No bids for 3 rounds due to Naxal threat: Govt to HC on bridge delay

No bids for 3 rounds due to Naxal threat: Govt to HC on bridge delay

Time of India27-04-2025
Raipur: In response to delay in constructing a bridge over Chintavagu River in Bijapur, the state govt has informed the Chhattisgarh High Court that contractors are least interested in undertaking construction work in highly Naxal-affected districts of Bijapur, Sukma, and Narayanpur in the state.
In a previous order, the high court had asked the Bijapur collector to file a personal affidavit regarding the construction of a bridge over the Chintavagu River. Now, in the affidavit submitted to the high court, the collector stated that these districts are heavily affected by Naxal activities, which is deterring contractors from participating in any construction in the region.
The collector further said that 3 rounds of bidding for the bridge were held from Nov to Feb but no contractors came forward until the fourth round in March wherein one contractor submitted a bid but a technical bid is yet to be opened.
The state govt, in its submission, also informed the court that it decided on April 1, 2025, to execute sanctioned construction work through the 'Zila Nirman Samiti' if this reluctance of contractors continues and they do not recieve any bids from them. The Samiti is authorised to carry out works up to Rs 10 crore in the district.
Sponsored Links
Sponsored Links
Promoted Links
Promoted Links
You May Like
Google Brain Co-Founder Andrew Ng, Recommends: Read These 5 Books And Turn Your Life Around
Blinkist: Andrew Ng's Reading List
Undo
The High Court, hearing a Suo Moto public interest litigation, had directed the Bijapur collector on March 10, 2025, to file a personal affidavit detailing the response to the third call for tenders (Notice Inviting Tender - NIT).
The Bijapur collector's affidavit acknowledged the necessity of a bridge over the Chintavagu River and stated that a request was made to the Public Works Department (PWD). Administrative approval of Rs 787.66 lakh for the bridge construction on the Gorella-Minnur route was granted on Oct 18, 2024.
The proposal was included in the 2024-25 budget as well, it stated.
Then, the chief engineer, PWD, Bridge Zone, accorded administrative approval for the work on Oct 24, 2024, the collector submitted.
NITs were subsequently issued on Nov 22 and Dec 27, 2024, and Feb 28, 2025, but no contractors came forward due to the 'Naxal deterrent'.
A fourth call for tenders was issued on March 28, 2025, and one contractor submitted a bid. The technical bid is yet to be opened.
The district collector informed the court that if the fourth call is unsuccessful, the bridge construction will be undertaken by the Zila Nirman Samiti, as per the order dated April 1, 2025.
Advocate general Prafull N. Bharat told the division bench of Chief Justice Ramesh Sinha and Justice Arvind Kumar Verma during a recent hearing that the third round of the tender process was completed without any bidders, and the fourth call was issued on March 28, 2025.
If there are no participants this time, the Zila Nirman Samiti will initiate the bridge construction, he said.
Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Good news for Bengaluru as PM Modi to launch Metro's Yellow line and a new Vande Bharat Express to...,important stations include...
Good news for Bengaluru as PM Modi to launch Metro's Yellow line and a new Vande Bharat Express to...,important stations include...

India.com

time30 minutes ago

  • India.com

Good news for Bengaluru as PM Modi to launch Metro's Yellow line and a new Vande Bharat Express to...,important stations include...

Bangalore Metro- File image Bengaluru: In a significant event for the city of Bengaluru, Prime Minister Narendra Modi will inaugurate the much-awaited Yellow Line of Bangalore Metro and the Vande Bharat Express train between Bengaluru and Belagavi here today. In the recent development, PM will also lay the foundation stone for the Bangalore Metro Phase-3 project. Here are all the details you should know about the Bengaluru's Yellow Line Metro and how it will help Bengaluru. As a part of the plan, PM Modi will be landing at the HAL Airport here at 10.30 am and then travel by helicopter and road to the KSR Bengaluru (city) railway station, where he will flag off Vande Bharat Express train between KSR Bengaluru-Belagavi. PM Modi to flag Vande Bharat Express trains: Check details PM Modi will also virtually flag off two more Vande Bharat Express trains between Amritsar-Sri Mata Vaishno Devi Katri, and Ajni (Nagpur)-Pune. Bengaluru traffic police announces traffic restrictions The Bengaluru traffic police has announced traffic restrictions across several areas from 10 AM on Sunday, where the restrictions will remain in place till 2:30 PM. Bengaluru's Yellow Line Metro: What are the details you should know As per the Sunday plan, PM will be flagging off Yellow Line (reach 5) and take a metro ride to the Electronic City station. The yellow line metro from RV Road (Ragigudda) to Bommasandra of Bangalore Metro Phase-2 project, having a route length of over 19 km and 16 stations, is worth around Rs 7,160 crore. How will Yellow Line Metro help Bengaluru? With the opening of this yellow line, the operational metro network in Bengaluru will increase to over 96 km, serving a large population in the region. As per officials, the yellow line is expected to ease traffic congestion in several heavily congested corridors like Hosur Road, Silk Board Junction, and Electronics City Junction. The Metro Phase 3, also known as the Orange Line, for which the PM will be laying the foundation, will be built at an estimated cost of Rs 15,611 crore. The total route length of the project will be more than 44 km with 31 elevated stations. This infrastructure project will address the growing transportation needs of the city, catering to residential, industrial, commercial, and educational areas. Phase 3 will have two corridors or lines: JP Nagar 4th Phase to Kempapura (32.15 km) and Hosahalli to Kadabagere (12.5 km). (With inputs from agencies)

BharatPe to raise funds before IPO, listing not on card this fiscal: CEO Nalin Negi
BharatPe to raise funds before IPO, listing not on card this fiscal: CEO Nalin Negi

Time of India

time30 minutes ago

  • Time of India

BharatPe to raise funds before IPO, listing not on card this fiscal: CEO Nalin Negi

Academy Empower your mind, elevate your skills BharatPe will raise funds before the initial public offer, but the listing will take place only when market conditions are favourable, a top official of the unicorn fintech firm last week, announced that it had achieved operational profitability after excluding the employee stock ownership plan."Whatever goals we set for ourselves, we have gone ahead and achieved has to remain intact, and thereafter, once the market conditions are right, we will definitely go for an IPO. There will be a pre-IPO funding round, while an IPO is not on the cards for this financial year. Anything beyond that is a fair game, once the market conditions are right," BharatPe CEO Nalin Negi told company closed FY25 with a Rs 6 crore adjusted profit before tax (excluding Esop expense), recovering strongly from a loss of Rs 342 crore in FY24."We have always believed that demonstrating consistent performance is key to building investor confidence ahead of a potential IPO," Negi company is backed by many marquee investors, including Peak XV, Tiger Global, Beenext, Steadfast Capital, and Ribbit is the only fintech player with an NBFC arm (Trillionloans), a stake in a Small Finance Bank (Unity SFB), and an online PA (payment aggregator) April this year, BharatPe received the final authorisation from the Reserve Bank of India (RBI) to operate as an online Payment Aggregator. The permit helped BharatPe scale its payment solutions across a broader merchant base, deepen its presence in tier II and III cities, and invest in building advanced technology infrastructure to support high-growth company has also increased its stake in its lending arm Trillionloans to 74%.

BharatPe to raise funds before IPO, listing not on card in FY26: CEO
BharatPe to raise funds before IPO, listing not on card in FY26: CEO

Business Standard

time30 minutes ago

  • Business Standard

BharatPe to raise funds before IPO, listing not on card in FY26: CEO

BharatPe will raise funds before the initial public offer, but the listing will take place only when market conditions are favourable, a top official of the unicorn fintech firm said. BharatPe, last week, announced that it had achieved operational profitability after excluding the employee stock ownership plan. "Whatever goals we set for ourselves, we have gone ahead and achieved has to remain intact, and thereafter, once the market conditions are right, we will definitely go for an IPO. There will be a pre-IPO funding round, while an IPO is not on the cards for this financial year. Anything beyond that is a fair game, once the market conditions are right," BharatPe CEO Nalin Negi told PTI. The company closed FY25 with a Rs 6 crore adjusted profit before tax (excluding ESOP expense), recovering strongly from a loss of Rs 342 crore in FY24. "We have always believed that demonstrating consistent performance is key to building investor confidence ahead of a potential IPO," Negi said. The company is backed by many marquee investors, including Peak XV, Tiger Global, Beenext, Steadfast Capital, and Ribbit Capital. BharatPe is the only fintech player with an NBFC arm (Trillionloans), a stake in a Small Finance Bank (Unity SFB), and an online PA (payment aggregator) license. In April this year, BharatPe received the final authorisation from the Reserve Bank of India (RBI) to operate as an online Payment Aggregator. The permit helped BharatPe scale its payment solutions across a broader merchant base, deepen its presence in tier 2 and 3 cities, and invest in building advanced technology infrastructure to support high-growth sectors. The company has also increased its stake in its lending arm Trillionloans to 74 per cent. (Only the headline and picture of this report may have been reworked by the Business Standard staff; the rest of the content is auto-generated from a syndicated feed.)

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store