Why has the Axiom-4 mission been delayed?

Why has the Axiom-4 mission been delayed?

The Hindua day ago

The story so far: On June 10, Axiom Space announced that the launch of its Axiom-4 mission to the International Space Station (ISS) would be postponed indefinitely. The mission crew included India's astronaut-designate Shubhanshu Shukla, who — if the rocket had lifted off as planned — would have become the first Indian in earth orbit after 40 years and the first Indian onboard the ISS.
What is the Axiom-4 mission?
The Axiom-4 mission is the fourth mission planned by US-based spaceflight company Axiom Space to the ISS. It consists of a crew of four people — Peggy Whitson, Shubhanshu Shukla, Sławosz Uznański-Wiśniewski, and Tobir Kapu — plus cargo.
To facilitate the mission, NASA had contracted Axiom, which in turn had contracted the Falcon 9 rocket and the Dragon crew capsule for the mission from SpaceX. The mission is commercial in nature and isn't part of the regular resupply missions NASA undertakes to the ISS.
Following an announcement to strengthen India-US ties in 2023, the Indian Space Research Organisation (ISRO) spent more than Rs 500 crore for Mr. Shukla to fly on the mission. Mr. Shukla is one of the four astronaut-designates for ISRO's forthcoming Gaganyaan human spaceflight mission. His compatriot Prasanth Nair is part of the Axiom-4 backup crew.
Why was the launch called off?
Ahead of Thursday's flight, SpaceX had tested one of the rocket's engines as a matter of procedure and discovered it was leaking liquid oxygen (LOX). LOX is a cryogenic fuel, meaning it needs to be stored at an extremely low temperature. If LOX is exposed to warmer conditions, the oxygen will turn into gas and not be usable as fuel (since it's very difficult to pump gases).
Falcon 9 engines combust a mix of rocket-grade kerosene and LOX to generate thrust, meaning a LOX leak is a serious issue. The Axiom-4 mission had first been scheduled for liftoff on May 29 but had to be postponed to June 8, June 10, and June 11. There was a back-up launch window on June 12. The delays were a result of a combination of unfavourable conditions related to the weather and the launch vehicle.
The crew thus continues its wait.
Why has no new date been announced?
Since a LOX leak is a serious issue, SpaceX needs to find the precise source of the leak and why the underlying component(s) failed. How much time this will take is unclear. There are also particular launch 'windows' (specific moments in time) when a launch can deliver the crew to the ISS with minimal fuel and energy use, including the amount of time the crew capsule will be exposed to sunlight and generate solar power without overheating.
But because the ISS is so close to the earth, launch windows appear more frequently than those for the moon or Mars. NASA has already indicated there are more opportunities through June and July.
Other factors that affect the suitability of a launch window include time on the launch pad for liftoff and access to free docking ports on the ISS. The US's NASA, Russia's Roscosmos, and (less often) some other space agencies also send missions to the ISS and need to plan when and for how long their capsules are docked.
How hard is it to fix a LOX leak?
When it leaks, LOX flashes to an invisible vapour almost instantly and can be blown away by winds or fans nearby. Detecting it often entails time-consuming, labour-intensive work.
Many joints in the components associated with storing and pumping LOX are insulated with foam or are located in nooks, meaning many regular leak-detecting methods can't physically reach them. Materials contract at cryogenic temperatures (around 90 K), so a hole may appear closed at ambient temperature but open at cryogenic temperatures. So once a hole has been fixed, engineers may need to repeat tests at both warm and cold conditions or test with liquid nitrogen to mimic operating conditions. Testing with LOX itself can be hazardous.
Fortunately experts have been working with cryogenic engines for long enough to know which tools to use and which processes to follow once the leak has been identified. They include visual inspection, bubble tests, helium signature tests, flow-meter tests, ultrasonic microphones, and thermal imaging.

Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Working closely with Nasa to address Ax-4 delay, says Isro chairman
Working closely with Nasa to address Ax-4 delay, says Isro chairman

Business Standard

time20 minutes ago

  • Business Standard

Working closely with Nasa to address Ax-4 delay, says Isro chairman

Indian Space Research Organisation (Isro) is working closely with Axiom Space, Nasa, SpaceX as they responsibly address the ISS Zvezda module observation causing the Ax-4 delay. V Narayanan, the Secretary DOS/ Chairman Isro and Chairman Space Commission said that safety and mission integrity were their priorities. In a post on X, Isro stated, "Isro is working closely with Axiom Space, Nasa, SpaceX as they responsibly address the ISS Zvezda module observation causing the Ax-4 delay. Safety and mission integrity remain our top priorities." On June 11, SpaceX announced the postponement of the Falcon 9 launch of the Ax-4 mission to the International Space Station (ISS), citing the need for additional time to repair a liquid oxygen (LOx) leak. "Standing down from tomorrow's Falcon 9 launch of Ax-4 to the @Space_Station to allow additional time for SpaceX teams to repair the LOx leak identified during post static fire booster inspections. Once complete - and pending Range availability - we will share a new launch date," the company said in a post on X. Following the announcement, the Indian Space Research Organisation (Isro) also confirmed the delay of the Axiom-4 mission, which was scheduled for launch on June 11, 2025, and was set to carry the first Indian Gaganyatri to the ISS. Despite the delay, the Axiom-4 mission remains significant. The Ax-4 crew includes members from India, Poland, and Hungary, marking each nation's first mission to the space station in history and the second government-sponsored human spaceflight mission in over 40 years, according to Axiom Space. Group Captain Shubhanshu Shukla will be India's second national astronaut to go to space since 1984. Group Captain Shubhanshu Shukla is part of Axiom Space's fourth private astronaut mission (Ax-4), marking a historic moment for India's space collaboration with Nasa. According to Axiom Space, the Ax-4 mission will "realise the return" to human spaceflight for India, Poland, and Hungary, marking each nation's first government-sponsored flight in more than 40 years. (Only the headline and picture of this report may have been reworked by the Business Standard staff; the rest of the content is auto-generated from a syndicated feed.)

Safety, mission integrity top priority, says ISRO amid Axiom-4 delay
Safety, mission integrity top priority, says ISRO amid Axiom-4 delay

Mint

timean hour ago

  • Mint

Safety, mission integrity top priority, says ISRO amid Axiom-4 delay

New Delhi, Jun 13 (PTI) ISRO on Friday said safety and mission integrity were its top priority as NASA and Axiom Space said they were working to address an issue related to a leak at the International Space Station. India's Shubhanshu Shukla along with three other astronauts are scheduled to travel to the International Space Station (ISS) as part of the Axiom-4 commercial mission that has now been put on indefinite delay, as space agencies address various issues that have cropped up ahead of the launch. "Safety and mission integrity remain our top priorities," ISRO Chairman V Narayanan said in a post on X. He said ISRO is working closely with Axiom Space, NASA and SpaceX, as they responsibly address the ISS Zvezda module observation causing the delay. India's return to spaceflight as part of the Axiom-4 private mission has run into further delay as NASA announced on Thursday that it was examining a leak onboard the ISS' Russian module. "NASA and Axiom Space are postponing the launch of Axiom Mission 4 to the International Space Station," a NASA statement said. The astronauts were originally scheduled for lift-off on May 29, which was put off to June 8, June 10 and June 11, when SpaceX, the providers of the launch rocket and the space capsule, detected a liquid oxygen leak in the Falcon-9 rocket. Former NASA astronaut and director of human spaceflight at Axiom Space, Peggy Whitson, will command the commercial mission, while Indian Space Research Organisation (ISRO) astronaut Shubhanshu Shukla will serve as pilot. The two mission specialists are European Space Agency (ESA) project astronaut Slawosz Uznanski-Wisniewski of Poland and Tibor Kapu of Hungary. The 14-day mission will "realise the return" to human spaceflight for India, Poland and Hungary. "Setbacks and delays are a normal part of spaceflight. Our Ax-4 crew remains upbeat and looking forward to a safe and successful flight to the Space Station," Whitson said in a post on X.

Decision on new Axiom-4 launch date expected soon
Decision on new Axiom-4 launch date expected soon

Time of India

time2 hours ago

  • Time of India

Decision on new Axiom-4 launch date expected soon

Decision on new Axiom-4 launch date expected soon (Picture credit: ANI) CAPE CANAVERAL (FLORIDA): SpaceX appears to have fixed the liquid oxygen ( LOX ) leak it detected in Falcon-9 , and a new date for the launch of the Axiom-4 mission is expected to be finalised after a meeting scheduled post midday here (late in India). At the time of going to press, no formal announcement about a new date was made by SpaceX. But, sources who were part of the two meetings held on June 11 told TOI the final decision would be taken after a test scheduled for June 12. "The test is expected to take a couple of hours and they expect to complete it at least by 2 pm local time here. There will be a meeting soon after the test is complete," a source said around 7 pm IST. "A final decision on the new launch date is expected to be taken there. As of now, SpaceX is looking at two options, June 13 and June 14, and the weather appears to look OK. However, the weather will also be monitored closely." No final decision had been made at the time of filing this report. TOI had reported earlier that SpaceX had detected the LOX leak during a static test fire on Sunday (June 8) and made its discovery public late Monday, stating that the issue was being addressed. Following that, the company said it was "standing down" from the previously decided June 11 launch, to "allow additional time for SpaceX teams to repair the LOX leak identified during post-static fire booster inspections". The final decision on the new launch date will also depend on range availability and weather.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into the world of global news and events? Download our app today from your preferred app store and start exploring.
app-storeplay-store