Pakistan govt urges World Bank to restructure $393.73m HEDP project
ISLAMABAD: The government has requested the World Bank for restructuring of Higher Education Development in Pakistan (HEDP) project worth $393.73 million for the fourth time to allow for the completion of critical IT and IT-related activities at the universities whose impact will be seen beyond the project period.
The project is in its sixth year of implementation, and its project development objective (PDO) is to support research excellence in strategic sectors of the economy, improve teaching and learning and strengthen governance, in the higher education sector.
The Economic Affairs Division has requested a four-month extension through a letter as the project requires restructuring to complete five remaining packages under IT and IT-related services, which are at an advanced stage of contract implementation.
The additional time is sought following several disruptions and procedural delays, which delayed the delivery of IT hardware to ports and, subsequently, of deployment of related software and services packages. An extension of the closing date is needed to enable the project to complete the establishment of critical IT activities at the universities whose impact will be seen beyond the project period.
The overall project implementation progress is rated moderately satisfactory. Key results achieved by the project: (i) thirty one research grants awarded in Year 2 achieved 80 per cent of their outcome and 28 research grants awarded in Year 3 achieved 60 per cent of their outcome target, and nine RTTG awarded in Year 5 have achieved 50 per cent of their outcome targets; (ii) the NAHE conducted training for 1,113 faculty and 903 higher education managers, (iii) 50 QECACs completed SARs, (iv) twenty Affiliating Universities or ACs implement the career and internship framework; (v) 300 higher education institutions connected to PERN; and (vi) HEC developed, approved and rolled critical policies including the Undergraduate Education Policy and the Open Distance Learning Policy. Nine out of 11 intermediate results indicators have been met and two others will be met by June 30, 2025.
The disbursement as of June 10, 2025, from IDA Credit is $375.70 million, including $319 million against PBCs and $56.70 million for the IPF component. The final disbursement of $12.3 million against the PBCs has been approved and is being processed. The balance of the IPF component will be disbursed in fiscal year 2026.
This restructuring will only involve the extension of the project closing date by four months to October 31, 2025. The work plan will be adjusted with the proposed closing date. There will be no changes in PDO, PDO indicators, any activities or any components of the project as a result of this restructuring. No revision of implementation arrangement and M&E mechanism will take place. There will be no modification or scale-up of any activity of the project.
The extension of the project's closing date does not involve any modifications to the current Financial Management (FM), procurement, and environmental and social safeguards arrangements, which have been deemed adequate and will continue to effectively support the project's operations. The existing FM systems, including budgeting, disbursement, accounting, and financial reporting, including the reporting frequency, will remain unchanged and will operate according to the established procedures.
The project has been restructured thrice. The first restructuring was approved on June 14, 2021, to respond to the Covid-19 pandemic impacts and involved: (a) introduction of Component 6 to support continued learning for all in case of unpredicted crises and university lockdowns and provision of special funds to universities to increase their financial autonomy, (b) reallocation of funds between Components to better address ongoing needs, and (c) revision of the Results Framework to reflect the changes in activities.
The second restructuring was approved on June 15, 2023, to repurpose the unutilised funds from lapsed targets under Performance Based Condition (PBC) 1 and PBC 2 toward: (a) a new round of Rapid Technology Transfer Grants (RTTGs) focused on emergency response, climate change, extreme weather event preparedness and import replacement research (PBC 1, Component 1); (b) a new target to track RTTG outcomes (PBC 2, Component 1); and (c) an increased target for universities participating in the framework for improvement in financial autonomy (PBC 10, Component 6).
The third restructuring was completed on April 1, 2024 to: (a) extend the project closing date by 12-months to June 30, 2025; (b) adjust four PBC targets to align with implementation of activities; (c) drop two PBCs associated with activities no longer relevant and reallocate the associated $4 million to support funding required for Information Technology (IT) and IT-related activities and conduct a tracer study to inform labour market outcomes of higher education graduates; and (d) refine the Results Framework to reflect the activity changes, set more ambitious targets given the 12-month extension, and add a corporate scorecard indicator.
Copyright Business Recorder, 2025
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Business Recorder
4 hours ago
- Business Recorder
World Bank approves $194mn to support education & access to water in Balochistan
ISLAMABAD: The World Bank Board of Executive Directors on Tuesday approved $194 million for two projects to enhance educational opportunities for children and boost water security in Balochistan. 'The GRADES-Balochistan project aims to reduce learning poverty in the province, while the Balochistan Water Security and Productivity Improvement Project will help address the province's water security challenges and enhance climate resilience,' said Najy Benhassine, World Bank Country Director for Pakistan. 'The World Bank remains committed to supporting Balochistan through strategic investments in infrastructure and human development to build the foundations for more job creation, poverty reduction, and stronger resilience,' he added. The Getting Results: Access and Delivery of Quality Education Services in Balochistan (GRADES-Balochistan) project, i.e. $100 million, will benefit 250,000 students with a focus on increasing enrollment and improving literacy and numeracy skills in early childhood and primary education. Pakistan seeks fourth restructuring of $393.73mn WB-funded higher education project The project will also provide support for 5,000 teachers through continuous professional development programs. Additionally, scholarships will be provided to 400 female students to pursue teacher pre-service education, fostering a new generation of educators who will serve as mentors and role models. 'The GRADES-Balochistan project is a strategically important initiative that addresses critical gaps in access to and quality of pre-primary and primary education in the province,' said Inga Afanasieva, Team Leader for the project. 'The project not only aims to enhance educational infrastructure but also to increase resilience to disasters and environmental sustainability. These efforts underscore the World Bank's commitment to creating a safer and more sustainable future for the children of Balochistan.' Meanwhile, the World Bank also approved the Balochistan Water Security and Productivity Improvement Project (BWSPIP) i.e. $94 million, which aims to improve the lives of smallholder and tenant farmers in the Nari, Talli, and Lehri river basins of the Kachi Plain and improve water supply services in Quetta. The project is expected to benefit 500,000 people with improved access to basic water supply services and benefit more than 80,000 people by providing climate-resilient infrastructure. Key elements include enhancing flood protection, increasing access to water for productive use, and improving water supply service delivery. 'The project supports the implementation of Pakistan's Resilient Recovery Framework and aims to provide significant benefits for the farming communities in the province as well as for the residents of Quetta. It will also empower women in community-level water management,' said Carolina Dominguez Torres, Task Team Leader for the Project. 'Through strategic investments, improved water management, and community engagement, the project aims to deliver lasting benefits for the sustainable development of Balochistan.' The GRADES project, designed to reduce learning poverty, and the BWSPIP project, designed to reduce child stunting through increased access to safe water and sanitation services, are key outcome targets under the 10-year Country Partnership Framework for Pakistan, the World Bank said.


Business Recorder
7 hours ago
- Business Recorder
Pakistan govt urges World Bank to restructure $393.73m HEDP project
ISLAMABAD: The government has requested the World Bank for restructuring of Higher Education Development in Pakistan (HEDP) project worth $393.73 million for the fourth time to allow for the completion of critical IT and IT-related activities at the universities whose impact will be seen beyond the project period. The project is in its sixth year of implementation, and its project development objective (PDO) is to support research excellence in strategic sectors of the economy, improve teaching and learning and strengthen governance, in the higher education sector. The Economic Affairs Division has requested a four-month extension through a letter as the project requires restructuring to complete five remaining packages under IT and IT-related services, which are at an advanced stage of contract implementation. The additional time is sought following several disruptions and procedural delays, which delayed the delivery of IT hardware to ports and, subsequently, of deployment of related software and services packages. An extension of the closing date is needed to enable the project to complete the establishment of critical IT activities at the universities whose impact will be seen beyond the project period. The overall project implementation progress is rated moderately satisfactory. Key results achieved by the project: (i) thirty one research grants awarded in Year 2 achieved 80 per cent of their outcome and 28 research grants awarded in Year 3 achieved 60 per cent of their outcome target, and nine RTTG awarded in Year 5 have achieved 50 per cent of their outcome targets; (ii) the NAHE conducted training for 1,113 faculty and 903 higher education managers, (iii) 50 QECACs completed SARs, (iv) twenty Affiliating Universities or ACs implement the career and internship framework; (v) 300 higher education institutions connected to PERN; and (vi) HEC developed, approved and rolled critical policies including the Undergraduate Education Policy and the Open Distance Learning Policy. Nine out of 11 intermediate results indicators have been met and two others will be met by June 30, 2025. The disbursement as of June 10, 2025, from IDA Credit is $375.70 million, including $319 million against PBCs and $56.70 million for the IPF component. The final disbursement of $12.3 million against the PBCs has been approved and is being processed. The balance of the IPF component will be disbursed in fiscal year 2026. This restructuring will only involve the extension of the project closing date by four months to October 31, 2025. The work plan will be adjusted with the proposed closing date. There will be no changes in PDO, PDO indicators, any activities or any components of the project as a result of this restructuring. No revision of implementation arrangement and M&E mechanism will take place. There will be no modification or scale-up of any activity of the project. The extension of the project's closing date does not involve any modifications to the current Financial Management (FM), procurement, and environmental and social safeguards arrangements, which have been deemed adequate and will continue to effectively support the project's operations. The existing FM systems, including budgeting, disbursement, accounting, and financial reporting, including the reporting frequency, will remain unchanged and will operate according to the established procedures. The project has been restructured thrice. The first restructuring was approved on June 14, 2021, to respond to the Covid-19 pandemic impacts and involved: (a) introduction of Component 6 to support continued learning for all in case of unpredicted crises and university lockdowns and provision of special funds to universities to increase their financial autonomy, (b) reallocation of funds between Components to better address ongoing needs, and (c) revision of the Results Framework to reflect the changes in activities. The second restructuring was approved on June 15, 2023, to repurpose the unutilised funds from lapsed targets under Performance Based Condition (PBC) 1 and PBC 2 toward: (a) a new round of Rapid Technology Transfer Grants (RTTGs) focused on emergency response, climate change, extreme weather event preparedness and import replacement research (PBC 1, Component 1); (b) a new target to track RTTG outcomes (PBC 2, Component 1); and (c) an increased target for universities participating in the framework for improvement in financial autonomy (PBC 10, Component 6). The third restructuring was completed on April 1, 2024 to: (a) extend the project closing date by 12-months to June 30, 2025; (b) adjust four PBC targets to align with implementation of activities; (c) drop two PBCs associated with activities no longer relevant and reallocate the associated $4 million to support funding required for Information Technology (IT) and IT-related activities and conduct a tracer study to inform labour market outcomes of higher education graduates; and (d) refine the Results Framework to reflect the activity changes, set more ambitious targets given the 12-month extension, and add a corporate scorecard indicator. Copyright Business Recorder, 2025


Business Recorder
10 hours ago
- Business Recorder
Dasu hydropower project to start generating power by 2027: Asghar
LAHORE: Chairman WAPDA Naveed Asghar Chaudhry visited Dasu Hydropower Project Tuesday to review construction work on key sites, including the main dam, powerhouse, transformer cavern and the relocated section of the Karakoram Highway (KKH-1). The GM/PD Dasu Hydropower Project and representatives of the Consultants and the Contractors were also present on the occasion. The Chairman also presided over a progress review meeting at the project office. The project management team briefed him about the targets and the achievements on the project. He was briefed that construction work is currently underway on 20 different sites and is progressing at a steady yet satisfactory pace. Referring to the targets achieved so far and the milestones to be achieved in the days to come, it was briefed that the excavation works on both the right and left abutments of the main dam have been completed. The extended right bypass tunnel and the right-side open channel have also been completed and are ready to divert excess river flow during the high-flow season. Excavation of the main dam foundation is continuing and is scheduled for completion by October this year. Placement of Roller Compacted Concrete (RCC) in the main dam is expected to begin in March 2026. The excavation of the underground powerhouse is expected to be completed by February 2026, while the 25-kilometer-long relocated KKH-1-comprising seven tunnels and three bridges - is scheduled for completion by March 2026. Power generation from the project is expected to commence in 2027. Highlighting the strategic importance of Dasu Hydropower Project for Pakistan's energy needs and economic stability, the Chairman urged the Consultants and the Contractors to excel their efforts to meet the project timelines. Emphasizing upon the significance of maintaining the highest construction standards, the Chairman directed the Contractors to adhere to the stipulated quality standards for completion of the project. The 4,320 MW Dasu Hydropower Project is being constructed on the River Indus in Upper Kohistan District of Khyber Pakhtunkhwa with the financial assistance of the World Bank. The project is planned to be completed in two stages. Currently, WAPDA is executing Stage I, which will have an installed capacity of 2,160 MW and generate 12 billion units of clean, green, and affordable electricity annually. Copyright Business Recorder, 2025