Eskom admits to challenges in meeting 2030 emissions targets

Eskom admits to challenges in meeting 2030 emissions targets

IOL News17-07-2025
Cooling towers at an Eskom coal-based power station in Duhva. Eskom's head of generation Bheki Nxumalo on Wednesday revealed that the utility's existing power stations may struggle to meet the crucial emissions standards due to insufficient technology designed to curb nitrogen oxides (NOx) and sulphur oxides (SOx).
Image: Mike Hutchings/Reuters
South Africa's power utility, Eskom, has openly acknowledged significant hurdles in achieving the ambitious decommissioning targets set for the Just Energy Transition (JET) by 2030.
During a presentation to Parliament on Wednesday, Eskom's head of generation Bheki Nxumalo revealed that the utility's existing power stations may struggle to meet the crucial emissions standards due to insufficient technology designed to curb nitrogen oxides (NOx) and sulphur oxides (SOx).
"The emissions standards post-2030 call for reduction much more aggressively. That's where the risks are because stations have different technologies. We are now on a drive for emissions abatement technologies post-2030 but its not all of them that will be ready, including Medupi," Nxumalo said in response to questions from MK Party MP, Brian Molefe.
"Kusile will meet most of the requirements but it is going to be an issue to comply with that. Most will but the "NOx and SOx" will require more in refurbishment."
Video Player is loading.
Play Video
Play
Unmute
Current Time
0:00
/
Duration
-:-
Loaded :
0%
Stream Type LIVE
Seek to live, currently behind live
LIVE
Remaining Time
-
0:00
This is a modal window.
Beginning of dialog window. Escape will cancel and close the window.
Text Color White Black Red Green Blue Yellow Magenta Cyan
Transparency Opaque Semi-Transparent Background Color Black White Red Green Blue Yellow Magenta Cyan
Transparency Opaque Semi-Transparent Transparent Window Color Black White Red Green Blue Yellow Magenta Cyan
Transparency Transparent Semi-Transparent Opaque
Font Size 50% 75% 100% 125% 150% 175% 200% 300% 400% Text Edge Style None Raised Depressed Uniform Dropshadow Font Family Proportional Sans-Serif Monospace Sans-Serif Proportional Serif Monospace Serif Casual Script Small Caps
Reset
restore all settings to the default values Done
Close Modal Dialog
End of dialog window.
Advertisement
Video Player is loading.
Play Video
Play
Unmute
Current Time
0:00
/
Duration
-:-
Loaded :
0%
Stream Type LIVE
Seek to live, currently behind live
LIVE
Remaining Time
-
0:00
This is a modal window.
Beginning of dialog window. Escape will cancel and close the window.
Text Color White Black Red Green Blue Yellow Magenta Cyan
Transparency Opaque Semi-Transparent Background Color Black White Red Green Blue Yellow Magenta Cyan
Transparency Opaque Semi-Transparent Transparent Window Color Black White Red Green Blue Yellow Magenta Cyan
Transparency Transparent Semi-Transparent Opaque
Font Size 50% 75% 100% 125% 150% 175% 200% 300% 400% Text Edge Style None Raised Depressed Uniform Dropshadow Font Family Proportional Sans-Serif Monospace Sans-Serif Proportional Serif Monospace Serif Casual Script Small Caps
Reset
restore all settings to the default values Done
Close Modal Dialog
End of dialog window.
Next
Stay
Close ✕
Nxumalo said Eskom was doing economic studies on its overall Flue Gas Desulphurization (FGD) strategy from exemptions granted by the Department of Fisheries and Forestries and Environment (DFFE), not only for Kusile and Medupi's compliance, with stricter emission standards.
"We are preparing to go to market but also considering the number of units. We are not going to do all of them by 2030, implementation will go post-2030," Nxumalo said.
"We are not only looking at Medupi for reduction of the carbon footprint and also the NOx and SOx across the fleet. The research team is busy at work looking at other means we can employ in units running post-2030."
Eskom Group Executive for Renewables, Rivoningo Mnisi, said the power utility had made a breakthrough in other global entities taking over the slack left by the US withdrawing its more than $1.5 billion commitments to South Africa's JET programme.
"Dynamics and changes from the US have changed how we traditionally view funding, but it comes with opportunities. What we noticed is that the clean energy initiatives need to make business sense," Mnisi said.
"We have had engagements with the World Bank that sourced funding from various funders. They are quite aware of our 5-year projects and are quite keen and confident to support the funding requirement.
"We have also engaged with others [such as] the French Union. There is an appetite to partner. There is also interest from the Chinese funders interested in this. It's key how we go to market on this. We are working on the Public-Private Partnership (PPP) model, which should be structured to allow us offtake and show how projects will make money and what our contribution from the balance sheet will be.
"There is no shortage of funding to support the clean energy initiatives. What's more important is the governance structures to allow the PPP participation and the funding model to take place."
As part of its strategy, Eskom is considering blended financing to avoid restrictions from single funders that could conflict with its operational needs.
"We are in the process of shortlisting the supplier for the 72MW solar PV, while on the 150MW of gas the contract award is imminent and should be done potentially in the next two months," Mnisi said.
"We are also doing some assessment of the long duration energy storage as part of the options we can implement at Komati, as well Grootvlei solar PV and gas on plan. They should be delivered by 2029, a shift from what we did at Komati Development. Work for Arnot, Camden and Hendrina is also started and the intention is to ensure that all projects are implemented and operational before 2030."
BUSINESS REPORT
Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Matshela Koko won't challenge court ruling on R1. 56bn Eskom, ABB settlement
Matshela Koko won't challenge court ruling on R1. 56bn Eskom, ABB settlement

IOL News

time11 hours ago

  • IOL News

Matshela Koko won't challenge court ruling on R1. 56bn Eskom, ABB settlement

Former acting Eskom chief executive Matshela Koko will not challenge the Gauteng High Court, Pretoria judgment dismissing his application to intervene in the dispute between the power utility and ABB South Africa, which agreed to pay almost R1.56 billion in 2020. Image: Bheki Radebe / Independent Newspapers Former acting Eskom chief executive, Matshela Koko, will not challenge the ruling declining his bid to intervene in the R1.56 billion settlement agreement reached by the power utility and ABB South Africa. The Gauteng High Court, Pretoria, last month dismissed with costs Koko's application to intervene in the matter in terms of an earlier judgment delivered in April 2024. At the time, the high court ordered any interested party who has a direct and material interest in its orders on the R1.56bn settlement to apply within 30 days of the last date of publication of the order for leave to intervene and describe the nature of their interest in the relief and the relief sought. The court also ordered that interested parties must show cause, on a date and on such terms as it may determine after receipt of any application why the order should be altered, varied or rescinded. In compliance with the April 2024 order Koko complained that unflattering allegations were made against him in the papers filed in the review proceedings and that he was referred to by name and some paragraphs contain reference to his conduct. He said the settlement agreement for ABB to pay Eskom had negative consequences for him as his bank account was closed and he suffered reputational harm. In refusing Koko's intervention application, Acting Judge Irene de Vos found that he lacked a direct and substantial interest in the subject matter of the review proceedings. "Koko launched an application to rescind an order in circumstances where he largely accepts the order is correct; where he is not mentioned in either the order or the judgment; for purposes of protecting his reputation," the acting judge stated. The contract in question was for the provision of control and instrumentation system for the coal-fired Kusile Power Station project constructed under Eskom's nation building programme to increase its generating capacity. Eskom, ABB and the Special Investigating Unit (SIU) later applied to the court to set aside the contract as a result of corruption and bribery that occurred in the award. The SIU has publicly indicated that it intends to claim monies from Koko, who fears such action. He told the court that not having been cited in the review proceedings means he is limited in presenting a defence in potential future proceedings to be brought against him. In response to questions, Koko, who represented himself in the matter, said the judgment could be summarised as a mixed outcome, adding that he lost the battle to intervene in the review proceedings, but emerged with a significant procedural victory in the broader context. He further said he won the war by emerging from the case without adverse findings or direct legal accountability. Koko added that this procedural victory distances him from the ABB contract irregularities and undermines the narrative tying him to corruption, providing him with a solid defence in this specific legal chapter. [email protected] [email protected]

Fishing industry nets jobs and billions despite small economic share
Fishing industry nets jobs and billions despite small economic share

IOL News

time13 hours ago

  • IOL News

Fishing industry nets jobs and billions despite small economic share

Fishing boats in Kalk Bay Harbour Image: Charles Dagnall Even though the sardine run for this year is officially over, with the reopening of Amanzimtoti Beach following the end of the seasonal fish sea trip, the marine sector remains an important contributor to South Africa's economy. Recent information from Statistics South Africa noted the sector employs just over 16 000 people across South Africa. 'Although the 2025 sardine run has come to an end, the fishing industry continues to play an essential role in supporting coastal communities and contributing to the economy,' it said. The fishing industry contributes around 0.2% to the South African economy. However, when considering the entire value chain of the sector, including related industries, its contribution to gross domestic product can reach about 3%. Caught fish generated R5.4 billion in 2023, making it the second-largest income source within the marine fishing sector. Processed fish was the top income earner. Total industry income reached R19.9 billion last year. While this places it well behind larger industries, such as manufacturing, for example, the marine fishing sector remains vital for food security and livelihoods. The annual migration of sardines along South Africa's east coast, which takes place between May and July, provides seasonal economic benefits for fishing communities along the KwaZulu-Natal coastline. Video Player is loading. Play Video Play Unmute Current Time 0:00 / Duration -:- Loaded : 0% Stream Type LIVE Seek to live, currently behind live LIVE Remaining Time - 0:00 This is a modal window. Beginning of dialog window. Escape will cancel and close the window. Text Color White Black Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Background Color Black White Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Transparent Window Color Black White Red Green Blue Yellow Magenta Cyan Transparency Transparent Semi-Transparent Opaque Font Size 50% 75% 100% 125% 150% 175% 200% 300% 400% Text Edge Style None Raised Depressed Uniform Dropshadow Font Family Proportional Sans-Serif Monospace Sans-Serif Proportional Serif Monospace Serif Casual Script Small Caps Reset restore all settings to the default values Done Close Modal Dialog End of dialog window. Advertisement Video Player is loading. Play Video Play Unmute Current Time 0:00 / Duration -:- Loaded : 0% Stream Type LIVE Seek to live, currently behind live LIVE Remaining Time - 0:00 This is a modal window. Beginning of dialog window. Escape will cancel and close the window. Text Color White Black Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Background Color Black White Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Transparent Window Color Black White Red Green Blue Yellow Magenta Cyan Transparency Transparent Semi-Transparent Opaque Font Size 50% 75% 100% 125% 150% 175% 200% 300% 400% Text Edge Style None Raised Depressed Uniform Dropshadow Font Family Proportional Sans-Serif Monospace Sans-Serif Proportional Serif Monospace Serif Casual Script Small Caps Reset restore all settings to the default values Done Close Modal Dialog End of dialog window. Next Stay Close ✕ Statistics South Africa said that the run also highlights the value of South Africa's marine resources. It said the ocean (marine) fisheries and related services industry remains a significant contributor to food supply, employment, and economic activity, despite being the smallest of the 16 industries surveyed in the agency's recent series of industry-specific reports. Measured by catch volume, anchovy was the most harvested fish species in 2023, with 152 431 metric tons landed. In South Africa, anchovies are used primarily to produce fishmeal and oil rather than for human consumption. Hake was the second-largest species caught by volume, followed by sardines. However, hake generated the highest income, accounting for more than a quarter of total revenue from caught fish in 2023, said Statistics South Africa. This fish brought in R1.4 billion, up from R700 million in 2014. According to Stats South Africa, hake is a staple in South African households. It makes up 0.8% of total household food spending, as reflected in the consumer inflation basket – more than beef steak, sausages or meat patties. Other species such as squid and tuna also showed significant growth in value, contributing more to the industry's income compared to previous years. IOL

Eskom ordered to cough up R1 billion in costs after cancelled Koeberg project
Eskom ordered to cough up R1 billion in costs after cancelled Koeberg project

IOL News

time13 hours ago

  • IOL News

Eskom ordered to cough up R1 billion in costs after cancelled Koeberg project

Eskom loses court bid to fend off R1bn payment after cancelling a contract. Image: Supplied Eskom has been ordered to pay close to R1 billion to French nuclear contractor Framatome, after the Western Cape High Court found the utility refused to pay damages after it cancelled a contract to install steam generators at Koeberg nuclear power station. The ruling stems from a 2014 agreement Eskom originally concluded with Areva, which was later ceded to Framatome. The deal covered the design, manufacture and installation of six replacement steam generators – three for each unit at Koeberg. Framatome, which has been in operation for 60 years, was contracted to supply and install two sets of three replacement steam generators, one set to be installed in each of the reactor buildings at units 1 and 2 at Koeberg during separate planned outages of these units. These installations were meant to take place during a scheduled maintenance outage, which kept getting postponed. Two months after the outage was finally scheduled to happen, 'Eskom informed Framatome that it would not be continuing with the steam generator replacement,' the judgement said. As a result of the cancellation of the deal, Eskom's project manager 'acknowledged that Eskom's decision to postpone the work constituted a compensation event,' the judgment read. Although the project manager had acknowledged that Eskom's cancellation triggered compensation, he determined that the value of compensation was nil. The entire matter then went to arbitration, where the adjudicator ordered that Eskom must pay compensation for cancelling the contract, including for storing equipment, as well as implementation activities, which work had been wasted by Eskom delaying the date of the planned maintenance outage. Video Player is loading. Play Video Play Unmute Current Time 0:00 / Duration -:- Loaded : 0% Stream Type LIVE Seek to live, currently behind live LIVE Remaining Time - 0:00 This is a modal window. Beginning of dialog window. Escape will cancel and close the window. Text Color White Black Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Background Color Black White Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Transparent Window Color Black White Red Green Blue Yellow Magenta Cyan Transparency Transparent Semi-Transparent Opaque Font Size 50% 75% 100% 125% 150% 175% 200% 300% 400% Text Edge Style None Raised Depressed Uniform Dropshadow Font Family Proportional Sans-Serif Monospace Sans-Serif Proportional Serif Monospace Serif Casual Script Small Caps Reset restore all settings to the default values Done Close Modal Dialog End of dialog window. Advertisement Video Player is loading. Play Video Play Unmute Current Time 0:00 / Duration -:- Loaded : 0% Stream Type LIVE Seek to live, currently behind live LIVE Remaining Time - 0:00 This is a modal window. Beginning of dialog window. Escape will cancel and close the window. Text Color White Black Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Background Color Black White Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Transparent Window Color Black White Red Green Blue Yellow Magenta Cyan Transparency Transparent Semi-Transparent Opaque Font Size 50% 75% 100% 125% 150% 175% 200% 300% 400% Text Edge Style None Raised Depressed Uniform Dropshadow Font Family Proportional Sans-Serif Monospace Sans-Serif Proportional Serif Monospace Serif Casual Script Small Caps Reset restore all settings to the default values Done Close Modal Dialog End of dialog window. Next Stay Close ✕ After some back and forth between the parties and the adjudicator, during which the parties didn't agree on costs, 'Eskom made it clear that it had no intention of providing the adjudicator with any further information or participating any further in the adjudication process,' the ruling read. As a result, the adjudicator issued a determination of the damages amount, and Eskom decided to take the issue to the Western Cape High Court, arguing that the amount in damages was not determined by the date it was due – voiding his determination. In defending Eskom's legal action, Framatome argued that none of the arbitration proceedings were improper, nor was the adjudicator abusing his power. The Judge ruled that 'there is no basis to set aside the decisions of the adjudicator which are valid and binding. In terms of the parties' contract Eskom was obliged to comply therewith.' Eskom, it found, had to comply with its contractual obligations. The court found that Framatome was entitled to the full amount it sought. In addition to the R1bn payment, Eskom had to pay interest and costs. IOL

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store