Redeeming India's nuclear power promise
Simultaneously, the Nuclear Energy Mission announced a special allocation of ₹20,000 crore to develop 'at least five indigenously designed and operational Small Modular Reactors (SMR) by 2033.' Such ambitious plans will need the involvement of private players, both domestic and foreign, into a hitherto government sector, which will require significant changes to the legislative, financial and regulatory framework. The government has indicated that some changes in the Atomic Energy Act, 1962 and the Civil Liability for Nuclear Damage Act (CLNDA), 2010 are in the offing. However, such reforms also need a change in mind set.
India's nuclear journey
India had an early start, setting up Asia's first nuclear research reactor, Apsara, in 1956, and beginning work on Asia's first nuclear power reactors at Tarapore in 1963. As early as 1954, Dr. Homi Bhabha, the architect of India's nuclear programme, presented a target of generating 8 GW of nuclear power by 1980.
However, the journey has been long and difficult. Following India's war with China in 1962; its entry into the nuclear club in 1964; the decision to stay out of the nuclear Non-Proliferation Treaty (NPT) in 1968; and the Peaceful Nuclear Explosion (PNE) test in 1974, India was excluded from the emerging nuclear order. International cooperation ceased and export controls slowed down the nuclear power programme. This led to the nuclear power target being pushed to 10 GW by 2000.
Moreover, India took time to successfully indigenise the design of the 220 MW Pressurised Heavy Water Reactor (PHWR), employed in Rajasthan. Its advantage was that it used natural uranium as fuel unlike the design of the Tarapur Light Water Reactor (LWR), which used Low Enriched Uranium (LEU) that India obtained from the U.S., and later, from France. Subsequently, the same 220 MW PHWR units were established at Narora, Kaiga, Kakrapar etc., and the design was upgraded to 540 MW (set up at Tarapur in 2005-06) and to 700 MW with two units becoming operational at Kakrapar in 2024.
After the nuclear tests in 1998, followed by intense negotiations with the U.S. and other strategic partners, India finally gained acceptance as a responsible nuclear power. It also got a special waiver from the Nuclear Suppliers Group (NSG).
India was thus ready to resume exchanges with other nuclear powers to import both nuclear fuel and more advanced reactors to expand its nuclear energy programme.
However, the CLNDA created new difficulties that have prevented such anticipated external participation. In fact, Russia is the only country that is partnering with us at Kudankulum with six VVER-1000 power reactors because the government-to-government agreement, signed in 1988, predated the CLNDA.
Towards green development
To become a developed country by 2047, India's annual per capita income needs to grow from the current $2,800 to $22,000, and correspondingly, the GDP needs to grow from the current $4 trillion to over $35 trillion. There is a well-established correlation between economic growth and energy consumption. In 2022, India's per capita electricity consumption stood at 1,208 kWh, compared to 4,600 kWh for China, and over 12,500 kWh for the U.S.
India's electricity generation capacity, currently at 480 GW (divided almost equally between fossil fuels and renewables), will have to grow five-fold, accounting for growth in population and urbanisation. However, solar, wind, and small hydro projects provide only intermittent power. That is why out of 2030 terrawatt-hours (TWh) — the total electricity generated in 2024 — renewable energy, with half the generation capacity, accounted for only 240 TWh. Coal fired thermal plants accounted for 75% of energy generation.
The climate change commitments announced by Prime Minister Narendra Modi in 2021 at Glasgow COP26 of 'net zero emissions by 2070, raising non-fossil energy generation capacity to 500 GW by 2030 while meeting 50% of the energy demand through renewables, and achieving a carbon intensity reduction of 45% over 2005 levels by 2030' means that India will not be able to rely on fossil fuels for its growth. Renewable energy is (including solar, hydro, wind, and biomass) is estimated to provide 20% of the demand and up to 25% with investments in battery and pumped storage. Therefore, the obvious candidate to fuel India's energy growth is nuclear power.
There is a renewed interest globally in nuclear power. This reflected in the Dubai 2023 COP28 'Declaration to Triple Nuclear Energy', acknowledging nuclear power as a critical input in reducing reliance on fossil fuels, enhancing energy security, and a move towards a low carbon future. In June, the International Atomic Energy Agency (IAEA) and the World Bank agreed to work together to support nuclear energy in developing countries, marking a significant policy shift. World Bank President Ajay Banga pointed out, 'nuclear (energy) delivers base load power, which is essential to building modern economies.'
Creating an enabling environment
The government is looking at three routes. One is to standardise the 220 MW PHWR design and apply it to Bharat Small Modular Reactors, which would significantly reduce costs and commissioning time. This could replace captive thermal power plants that today account for over 100 GW, and which will be replaced over the next two decades.
The second track is to scale up the Nuclear Power Corporation of India Limited (NPCIL) plans for the 700 MW PHWR by facilitating land acquisition, streamlining licensing, and strengthening indigenous supply chains.
The third track is to accelerate negotiations with partners in France and U.S. that have been moving at a glacial pace for the last 15 years.
Under the Atomic Energy Act, nuclear power is a sector reserved by the government. The NPCIL is a government owned company that builds, owns, and operates the PHWRs, the first two Tarapur LWRs, and the Russian designed VVERs. Nuclear power financing is qualitatively different because of the higher upfront capital costs, lower operating costs, a lifecycle of 50-60 years, and costs associated with decommissioning as well as managing radioactive waste. The indigenised PHWR model has a capital cost of $2 million/MW while the equivalent cost for a coal fired thermal unit is just under a million. Given NPCIL's annual budget of $1.2 billion, the government has realised that to achieve the target of 100 GW, private sector companies will have to be brought into the sector, necessitating a comprehensive set of amendments to the Atomic Energy Act.
Questions of majority/minority ownership; whether the nuclear operator will be exclusively NPCIL; who has responsibility and control over the nuclear island part of the plant; and concerns over assured fuel supply and waste management responsibility will need to be discussed with potential stakeholders that include major players like Tatas, Adani, Ambani, Vedanta etc. All these will require amendments to the 1962 Act.
A set of comprehensive amendments will also be needed for the 2010 CLNDA especially with regards to its liability clause which affects not just the 'operator' but also the 'supplier' of nuclear power.
A third area is commercial disputes relating to tariffs. Nuclear electricity tariff for NPCIL is notified under the Atomic Energy Act. Generally, commercial disputes fall under the Electricity Act and are settled by the Central Electricity Regulatory Commission (CERC) but a recent dispute between NPCIL and Gujarat Urja Vikas Nigam has led to conflicting views by the CERC and the Appellate Tribunal. The case is now under consideration before the Supreme Court. With the entry of the private sector into the field, should the tariff setting come into the 'levelised cost of energy' as applicable to thermal, solar, wind and hydro will depend on how the question of ownership and control are determined.
While India has had an impeccable nuclear safety record, the certification and safety oversight is the responsibility of the Atomic Energy Regulatory Board (AERB) that is 'autonomous' but not a legal entity and is subordinate to the Department of Atomic Energy. In 2011, a draft Bill was circulated to establish AERB as an independent regulator, but the Bill lapsed. With the entry of the private sector, the need for an independent regulator becomes paramount.
In addition, a raft of financial incentives will need to be introduced. While nuclear energy is a low-carbon energy source, it is not classified as 'renewable', like solar or wind. Revising this classification would make nuclear power projects eligible for tax incentives and specially designed 'green financing' instruments. Long term power-purchase-agreements and provision for viability-gap-funding are other incentives. The sector also needs to be opened up to foreign direct investments, perhaps up to 49%, to ensure Indian ownership and control.
In the past, the process of reform has been tentative. In 2011, the NPCIL set up a Joint Venture (JV) with the National Thermal Power Corporation (NTPC), but it languished till it was revived last year. It will now build and operate four units of 700 MW each, scheduled to come up at Mahi Banswara in Rajasthan. Land acquisition has been underway and once completed, the first unit will take seven years. A JV with the Rural Electrification Corporation (REC) is also being envisaged. Both the REC and NTPC are public sector units and these JVs will be wholly government entities.
However, if India has to deliver on the promise of 100 GW by 2047, it needs foreign partners and the private sector. While this has been accepted by the government, it now has to move forward with the reforms comprehensively and decisively.
Rakesh Sood is a former diplomat and is currently Distinguished Fellow at the Council For Strategic and Defence Research.
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Time of India
32 minutes ago
- Time of India
Raising FDI limit in insurance aimed at unlocking full potential of sector: FM Sitharaman
Raising the FDI limit in insurance to 100 per cent will help the sector achieve its full potential by growing at 7.1 per cent per annum over the next 5 years, outpacing the global growth, Finance Minister Nirmala Sitharaman informed Parliament on Monday. The finance minister in Union Budget 2025-26 had proposed to raise the limit of foreign investment in insurance sector from the existing 74 per cent to 100 per cent. Explore courses from Top Institutes in Please select course: Select a Course Category Healthcare Project Management MCA MBA Public Policy Data Science Digital Marketing Cybersecurity others CXO Data Science Management Product Management Leadership Design Thinking Others healthcare Data Analytics Finance Artificial Intelligence Operations Management Skills you'll gain: Financial Analysis in Healthcare Financial Management & Investing Strategic Management in Healthcare Process Design & Analysis Duration: 12 Weeks Indian School of Business Certificate Program in Healthcare Management Starts on Jun 13, 2024 Get Details Raising the limit will eliminate the need for foreign investors to find Indian partners for the remaining 26 per cent, easing the process of setting up their operations in India, effectively increasing the number of insurers in the country, she said in a written reply to Lok Sabha. by Taboola by Taboola Sponsored Links Sponsored Links Promoted Links Promoted Links You May Like 2 Insane Cards Now Charging 0% Interest Until Nearly 2027 CompareCredit Undo This will attract stable and sustained foreign investment, increase competition, facilitate technology transfer, and improve insurance penetration in the country, she said. The decision to increase FDI component in a particular insurance company is made by its promoters, depending upon various factors such as capital requirement of the company, solvency requirement, future business plans etc, the minister said. Live Events Replying to another question, Sitharaman said in order to increase coverage under Pradhan Mantri Jeevan Jyoti Bima Yojana (PMJJBY), Pradhan Mantri Suraksha Bima Yojana (PMSBY) and Atal Pension Yojana (APY), regular campaigns were held at grass root level with active participation of banks and local administration. Further, she said, a 3-month 'Financial Inclusion Saturation Campaign' has been launched across the country in 2.70 lakh gram panchayats and Urban Local Bodies (ULBs) from July 1, 2025, with the aim of increasing enrolments in PMJJBY, PMSBY and APY. To achieve saturation in these Jansuraksha schemes, camps are being organized at gram panchayat level and ULBs by banks, providing residents with direct access to information and assistance for enrolling in the scheme, she said. The initiative is aimed to raise awareness and improve participation, helping to bridge gaps in enrolment under the scheme. The Centre for Financial Literacy (CFL) project was initiated by the Reserve Bank of India in 2017 with an objective to adopt community-led innovative and participatory approaches to financial literacy, the minister said. As on March 31, 2025, a total of 2,421 CFLs have been set up across the country with one CFL covering three blocks on an average, she added. PTI


Economic Times
an hour ago
- Economic Times
UltraTech lines up Rs 10,000 cr capex for FY26 to bolster capacity
Cement maker UltraTech, which expects around 7 per cent growth in FY26, has allocated up to Rs 10,000 crore as capex to bolster its capacity as well as energy and efficiency initiatives, according to the company's latest annual report. The Aditya Birla group firm recently acquired South-based India Cements and the cement business of Kesoram Industries, and added 26.3 MTPA of grey cement capacity to its portfolio. It has planned an organic capacity addition of 28.8 MTPA by FY27. UltraTech, which crossed the Rs 75,000 crore revenue mark in FY25 and is now very close to 200 MTPA (million tonnes per annum) capacity, anticipate a reduction in "net debt to EBITDA ratio", helped by a higher volume growth and improving margins. "Although our net debt to EBITDA (pre-tax profit) ratio rose to 1.33x in March 2025, we anticipate higher volume growth and an improving EBITDA profile to reduce this rapidly," its Managing Director K C Jhanwar said while addressing the shareholders. Like other cement makers, UltraTech also faced a lowered sales realisation amidst tepid demand conditions last year, which marginally declined its EBITDA (earnings before interest, taxes, depreciation and amortisation) compared with FY24. The cement demand has reached approximately 435 million tonnes in India, and with tailwinds such as continued government focus on infrastructure development, affordable housing, and urbanisation is expected to bolster the demand further, the company said. Moreover, the government in its Union Budget allocated Rs 11.21 lakh crore for the infrastructure sector, providing further tailwind to demand for cement. "While cement demand moderated to 4-5 per cent in FY 2024-25 owing to a temporary slowdown in government infrastructure spending and a prolonged monsoon, it is likely to rebound to 6-7 per cent in FY 2025-26," Jhanwar added. He further said UltraTech added 42.6 MTPA of consolidated grey cement capacity through organic and inorganic growth in FY25, taking total capacity to 188.8 MTPA. As of June 30, 2025, the company's consolidated capacity has reached 192.26 MTPA and is accelerating its journey towards the 200 MTPA capacity milestone, he added. On scaling up the capacity, Jhanwar said, besides acquisitions of India Cements and Kesoram Industries, the company has added 16.3 MTPA through organic expansions, which accounted for 55 per cent of India's total cement sector expansion in FY25, reinforcing its industry-leading position. On India Cements and Kesoram, he said the two entities have significantly strengthened our footprint in the attractive South India market. "We are unlocking further value through energy and efficiency initiatives. For instance, at the erstwhile Kesoram units, we are expanding green energy capacity by 107 MW to enhance operational efficiencies," he said. For India Cement, which achieved EBITDA break-even in the March 2025 quarter after efficiency improvements, UltraTech said "a capex plan is being made for investments over the next two years for improvement in all areas of operations to bring these assets at par with UltraTech standards". UltraTech is facing competition from Adani group firm Ambuja Cements, which is also adding capacity through acquisitions and pacing up organic capacity addition at existing units. It has crossed 100 MTPA capacity in FY25 in a record time, mainly through acquisitions, and now aims to reach 118 MTPA by FY2026 and 140 MTPA by FY2028. Adani Group, which jumped into the Cement sector in September 2022 after acquiring controlling stakes in Ambuja Cement from Swiss firm Holcim for cash proceeds of USD 6.4 billion (about Rs 51,000 crore), owns ACC Ltd. Later, it acquired small companies such as Hyderabad-based Penna Cement, Saurastra-based Sanghi Industries and Orient Cement from the CK Birla group.


News18
2 hours ago
- News18
UltraTech lines up Rs 10,000 cr capex for FY26 to bolster capacity
New Delhi, Jul 28 (PTI) Cement maker UltraTech, which expects around 7 per cent growth in FY26, has allocated up to Rs 10,000 crore as capex to bolster its capacity as well as energy and efficiency initiatives, according to the company's latest annual report. The Aditya Birla group firm recently acquired South-based India Cements and the cement business of Kesoram Industries, and added 26.3 MTPA of grey cement capacity to its portfolio. It has planned an organic capacity addition of 28.8 MTPA by FY27. UltraTech, which crossed the Rs 75,000 crore revenue mark in FY25 and is now very close to 200 MTPA (million tonnes per annum) capacity, anticipate a reduction in 'net debt to EBITDA ratio", helped by a higher volume growth and improving margins. 'Although our net debt to EBITDA (pre-tax profit) ratio rose to 1.33x in March 2025, we anticipate higher volume growth and an improving EBITDA profile to reduce this rapidly," its Managing Director K C Jhanwar said while addressing the shareholders. Like other cement makers, UltraTech also faced a lowered sales realisation amidst tepid demand conditions last year, which marginally declined its EBITDA (earnings before interest, taxes, depreciation and amortisation) compared with FY24. The cement demand has reached approximately 435 million tonnes in India, and with tailwinds such as continued government focus on infrastructure development, affordable housing, and urbanisation is expected to bolster the demand further, the company said. Moreover, the government in its Union Budget allocated Rs 11.21 lakh crore for the infrastructure sector, providing further tailwind to demand for cement. 'While cement demand moderated to 4-5 per cent in FY 2024-25 owing to a temporary slowdown in government infrastructure spending and a prolonged monsoon, it is likely to rebound to 6-7 per cent in FY 2025-26," Jhanwar added. He further said UltraTech added 42.6 MTPA of consolidated grey cement capacity through organic and inorganic growth in FY25, taking total capacity to 188.8 MTPA. As of June 30, 2025, the company's consolidated capacity has reached 192.26 MTPA and is accelerating its journey towards the 200 MTPA capacity milestone, he added. On scaling up the capacity, Jhanwar said, besides acquisitions of India Cements and Kesoram Industries, the company has added 16.3 MTPA through organic expansions, which accounted for 55 per cent of India's total cement sector expansion in FY25, reinforcing its industry-leading position. On India Cements and Kesoram, he said the two entities have significantly strengthened our footprint in the attractive South India market. 'We are unlocking further value through energy and efficiency initiatives. For instance, at the erstwhile Kesoram units, we are expanding green energy capacity by 107 MW to enhance operational efficiencies," he said. For India Cement, which achieved EBITDA break-even in the March 2025 quarter after efficiency improvements, UltraTech said 'a capex plan is being made for investments over the next two years for improvement in all areas of operations to bring these assets at par with UltraTech standards". UltraTech is facing competition from Adani group firm Ambuja Cements, which is also adding capacity through acquisitions and pacing up organic capacity addition at existing units. It has crossed 100 MTPA capacity in FY25 in a record time, mainly through acquisitions, and now aims to reach 118 MTPA by FY2026 and 140 MTPA by FY2028. Adani Group, which jumped into the Cement sector in September 2022 after acquiring controlling stakes in Ambuja Cement from Swiss firm Holcim for cash proceeds of USD 6.4 billion (about Rs 51,000 crore), owns ACC Ltd. Later, it acquired small companies such as Hyderabad-based Penna Cement, Saurastra-based Sanghi Industries and Orient Cement from the CK Birla group. PTI KRH KRH SHW view comments First Published: July 28, 2025, 15:15 IST Disclaimer: Comments reflect users' views, not News18's. Please keep discussions respectful and constructive. Abusive, defamatory, or illegal comments will be removed. News18 may disable any comment at its discretion. By posting, you agree to our Terms of Use and Privacy Policy.