fridges and kids' beds or £200 payments this summer – and you can apply now "This fund will help those who need it most get back on stable ground and feel confident in keeping their homes and families warm and safe.' Although British Gas Energy Trust welcomes applications from customers of all energy suppliers, customers from the following companies should seek assistance through their own hardship schemes first: Ovo Energy Next EDF Energy Scottish Power Octopus Energy Utilita If you're rejected by your own energy company's fund, you can apply for the grant at What other suppliers offer Most energy suppliers have a discretionary grant scheme to help support vulnerable customers. Grants vary by supplier, and the exact amount you'll get will depend on your own financial circumstances. These are all the other energy suppliers offering support. EDF Energy EDF's Customer Support Fund provides grants to support vulnerable customers struggling with energy debt. Grants are given to help clear debt and to help fund the provision of essential white goods, such as fridges or cookers. You can apply to the scheme at But before you can apply for funding, you need to seek independent debt advice. You will also need to provide your EDF account number, current debt balance and details of your household finances and vulnerability. Next Customers of Next can apply for cash grants to help with their energy costs. doesn't have established eligibility criteria, but the fund aims to help as many people as possible, and applications from individuals with the greatest needs will be prioritised. You must know your energy account number and provide a recent meter reading to complete your application. As part of your application, you'll also be asked to provide evidence of your circumstances, such as proof of household income or DWP benefit payments. Find out more, including how to apply, by visiting Octopus Energy Octopus Energy offers a range of support, including cash from its Octopus Energy Assist Fund. It could also include loaning a thermal imagery camera to find heat leaks in your home, which you can fix to reduce energy usage and your bill. It also conducts home energy visits to discuss how households can reduce their usage and gives out free electric blankets. Octopus is encouraging all customers to get in contact if they're struggling with their bills. Octo Assist fund is still open for applications, and customers have no deadline for applying. Find out more by visiting ScottishPower ScottishPower has handed out more than £60m in support to customers experiencing difficulties in paying their energy bills, through its Hardship Fund. You could qualify for help from the fund if you receive support from the following benefits: Income-related employment and support allowance Income-based Jobseeker's allowance Income support Housing benefit Universal Credit Tax credits Pension credit savings credit Help could also be available if you have a low household income or if special circumstances, such as illness, have impacted your earnings. To apply you'll first need to sought advice from debt charity Step Change by calling 0800 138 1111. You'll then need to apply for funding through Scottish Power 's scheme by visiting If your application is successful, the fund can wipe all or part of your energy debt. Utilita Utilita Giving is Utilita's charity partner and offers grants to vulnerable customers to help clear energy debt. The fund provides grants to wipe or reduce energy debts. However, it's only available to customers on legacy credit meter. To find out more and how to apply, visit Utility Warehouse Utility Warehouse offers financial assistance to customers struggling with their bills. Citizens Advice Plymouth operates the scheme, which also provides Utility Warehouse customers with budgeting advice and benefits assessments. .