logo
Meet decides to fast-track Thammanam-Pullepady Road work

Meet decides to fast-track Thammanam-Pullepady Road work

Time of India01-07-2025
Kochi: A joint meeting convened by mayor M Anilkumar and district collector NSK Umesh on Tuesday decided to expedite work on Thammanam-Pullepady Road. As part of it, the meeting decided to complete a social impact assessment (SIA) study at the earliest.
Officials were directed to complete the land acquisition swiftly to enable beginning of construction activities by year end. The 4(1) notification for the Thammanam-Pullepady Road was issued on April 10. Revenue department officials said that the land acquired would be handed over to Kerala Road Fund Board (KRFB) once the procedures were completed.
Data collection for social impact study has already begun. After completing social impact study, the 11(1) notification will be issued. Before the issuance of the 19(1) notification, the mayor requested the removal of electric poles and other obstacles from the acquired land to begin temporary road metalling.
Once the compensation is provided, land will be acquired from all landowners. KIFB has been instructed to prepare an estimate for removing obstacles, including potholes, from the stretch.
Get the latest lifestyle updates on Times of India, along with
Doctor's Day 2025
,
messages
and quotes!
Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Brahmapuram biomining: Corporation to extend contract till September 30
Brahmapuram biomining: Corporation to extend contract till September 30

New Indian Express

timea day ago

  • New Indian Express

Brahmapuram biomining: Corporation to extend contract till September 30

KOCHI: Kochi corporation has decided to extend its contract with Bhumi Green Energy, the Pune-based company entrusted with carrying out biomining at the Brahmapuram waste dumping yard, till September 30. The council meeting held on Wednesday made the decision as the work was not completed within the stipulated time of March 2025. UDF councillors said the contract should not be extended as the company failed to meet the deadline. 'We paid the company Rs 1,690 per tonne on the agreement that biomining would be completed in 16 months. Now, as they have sought an extension, we should at least reduce the cost per tonne,' said Antony Kureethara, leader of the Opposition. Opposition councillors also alleged lapses in carrying out the work. Bhumi Green Energy, which specialises in solid waste management, had approached Kochi corporation for an extension, saying the work was delayed because of heavy rain. Mayor M Anilkumar, responding to the allegations, said it was a challenging task to remove waste from the dumping yard, and yet, around 90% of the work has been completed. 'We have to pay the company around `45 crore for the work carried out in recent months. In such a scenario, how can we terminate the contract? Now, only 10% biomining is left. So, it is better to extend the contract till September 30,' the mayor said. When the agreement was signed in October 2023 after a major fire at Brahmapuram, the cost of treating seven lakh tonnes of waste was estimated at Rs 118 crore. However, a survey carried out by NIT Calicut found that 8.4 tonnes of waste had accumulated at the site. Meanwhile, Opposition councillors protested the decision to extend the contract. 'The officials aren't properly auditing the work carried out. Looting is taking place. Not completing the work on time is a violation of the agreement. The mayor should seek a detailed report from the officials on the work carried out,' said Antony Painuthura, a UDF councillor. The mayor, however, expressed confidence that there is no corruption involved. 'I have directed the officials not to be involved in such malpractices. Kerala High Court was also satisfied with the work,' he said. Brahmapuram biomining

Company seeks extension for biomining of legacy waste in Brahmapuram
Company seeks extension for biomining of legacy waste in Brahmapuram

Time of India

time4 days ago

  • Time of India

Company seeks extension for biomining of legacy waste in Brahmapuram

Kochi: The contracting company has requested an extension for completing biomining of waste piled up in Brahmapuram. Bhumi Green Energy Corporation approached Kochi corporation, stating that financial difficulties due to delayed bill payments and impact of heavy rains prevented completion of biomining within the scheduled time. The contract for biomining in Brahmapuram was signed between corporation and Pune-based Bhumi Green Energy on Nov 4, 2023, with a duration of 16 months, which ended in March 2025. Although the company continues biomining, corporation has not extended the contract duration. In this context, the company submitted a letter to corporation requesting an extension. The council meeting to be held on Wednesday will decide on the matter. Initially, cost for processing and removing 7,00,000 tonnes of waste was estimated at Rs 118 crore. However, with the increased waste volume in NIT Calicut (NITC) survey, the cost rose to Rs 142 crore. Mayor M Anilkumar said around 90% of biomining was completed. Corporation states that the 16-month duration was determined based on a survey report estimating 7,00,000 tonnes of legacy waste in Brahmapuram. However, NITC survey found 10.54 cubic metres (8,44,000 tonnes) of waste. Biomining contract was awarded at a rate of Rs 1,690 per tonne.

SN Junction–Poothotta road widening revived after decade-long delay
SN Junction–Poothotta road widening revived after decade-long delay

New Indian Express

time23-07-2025

  • New Indian Express

SN Junction–Poothotta road widening revived after decade-long delay

KOCHI: A key project aimed at easing the traffic congestion in Tripunithura and its surrounding areas, which has languished in the backburner for nearly a decade, is finally set to become a reality. The Rs 672-crore project to widen the 13-km SN Junction-Poothotta stretch into a four-lane road has been revived with the Kerala Road Fund Board (KRFB) completing the crucial realignment process, paving the way for immediate land acquisition. 'Land acquisition for the SN Jn-Poothotta road widening will begin soon,' MLA K Babu told TNIE. First included in the state budget in 2017, the delay in implementing the project has significantly worsened traffic woes in Tripunithura, a burgeoning residential hub on Kochi's outskirts. Residents have long grappled with slow-moving traffic, particularly along this vital corridor that connects key residential areas to the city. KRFB's recent completion of the realignment process marks a major breakthrough. The step not only finalises land requirements but also incorporates vital enhancements to the original plan. As part of the renewed project, nine key junctions -- including Kizhakkekotta, Nadakkavu, Kannankulangara, Puthenkavu and Udayamperoor -- along the stretch will see development like the construction of bell-mouths, promising smoother traffic flow and reduced bottlenecks. Additionally, 12 new bus bays will be constructed, providing designated stops that prevent buses from obstructing traffic, thereby improving overall road safety and public transport efficiency. 'We've submitted the revised alignment and also the request for 11 (1) notification, the crucial step for land acquisition, to the district collector. After this, the 19 (1) notification will have to be issued when the compensation amount for land owners will be determined,' a senior KRFB official said. Post realignment, the total land to be acquired for the project has risen to 13.12 hectares from the earlier 12.62 hectares. Acquisition often represents the most challenging and time-consuming aspect of infrastructure projects in densely populated areas. The official, however, promised quick implementation.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store