After 13 years and R9 billion, Go!Durban still lacks buses
Image: Doctor Ngcobo / Independent Newspapers
Approximately R9 billion has been spent on the Go!Durban project to streamline public transportation, but there are no buses on the route 13 years later.
The money was spent on infrastructure, fleet procurement, and related professional services, according to municipal reports.
In a general statement, the eThekwini Transport Authority (ETA) stated that it intends to redefine its Integrated Public Transport Network (IPTN) under the GO!Durban programme, presenting a revised strategy aimed at overcoming key challenges in its implementation.
In its efforts to address setbacks, including the prolonged negotiations within the minibus taxi and bus industries that stalled progress in 2021, the ETA's new strategy reflects a proactive realignment with national priorities and frameworks.
Video Player is loading.
Play Video
Play
Unmute
Current Time
0:00
/
Duration
-:-
Loaded :
0%
Stream Type LIVE
Seek to live, currently behind live
LIVE
Remaining Time
-
0:00
This is a modal window.
Beginning of dialog window. Escape will cancel and close the window.
Text Color White Black Red Green Blue Yellow Magenta Cyan
Transparency Opaque Semi-Transparent Background Color Black White Red Green Blue Yellow Magenta Cyan
Transparency Opaque Semi-Transparent Transparent Window Color Black White Red Green Blue Yellow Magenta Cyan
Transparency Transparent Semi-Transparent Opaque
Font Size 50% 75% 100% 125% 150% 175% 200% 300% 400% Text Edge Style None Raised Depressed Uniform Dropshadow Font Family Proportional Sans-Serif Monospace Sans-Serif Proportional Serif Monospace Serif Casual Script Small Caps
Reset
restore all settings to the default values Done
Close Modal Dialog
End of dialog window.
Advertisement
Next
Stay
Close ✕
Ad loading
Nelisiwe Zama, acting director of ETA, said they will initiate an in-depth engagement process with all relevant stakeholders, including regional briefings and discussions with affected minibus taxi and bus operators specific to phase one routes of the network.
On Thursday, eThekwini councillors noted the progress made towards the operation of the C3 corridor to achieve an integrated transportation system and preparations for other corridors, namely the C1 and C9, and the inner city to follow suit for an overall improved transport system within the municipality.
Other key points raised for noting were:
Transition from the Tactical Adjustment Framework to a refined corridor-based Go! Durban Implementation Strategy that aligns with the National Department of Transport (DoT), Treasury, and operator expectations.
The municipality is preparing for the transformation and devolution of the Public Transport Operator Grant (PTOG), with plans to integrate existing subsidised services and legacy operators into the Go! Durban corridors.
The refined Go!Durban implementation strategy, with corridor-based rollout, operator negotiations, and quality bus service activation model, will be approved.
The commencement of structured negotiations and identification of affected operators for Corridors C3, C1, C9, and Inner City Distribution System, to enable compliant Vehicle Operating Company formation and contracting
Councillors also approved the call for continued engagements with the provincial and national DoT and National Treasury regarding:
(a) disbursement and milestone compliance.
(b) institutional support for contract devolution and PTOG integration.
Councillors gave the go-ahead for the establishment of a PTOG Transition Framework and Task Team within ETA to lead planning for the absorption of legacy services and operators into the municipal framework.
At a council meeting, eThekwini Councillor Warren Burne described the report as vague and incomplete, with no mention of cash flow projections.
He said the good intentions for the project from the municipal administration in 2012 were now nothing but a pipe dream 13 years later.
'Here we are years later, trying desperately to breathe life into the matter,' he said.
Councillor Jenni Black said the Go!Durban was an important project for the livelihood of South Africans who would be able to access work opportunities outside of their living area.
'The stakeholders are the residents and ratepayers of eThekwini. We are responsible for how the money is spent,' she said.
Zwakele Mncwango, ActionSA councillor, described the process of noting this item in council as approving a blank cheque, while Sandile Gwala, an IFP councillor, was concerned that the infrastructure along the route would soon need rehabilitation.
Timeline In April 2012 municipal council approved Go! Durban IPTN.
In October 2021, tension around vehicle ownership between the operators and the municipality culminated in a deadlock, with the operators affected along C3.
In 2022, the eThekwini council commenced with the public participation process with the operators as well as the public on the revised strategy (Tactical Adjustment).
In 2023, the council approved the tactical adjustment; however, the National DoT did not fully endorse the strategy.
In May 2025, the strategy was finalised.
zainul.dawood@inl.co.za
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles

IOL News
10 hours ago
- IOL News
Why workforce flexibility is key to powering South Africa's renewable future
By supplying skilled, reliable labour that can adapt to changing site needs, TES providers are helping energy operators keep performance high, manage costs, and support surrounding communities. Image: Henk Kruger/Independent Newspapers South Africa's renewable energy sector is entering a new chapter. After years of growth focused on building solar farms and wind projects, the spotlight is shifting, and the new priority is making sure these sites operate efficiently and reliably for the long term. This is where Temporary Employment Services (TES) providers are stepping in. By supplying skilled, reliable labour that can adapt to changing site needs, TES providers are helping energy operators keep performance high, manage costs, and support surrounding communities. From construction to long-term performance In the early days, renewable energy projects were all about construction. Teams were sent into rural areas to build the infrastructure, install panels and get everything up and running. While the construction phase sees the most action, it is once a project has been commissioned that the real work begins, with these sites needing maintenance to ensure they produce energy as expected and remain financially viable. Here, ongoing maintenance is more than a technical requirement. It is essential for the long-term success of the entire renewable energy strategy. These sites need regular inspections, fault detection, cleaning, and servicing to stay productive, as without proper maintenance, even the best solar or wind farm can end up underperforming or sitting idle. Video Player is loading. Play Video Play Unmute Current Time 0:00 / Duration -:- Loaded : 0% Stream Type LIVE Seek to live, currently behind live LIVE Remaining Time - 0:00 This is a modal window. Beginning of dialog window. Escape will cancel and close the window. Text Color White Black Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Background Color Black White Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Transparent Window Color Black White Red Green Blue Yellow Magenta Cyan Transparency Transparent Semi-Transparent Opaque Font Size 50% 75% 100% 125% 150% 175% 200% 300% 400% Text Edge Style None Raised Depressed Uniform Dropshadow Font Family Proportional Sans-Serif Monospace Sans-Serif Proportional Serif Monospace Serif Casual Script Small Caps Reset restore all settings to the default values Done Close Modal Dialog End of dialog window. Advertisement Next Stay Close ✕ Ad Loading Maintenance is what ensures these projects continue delivering power, return on investment, and energy security over their full 20-year lifespan. As more sites move from construction to operation, there has been a rise in specialised maintenance companies. They are creating a whole new layer of the industry focused on long-term performance, and they need the right resources in place to keep things running smoothly. A smart, flexible workforce model TES providers are uniquely positioned to support this next phase. Unlike the large workforces required during construction, maintenance relies on smaller, specialised teams that need to be flexible and responsive. TES providers are built to meet this demand, offering a staffing model that allows companies to adjust their workforce according to site needs, without the complexity or cost of hiring permanent employees. TES teams are often involved in renewable energy projects from the construction phase, which means they are familiar with the local talent pool. They identify people with potential and help them grow into skilled roles, so that by the time maintenance starts, there is already a trained and trusted workforce available. Pierre Bekker, Director at Quyn International Outsourcing Image: Supplied

IOL News
20 hours ago
- IOL News
Economists warn of job losses as US tariffs threaten South African trade
The South African sugar industry is facing the threat of collapsing and job losses as a result of US President Donald Trump imposing 30% tariffs on the country's exports. Image: Karen Sandison / Independent Newspapers In the wake of the recent 30% tariff hike imposed by the United States, South Africa's sugar and automotive industries are bracing for significant upheaval. Economists warn that these tariffs could spell disaster for local businesses, jeopardising exports and leading to alarming job losses. An economist has warned that losing the market will collapse the industry after President Donald Trump's 30% tariff hike imposed on goods exported to the country's second biggest trade partner. Economist Miyelani Mkhabela shared these sentiments as some local exporters already expressed concern about their future. 'People have a reason to panic because the tariffs will make it difficult for South African products to appeal to the American market,' said Mkhabela. He said small industries are facing the danger of collapsing because although the normal trade deal between South Africa and the US might be restored after the end of Trump's presidency, 'four years is a lot for a company.' 'When the market is closed (through exorbitant tariffs), it means a lot for small businesses that are sending products to the American market would suffer, as their clients would say your products are 30% higher. 'That would collapse the South African manufacturing system because we depend on the US as our second trade partner,' he said. He said South Africa cannot easily find a country that could replace the American market, which 'is bigger than what we are sending to the whole of Africa'. However, he said the African economy would recover after four years as it recovered from the global financial crisis and 'is still recovering from the global health (Covid-19 pandemic). But after Trump, many emerging companies will no longer exist because they will fail to repay bank loans. SA Farmers Development Association (SAFDA) Executive Chairman Dr Siyabonga Madlala, who is involved in sugar manufacturing, is concerned that while businesses have no power over politically influenced tariffs, they are the ones bearing the brunt. Madlala anticipated a loss of millions of rand, a situation that would result in alarming job losses. He said the South African Sugar Association (SASA)'s lots of sugar meant for the US might go to waste. 'America, through AGOA (the African Growth and Opportunity Act), has given us a lucrative market for about 24,000 tons of sugar exports, so with the imposition of tariffs, our sugar won't be attractive to our US consumers as it is now becoming expensive. 'It forces US consumers to look for alternatives rather than buying from us because our sugar becomes 30% more expensive,' said Madlala. South African competitors in supplying the US with sugar are Mexico, Brazil, Australia, and several Central American and Caribbean nations. He estimated that, through the tariffs, SASA will lose R168 million from its annual revenue. According to Madlala, the US market, which found South African sugar affordable under the AGOA agreement, may look for alternative countries to buy from. 'The reason is that lots of other countries are subsidised, therefore they can afford to still sell sugar than us, as we are not subsidised but working on our own,' said Madlala. He said reducing production would cause job losses and the shutdown of sugar mills. 'Once you try to lower the production, it means some farms will shut down or diversify. By that, it means that sugar mills will lose sugar cane supply, which is the lifeblood of the sugar mill,' he said. He said the tariffs came at the wrong time when the government's master plan was succeeding in reviving some major sugar mills, including Tongaat Hulett, which in the process was coming out of business rescue. 'While we are appreciating the master plan's initiative, we are now bombarded with the tariffs,' said Madlala. Influential organisations such as FW De Klerk Foundation recently called for the country to expand its trade partners rather than relying on the US. Agriculture Minister John Steenhuisen said the government was also reaching out to other countries. However, Madlala said finding an alternative market was not easy to do overnight. National Association of Automotive Component and Allied Manufacturers (NAACAM) CEO Renai Moothilal told the media that the automotive industry was already feeling the effects, as some companies have started to lose US deals. 'We are already seeing new contracts, especially for the US, being cancelled or not pursued, putting one of the country's most critical manufacturing sectors at risk,' Moothilal said. Build One SA (BOSA) called on Ramaphosa to engage directly with the US Congress members, who will decide on the fate of AGOA, and tell them that over 500,000 US jobs are linked to trade with South Africa. Another economist, Khulekani Mathe, commended Ramaphosa for continuing to negotiate with Trump, as he cannot immediately find an alternative market. He said it was not guaranteed that South Africa/US trade would recover after Trump's departure. 'It is dependent on whether we are to negotiate anytime between now and four for more favourable terms. The economic recovery would depend on whether the country can find an alternative market to send the volume of products that are sent to the US, something that can not materialise in the short term. Professor Bonke Dumisa said Trump was miscalculating to think tariffs would benefit his economy because 'Economic History shows us that no one wins the tariff wars'. 'Purportedly, it is said that the USA wants to open space for its businesses to recapture the market space they lost as they focused on moving abroad to produce more competitively priced products. Unfortunately, USA businesses priced themselves out of the markets. 'The South African businesses affected by these Tariffs must look for alternative markets. There is very little that the government can do to help these businesses,' said Dumisa. [email protected]

IOL News
a day ago
- IOL News
Ratepayer associations praise eThekwini's landfill gas initiative for economic benefits
eThekwini officials along with Minister of Electricity and Energy, Dr Kgosientsho Ramokgopa tour the Landfill Gas to Electricity Clean Development Mechanism (CDM) project in Springfield, Durban. Image: Sibonelo Ngcobo eThekwini ratepayers were assured that the Landfill Gas to Electricity Clean Development Mechanism (CDM) project was financially sound and had an economic benefit. eThekwini mayor Cyril Xaba made the assurance during the visit to the project site in Durban by the minister of Electricity and Energy Dr Kgosientsho Ramokgopa, on Friday. Ramokgopa also announced the outcome of the Section 34 Ministerial Determination giving the municipality the go-ahead to procure new electricity generation capacity directly from Independent Power Producers. Xaba stated that preliminary modelling indicates savings of approximately R5 billion throughout the Power Purchase Agreements (PPAs), translating to around R250 million in annual savings. 'These are savings we can redirect to the upgrading of infrastructure for basic services that will directly benefit our residents,' he said. Xaba explained that this programme is catalytic as it is projected to unlock R8.5 billion in private investment and boost regional industrial activity. He said it will also create an estimated 2,200 jobs during construction and operation phases. Video Player is loading. Play Video Play Unmute Current Time 0:00 / Duration -:- Loaded : 0% Stream Type LIVE Seek to live, currently behind live LIVE Remaining Time - 0:00 This is a modal window. Beginning of dialog window. Escape will cancel and close the window. Text Color White Black Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Background Color Black White Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Transparent Window Color Black White Red Green Blue Yellow Magenta Cyan Transparency Transparent Semi-Transparent Opaque Font Size 50% 75% 100% 125% 150% 175% 200% 300% 400% Text Edge Style None Raised Depressed Uniform Dropshadow Font Family Proportional Sans-Serif Monospace Sans-Serif Proportional Serif Monospace Serif Casual Script Small Caps Reset restore all settings to the default values Done Close Modal Dialog End of dialog window. Advertisement Next Stay Close ✕ Ad loading 'This initiative will also empower small businesses and promote inclusive enterprise and supplier development. Therefore, this is not an abstract policy document; it is a tangible plan that will bring meaningful change to our communities,' Xaba said. From an energy security standpoint, Xaba stated that once fully operational, the new capacity will reduce eThekwini's reliance on the national grid by 18%, significantly cushioning us from up to Stage 3 load shedding. During this period, the economy can stay productive, and hospitals, schools, and police stations will continue operating without any disruption. eThekwini electricity official Logan Moodley and Minister of Electricity and Energy Dr Kgosientsho Ramokgopa at the Landfill Gas to Electricity Clean Development Mechanism (CDM) project in Springfield, Durban. Image: Sibonelo Ngcobo The project supports both the Climate Action Plan and South Africa's Nationally Determined Contributions (NDCs) under the Paris Agreement. It is expected to avoid 250,000 tonnes of CO₂-equivalent emissions annually, a significant step towards achieving a just transition and low-carbon emissions. This programme will allow eThekwini Municipality to procure 400 MW of new generation capacity (100 MW Solar PV and 300 MW Gas to Power (GTP), with a focus on dispatchable, reliable, and low-carbon energy technologies. Ramokgopa said eThekwini Metro's bold move to develop internal energy generation capacity to bolster energy security is commendable. He said that the Ministerial Determination is in line with the department's broader electricity reforms and the Just Energy Transition. Ramokgopa added that the embedded generation will reduce eThekwini's net dependence on Eskom supply. Potentially mitigating against Stage 3 load shedding across industrial and commercial zones Asad Gaffar, chairperson of eThekwini Ratepayers Protest Movement (ERPM) described the project as a move in the right direction, provided proper controls are put in place. 'There must be no tenderpreneurship opportunities and no corruption in the process. There is a need for an additional electricity supply, which, unfortunately, Eskom cannot provide at this stage. This will also be good for investor confidence,' Gaffar said. Norman Gilbert, chairperson of the Bluff Ratepayers and Residents Association, welcomed the news of this ambitious programme and the clear economic benefits it promises for the city. Gilbert said that the prospect of creating over 2,200 jobs, unlocking R8.5 billion in private investment, and stimulating regional industry is an incredible opportunity for Durban's people and economy. 'If the ultimate goal of reducing the electricity tariff is achieved, it will bring much-needed relief to households whose budgets are already under severe strain. For many residents, electricity has simply become unaffordable, and this initiative could restore the dignity that reliable and affordable power brings to daily life,' Gilbert stated. He described the project as forward-thinking, results-driven action that can transform the communities, create jobs, grow the economy, and improve the quality of life for all residents. Ish Prahladh, chairperson of the eThekwini Residents and Ratepayers Association (ERRA), said there must be a saving in the long run for residents. He said the project, if it goes ahead, will be a game-changer and will be a challenge to Eskom. 'The project must not be derailed. Eskom needs an opposition so that it can reduce electricity prices,' he said.