logo
Landslide fix for 'invaluable' road nearing completion after five-year nightmare

Landslide fix for 'invaluable' road nearing completion after five-year nightmare

Landslide repairs to a key Wrexham road are nearing fulfillment, according to a council report. Having been closed for more than four-and-a-half years, remediation work on the B5605 is edging towards 'substantial completion'.
The road between Newbridge and Cefn Mawr has been closed since Storm Christoph in January 2021. Heavy downpours caused part of the road to collapse down the Gelli Wood embankment into the River Dee, forcing drivers to take lengthy diversions.
Funding challenges meant renovations didn't start until 2024. The scheme was scheduled for completion this summer but 'unforeseen circumstances' meant this was revised to 'Q3 2025'. A local councillor has said he expects the work to finish in October.
At the start of the year major shotcrete and underpinning work stabilised the upper section of the bank beneath the old road. A temporary access track was built down to the river following some minor tree felling.
The most critical part of the project was the construction of a bored piled wall beneath the road near the river. This was designed both to support the rebuilt embankment and to protect it from river scouring.
An update sent to councillors last week detailed recent work on the complex engineering project. The new reinforced concrete retaining wall has emerged over the summer and is now complete.
Some 12,000 tonnes of in-fill stone are being brought to the site to rebuild the embankment. This is being added in layers and compressed to create the required profile.
To guard against 'soft spots' in the compressed embankment, contractors Jones Bros wrote: 'Nuclear Density Testing (NDT) is being carried out and this exercise will be repeated on each layer going forward.
'Some soft spot areas identified during the compaction testing have been remediated.'
Traditional stone walls are also being built alongside the 'Fisherman Path' to soften the visual impact of the brutal concrete retaining structure.
Following the in-fill operation, the road itself will be reconstructed before the route can reopen to traffic. The final step will be to place a ready-built parapet wall along the road - this is being manufactured off site.
Alterations to street lighting are underway already, with new pillars being installed and old columns being removed.
In its latest report, Jones Bros added: 'The reinstatement of the embankment supporting the realigned highway is continuing as programmed.
'The final embankment will be subject to landscaping works and as the scheme proceeds towards substantial completion, necessary cyclic maintenance works will continue to be arranged both to the north and south of the 'slip area' in anticipation of opening the project to through traffic.'
When the road collapsed in January 2021, it saw some journeys extended by up to 15 miles, causing huge frustration for residents and local businesses.
Drivers have been unable to use the road as a diversion route when the A483 viaducts are closed by bad weather or traffic incidents. On occasions this has caused gridlock in Llangollen, the alternative diversion route further along the Dee Valley.
In its early stages the project was blocked by the Welsh Government because it would 'only benefit the highway', so falling outside the criteria for storm damage funding to reduce residential flooding.
The breakthrough came in May 2022 after Wrexham Council submitted a business case following complex geo-technical surveys.
The Welsh Government awarded the full £2.8m funding, with officials accepting the road's importance as both a local link and a diversion route for the A483 trunk road.
Cardiff subsequently awarded another £2.6m, bringing the scheme's final cost to almost £5.6m. Sign up for the North Wales Live newsletter sent twice daily to your inbox
Last year Ken Skates, cabinet member for transport and North Wales, said the restored road would be 'invaluable for everybody'.
Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Landslide fix for 'invaluable' road nearing completion after five-year nightmare
Landslide fix for 'invaluable' road nearing completion after five-year nightmare

Wales Online

time11-08-2025

  • Wales Online

Landslide fix for 'invaluable' road nearing completion after five-year nightmare

Our community members are treated to special offers, promotions and adverts from us and our partners. You can check out at any time. More info Landslide repairs to a key Wrexham road are nearing fulfillment, according to a council report. Having been closed for more than four-and-a-half years, remediation work on the B5605 is edging towards 'substantial completion'. The road between Newbridge and Cefn Mawr has been closed since Storm Christoph in January 2021. Heavy downpours caused part of the road to collapse down the Gelli Wood embankment into the River Dee, forcing drivers to take lengthy diversions. Funding challenges meant renovations didn't start until 2024. The scheme was scheduled for completion this summer but 'unforeseen circumstances' meant this was revised to 'Q3 2025'. A local councillor has said he expects the work to finish in October. At the start of the year major shotcrete and underpinning work stabilised the upper section of the bank beneath the old road. A temporary access track was built down to the river following some minor tree felling. The most critical part of the project was the construction of a bored piled wall beneath the road near the river. This was designed both to support the rebuilt embankment and to protect it from river scouring. An update sent to councillors last week detailed recent work on the complex engineering project. The new reinforced concrete retaining wall has emerged over the summer and is now complete. Some 12,000 tonnes of in-fill stone are being brought to the site to rebuild the embankment. This is being added in layers and compressed to create the required profile. Sign up now for the latest news on the North Wales Live Whatsapp community (Image: Jones Bros/Wrexham Council) To guard against 'soft spots' in the compressed embankment, contractors Jones Bros wrote: 'Nuclear Density Testing (NDT) is being carried out and this exercise will be repeated on each layer going forward. 'Some soft spot areas identified during the compaction testing have been remediated.' Traditional stone walls are also being built alongside the 'Fisherman Path' to soften the visual impact of the brutal concrete retaining structure. Following the in-fill operation, the road itself will be reconstructed before the route can reopen to traffic. The final step will be to place a ready-built parapet wall along the road - this is being manufactured off site. Alterations to street lighting are underway already, with new pillars being installed and old columns being removed. (Image: Jones Bros/Wrexham Council) In its latest report, Jones Bros added: 'The reinstatement of the embankment supporting the realigned highway is continuing as programmed. 'The final embankment will be subject to landscaping works and as the scheme proceeds towards substantial completion, necessary cyclic maintenance works will continue to be arranged both to the north and south of the 'slip area' in anticipation of opening the project to through traffic.' When the road collapsed in January 2021, it saw some journeys extended by up to 15 miles, causing huge frustration for residents and local businesses. Drivers have been unable to use the road as a diversion route when the A483 viaducts are closed by bad weather or traffic incidents. On occasions this has caused gridlock in Llangollen, the alternative diversion route further along the Dee Valley. (Image: Wrexham Council) In its early stages the project was blocked by the Welsh Government because it would 'only benefit the highway', so falling outside the criteria for storm damage funding to reduce residential flooding. The breakthrough came in May 2022 after Wrexham Council submitted a business case following complex geo-technical surveys. The Welsh Government awarded the full £2.8m funding, with officials accepting the road's importance as both a local link and a diversion route for the A483 trunk road. Cardiff subsequently awarded another £2.6m, bringing the scheme's final cost to almost £5.6m. Sign up for the North Wales Live newsletter sent twice daily to your inbox Last year Ken Skates, cabinet member for transport and North Wales, said the restored road would be 'invaluable for everybody'. Find out what's happening on the roads near you

Landslide fix for 'invaluable' road nearing completion after five-year nightmare
Landslide fix for 'invaluable' road nearing completion after five-year nightmare

North Wales Live

time11-08-2025

  • North Wales Live

Landslide fix for 'invaluable' road nearing completion after five-year nightmare

Landslide repairs to a key Wrexham road are nearing fulfillment, according to a council report. Having been closed for more than four-and-a-half years, remediation work on the B5605 is edging towards 'substantial completion'. The road between Newbridge and Cefn Mawr has been closed since Storm Christoph in January 2021. Heavy downpours caused part of the road to collapse down the Gelli Wood embankment into the River Dee, forcing drivers to take lengthy diversions. Funding challenges meant renovations didn't start until 2024. The scheme was scheduled for completion this summer but 'unforeseen circumstances' meant this was revised to 'Q3 2025'. A local councillor has said he expects the work to finish in October. At the start of the year major shotcrete and underpinning work stabilised the upper section of the bank beneath the old road. A temporary access track was built down to the river following some minor tree felling. The most critical part of the project was the construction of a bored piled wall beneath the road near the river. This was designed both to support the rebuilt embankment and to protect it from river scouring. An update sent to councillors last week detailed recent work on the complex engineering project. The new reinforced concrete retaining wall has emerged over the summer and is now complete. Some 12,000 tonnes of in-fill stone are being brought to the site to rebuild the embankment. This is being added in layers and compressed to create the required profile. To guard against 'soft spots' in the compressed embankment, contractors Jones Bros wrote: 'Nuclear Density Testing (NDT) is being carried out and this exercise will be repeated on each layer going forward. 'Some soft spot areas identified during the compaction testing have been remediated.' Traditional stone walls are also being built alongside the 'Fisherman Path' to soften the visual impact of the brutal concrete retaining structure. Following the in-fill operation, the road itself will be reconstructed before the route can reopen to traffic. The final step will be to place a ready-built parapet wall along the road - this is being manufactured off site. Alterations to street lighting are underway already, with new pillars being installed and old columns being removed. In its latest report, Jones Bros added: 'The reinstatement of the embankment supporting the realigned highway is continuing as programmed. 'The final embankment will be subject to landscaping works and as the scheme proceeds towards substantial completion, necessary cyclic maintenance works will continue to be arranged both to the north and south of the 'slip area' in anticipation of opening the project to through traffic.' When the road collapsed in January 2021, it saw some journeys extended by up to 15 miles, causing huge frustration for residents and local businesses. Drivers have been unable to use the road as a diversion route when the A483 viaducts are closed by bad weather or traffic incidents. On occasions this has caused gridlock in Llangollen, the alternative diversion route further along the Dee Valley. In its early stages the project was blocked by the Welsh Government because it would 'only benefit the highway', so falling outside the criteria for storm damage funding to reduce residential flooding. The breakthrough came in May 2022 after Wrexham Council submitted a business case following complex geo-technical surveys. The Welsh Government awarded the full £2.8m funding, with officials accepting the road's importance as both a local link and a diversion route for the A483 trunk road. Cardiff subsequently awarded another £2.6m, bringing the scheme's final cost to almost £5.6m. Sign up for the North Wales Live newsletter sent twice daily to your inbox Last year Ken Skates, cabinet member for transport and North Wales, said the restored road would be 'invaluable for everybody'.

Newbridge Road contractors issue update on repairs
Newbridge Road contractors issue update on repairs

Leader Live

time08-05-2025

  • Leader Live

Newbridge Road contractors issue update on repairs

The B5605 road was subject to a landslip in 2021 during Storm Christoph, and has remained closed ever since, with January 25, 2025 marking the fourth anniversary of the closure. Its closure has proven a huge frustration for residents, and caused traffic "chaos" in Llangollen and surrounding areas when the A483 viaducts are closed during inclement weather. Earlier this year, Clwyd South MS Ken Skates published an update from Wrexham Council which detailed why work had been paused on site amid necessary permits and consents. Newbridge Road (Image: Newsquest) The local authority then issued a further update stating that there was set to be a large presence at the site and that the road will be open to traffic from spring/summer. Local councillor Terry Evans said that work was scheduled to be completed in May, however, an exact completion date was never confirmed. Towards the end of April, Jones Bros issued two updates on their Facebook page saying they were making "steady progress". MORE NEWS: A spokesperson for Jones Bros Contractors said: "We are making steady progress with installing the piled foundation wall at Newbridge. "The piles are 17m long each and will form the lower concrete wall that will eventually retain the new constructed slope and allow the road at the top to be reinstated. The walls scheduled for Newbridge Road. (Image: Jones Bros) "Thank you to all the local residents for their patience and understanding as we push on to complete this project. "The upper wall that will run along the footpath is currently being precast off site by our subcontractor in Ruthin and will be delivered to site in the coming months. Installation of the wall will commence once the fill material to the slope has been placed. We have sourced local materials for the cladding to match the existing aesthetics of the area." Wrexham Council were asked whether the repairs would be completed this month, they stated a further update would be published in the coming weeks.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store