PD in a quandary over less RLNG off-take by power plants
'SNGPL is continuously reporting reduced RLNG consumption by the power sector against its committed demand of 600 MMCFD for July 2025,' said Deputy Director (Tech Gas) Salahuddin Khan.
M/s SNGPL in a letter of July 15, 2025 has reiterated that consumption remained 327 MMFCD on July 16, 2025, with a monthly average of 501-MMFCD, leading to surplus gas accumulation that has pushed system pack beyond critical levels.
Short on commitment with SNGPL: Power sector uses 28pc less RLNG
SNGPL further highlighted that power consumption on July 17, 2025 was recorded at 300 MMCFD, leading to continued gas accumulation in the system, which is unsustainable.
'If RLNG off-take is not immediately increased and maintained as per demand, the resulting high pressures may disrupt re-gasification at terminals, risking cargo discharge delays and potential financial losses in the form of demurrages and take-or-pay applicability.
Alternatively, SNGPL shall be constrained to further curtail supplies from local gas fields,' said Directorate General (Gas) Petroleum Division.
According to sources, Power Division has been requested to advise the concerned quarters to increase RLNG off-take as per demand for the month of July 2025 with re-coupment of previously unconsumed volumes to ensure smooth operation of the SNGPL system and to avoid any untoward situation in the national interest.
On July 10, 2025, responding to the comments of Minister for Petroleum and Natural Resources Ali Pervaiz Malik on underutilisation of RLNG by the IPPs, Minister for Power, Sardar Awais Ahmad Khan Leghari staunchly defended the Economic Merit Order (EMO), declaring that any attempt to alter it would be a 'grave sin' (Gunnah Kabeera).
He urged the Petroleum Division to review Liquefied Natural Gas (LNG) contracts—if necessary—just as the Power Division had done with Independent Power Producers.
'Ali Pervaiz Malik is a close friend, and his concerns are valid if the contracts are flawed,' Leghari said. 'Power plants operate under the EMO, which prioritises electricity generation from the cheapest sources. If RLNG plants don't qualify under EMO, they simply can't be operated,' he further explained.
National Electric Power Regulatory Authority (Nepra) has been sharing violations of EMO by the System Operator during the public hearings on FCAs, on the basis of which billions of rupees of NGC (former NTDC) were withheld. However, this exercise has now almost been stopped without any reason.
Nepra has directed that the System Operator and NGC must present a comprehensive update that includes covering outages of economic power plants, the resulting financial impact, and reliance on out-of-merit generation. The update should also include the status of identified system constraint, progress made, revised completion timelines and associated financial implications.
At a recent meeting on gas issues, the representative of Power Division commented that challenges need to be met and disruptions need to be looked into. The Chair responded that the tactical issues would be discussed later and, presently, the focus needs to be on sustainability of the gas sector and how LNG over supply/ less off-take is affecting it.
Secretary Petroleum framed the key issues to be addressed by the Committee, namely rationalisation of gas tariffs (for both indigenous and imported gas), synchronisation of LNG demand with the power sector along with resolution of circular debt within the gas sector.
Copyright Business Recorder, 2025
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Business Recorder
a day ago
- Business Recorder
Rs431bn owed to Chinese power projects: PD and SBP at odds over repatriation?
ISLAMABAD: The Power Division and the State Bank of Pakistan (SBP) are reportedly at odds over the repatriation of Rs 431 billion owed to Chinese power sector projects—an amount meant to be repatriated through commercial banks, well-informed sources told Business Recorder. This issue came to light during a meeting of the Sub-Committee on Reforms, chaired by Minister for Petroleum and Natural Resources Ali Pervaiz Malik. The meeting was also attended by Special Assistant to the Prime Minister on Industries and Production, Haroon Akhtar. Chinese coal-fired power projects, such as Port Qasim and Sahiwal, have been persistently writing to the Ministry of Finance, seeking clearance of these outstanding payments. Chinese IPPs face Rs500bn in unpaid dues The matter surfaced during discussions on proposed measures to mitigate currency risks for foreign investors in Pakistan. The SBP stated that no loan repayments—whether principal or interest—nor profit repatriation payments are pending with the SBP or any commercial bank. The central bank acknowledged that only a profit payment of $26.5 million is pending with one commercial bank, which it expects will be cleared soon. SBP further clarified that no verbal or written directives had been issued to commercial banks to delay LC payments or other financial transactions. However, the Power Division reported that while the power payment cycle typically spans 90 days, Rs 431 billion in payments remain stuck with commercial banks—primarily for non-energy components. A detailed ageing report presented during the meeting indicated that while no energy payments have been overdue for more than three months, non-energy payments have been pending for years. The depreciation of the rupee has further reduced the dollar value of these payments. No representatives from NEPRA attended the meeting, and no information was shared regarding eight pending cases. The SBP reiterated that no Chinese company payments are currently pending for profit repatriation or debt servicing, and it has issued no instructions—verbal or written—to banks in this context. However, the SBP was asked to provide a written report detailing all payments to Chinese companies pending with commercial banks, including ageing data. The Power Division maintained its stance that Rs 431 billion in payments are pending with various banks and remain un-repatriated by the concerned Chinese companies. NEPRA was directed to provide an update on the potential claw back of the eight cases under adjudication. No conclusive way forward was proposed during the session. The committee noted a divergence in views between the SBP and the Power Division, making it difficult to issue a clear recommendation due to the lack of clarity. The chair emphasized several core principles as essential for attracting investment: (i) adherence to due process of law ;(ii) sanctity and enforceability of contracts;(iii) provision of adequate security measures ;(iv) a competitive and transparent process, and (v) policy consistency and predictability in the medium term. Regarding the development of physical infrastructure and utility services at Special Economic Zones (SEZs) and Export Processing Zones (EPZs), the Board of Investment (BoI) informed the sub-committee that six SEZs will be marketed to Chinese investors. BoI said that 40 companies have been identified to showcase as success stories, which will be narrowed down to 5–10 for targeted promotion. The committee supported promoting six SEZs—AIIC, BQIP, KIP, Rashakai, Dhabeji, and PSM—to Chinese investors. Of these, 3,000 acres are available for development at PSM and 700 acres at AIIC, with additional land parcels available at other developed SEZs, all equipped with basic amenities. The committee recommended establishing Service Level Agreements (SLAs) to define timelines. On easing regulatory hurdles and creating a one-stop-shop mechanism integrating federal and provincial authorities, the BoI presented updates on its Business Facilitation Center (BFC) initiative. BoI highlighted the 'regulatory guillotine' efforts and modernization of the Companies Act. The Cabinet Committee on Regulatory Reforms (CCoRR) has been notified, and BoI claims that two reform packages will reduce the cost of doing business by Rs 250 billion. Three additional reform packages are in the pipeline for CCoRR approval. BoI also shared its role in integrating 20 departments with SECP, harmonizing food standards across federal and provincial jurisdictions, and reducing DRAP's medical device registration timeline from two years to 45 days. The committee recommended that BoI implement a hub-and-spoke model for BFCs linked to regional offices in the six priority SEZs. SLAs will also be developed for these centers to provide transparency and predictability for investors. On reducing port clearance times and enhancing cold chain logistics, the Secretary of the Ministry of Maritime Affairs (MoMA), along with the Chairman of Port Qasim Authority (PQA) and the General Manager (Operations) of Karachi Port Trust (KPT), briefed the committee. They reported that recent reforms have reduced consignment clearance time by 24–48 hours. However, no precise data was available on reefer (refrigerated container) occupancy or costs. It was also noted that 35–40% of consignments are routed through yellow or red channels, and various departments at ports impact both import and export processes. The chair inquired whether consignments of vetted and established investors could be moved to the green channel. The committee recommended developing a comprehensive port governance model that ensures one-window operations and standard procedures for cold chain storage, aligned with international best practices. SLAs should also be signed with investors to guarantee faster clearance of their consignments. Pre-clearance mechanisms and a grievance redressal help desk for reputable importers were also advised. Lastly, the chair took serious notice of the long-vacant post of Chairman KPT and directed the Secretary of MoMA to resolve the matter urgently. A 'look-after' charge must also be assigned without delay. Copyright Business Recorder, 2025


Business Recorder
a day ago
- Business Recorder
Circular debt: banks to the rescue
Another year, another circular debt headline. But this time, something different has happened. For the first time in years, Pakistan's power sector has seen a significant resolution of circular debt stock, even if the flow remains a looming threat. Recent Power Division data shows circular debt at Rs 2.396 trillion as of March 2025, a marginal increase since July last year, and Rs 398 billion lower than March 2024. This is no small feat for a system accustomed to perpetual bleeding. Credit where it is due: the government has taken tough steps to control leakages, enforce cash flow discipline, and ring-fence funds to repay sector debt. The Finance Ministry's decision to redirect the Rs 3.23/kWh Debt Service Surcharge (DSS) solely towards debt reduction, rather than letting it disappear into the general pool, reflects fiscal prudence. Zafar Masud, Chairman of the Pakistan Banks Association (PBA), recently highlighted that this time, reforms go beyond temporary bailouts. There is an emerging focus on plugging systemic leakages, enforcing timely payments across the supply chain, and rethinking subsidy structures to reach the vulnerable without distorting the entire revenue cycle. Enhanced governance in DISCOs and technology-led oversight using digital monitoring tools are being rolled out to reduce theft and line losses, chronic ailments that have plagued the sector for decades. However, let's be clear: this is not the end, only a breather. NEPRA warns that average utilization of our 45,888 MW installed capacity remains just 34 percent, and even peak utilization is a mere 56 percent. Consumers continue to pay for idle capacity while distribution companies remain plagued by infrastructure decay, theft, inflated billing, and dismal recoveries. Without addressing these legacy issues, including both infrastructure upgrades and efficient collections, we will soon find ourselves back at square one. What makes this circular debt resolution truly historic is its scale and execution. It involved Rs 683 billion as the largest-ever restructuring of government debt sitting on bank balance sheets, combined with Rs 612 billion as the largest fresh syndicated financing ever raised independently. Collectively, this has become the largest banking transaction in Pakistan's history, by leaps and bounds, nearly 4.5 times bigger than the previous largest transaction. This was not only the largest, but perhaps the quickest execution ever of such a complex, multi-stakeholder financial transaction. The banking industry stepped up, taking a larger view of economic revival, knowing that healthier power sector cash flows will reduce financial risks and unlock growth opportunities for banks themselves. Banks agreed to a 150-basis-point reduction in their rate, bringing the new facility to KIBOR minus 90 bps. If rates fall, repayments will accelerate, potentially clearing this debt within four to six years. This frees up bank balance sheets, releases sovereign guarantee headroom for priority sector financing, and revives liquidity within the power sector itself. Power companies now have the room to invest in upgrades, efficiency, and financial discipline, while banks can redeploy freed capital into productive lending for SMEs, agriculture, green energy, and industrial revival. This is the kind of systemic fix that supports economic growth directly and indirectly. To bring all partners together, the PBA played a central and strategic role, building consensus, aligning stakeholder interests, and ensuring this was not just a transaction but a transformative milestone. The government's role has also been critical in enforcing discipline, but it is the collaborative spirit between the government, banks, and regulators that has created this breather. For the first time in years, there is visible alignment to move from crisis management to long-term planning. But let us be clear-eyed: the real battle is far from over. While the stock has been resolved at this point in time, the flow must stop and remain stopped going into the future. If we lose momentum, if governance reforms stall, if privatization of DISCOs remains shelved, if distribution efficiency improvements and collections falter, we will end up back where we started. Circular debt is not a disease in itself; it is a symptom of a broken system. Today, we have bought time. This is a positive step in a journey that must continue with unrelenting focus. The power sector crisis was not created overnight, nor will it be resolved overnight. But for the first time in a long while, there is a sense of shared responsibility, decisive action, and cautious hope. Let us not lose the momentum. The real work has just commenced. (The writer is advisor — Pakistan Banks Association) Copyright Business Recorder, 2025


Business Recorder
a day ago
- Business Recorder
Discos' T&D losses down Rs11bn in FY25
ISLAMABAD: Power Distribution Companies (Discos) made Transmission and Distribution (T&D) losses of Rs 265 billion during 2024-25, against Rs 276 billion in FY 2023-24, showing a reduction of Rs 11 billion. According to official statistics, Islamabad Electric Supply Company (IESCO) recorded losses of Rs 8.6 percent, financial cost of which was Rs 5 billion, Lahore Electric Supply Company (LESCO) 13.7 percent ( Rs 35 billion), Gujranwala Electric Power Company (GEPCO) 10.6 percent Rs 5 billion), Faisalabad Electric Supply Company 9 percent (Rs 3 billion, Multan Electric Power Company (MEPCO) 13.8 percent (Rs 14 billion), Peshawar Electric Supply Company (PESCO) 37.1 percent ( Rs 87 billion, Hyderabad Electric Supply Company (HESCO), 27.9 percent (Rs 27 billion, Quetta Electric Supply Company (QESCO), 38.4 percent,( Rs 52 billion), Sukkur Electric Supply Company (SEPCO) 39.2 percent (Rs 36 billion) and Tribal Areas Electric Supply Company (TESCO) 8.3 percent (Rs 0 billion). Power Division sources told Business Recorder that Discos average losses which stood at 18.3 percent during FY 2023-24 have decreased to 17.6 percent during FY 2024-25. The statistics further claim that Discos under recoveries recorded at Rs 132 billion during FY 2024-25 as compared to Rs 315 billion in FY 2023-24. Discos recoveries were 92.4 per cent in FY 2023-24 which have increased to 96.6 per cent in 2024-25. Discos' sell off: 'Turkish model' under consideration Prime Minister Shehbaz Sharif has given appreciation certificate to Power Minister and Power Secretary for outstanding performance during FY 2024-25, the figures of recovery and losses have been challenged by the National Electric Power Regulatory Authority (NEPRA). The power sector Regulator has directed its technical team to verify the claims of figures of losses and recovery of Discos, which it believes are doubtful. Another issue, which has also been brought to the notice of the Prime Minister is that Power Division is continuously failing to clear payments to the power plants including Chinese projects established under the CPEC framework. In addition, financial burden of billions of rupees has been shifted to Pakistan State Oil (PSO) incurred due to non-consumption of RLNG being imported from Qatar for the power sector. Copyright Business Recorder, 2025