Power Projects Gridlocked Due To Planning, Execution Failures

Power Projects Gridlocked Due To Planning, Execution Failures

Time of India7 days ago
New Delhi: With several key schemes aimed at strengthening Delhi's power transmission network going off track due to poor execution and persistent delays, Delhi Transco has submitted a presentation to the govt, urging a review of ongoing projects and the infusion of fresh ideas and innovative strategies for efficient implementation.
According to an internal document of Delhi Transco Limited (DTL), accessed by TOI, numerous schemes planned during the 13th Five-Year Plan (2017–22) and the first two years of the 14th Plan (2022–27) have faltered due to systemic inefficiencies. The document revealed that during the 13th Plan period, only 58 out of 120 proposed schemes were executed, and merely 36% of the planned expenditure—Rs 2,091 crore out of Rs 5,728 crore—was utilised.
It added that the situation so far remained the same under the 14th plan.
DTL was established in July 2002 following the restructuring of Delhi's power sector. Carved out of the Delhi Vidyut Board, it was designated as the state transmission utility, while power distribution was handed over to three private companies.
You Can Also Check:
Delhi AQI
|
Weather in Delhi
|
Bank Holidays in Delhi
|
Public Holidays in Delhi
The document further revealed that there have been 18 instances of transformer failures since 2020, but none have been replaced with new units.
by Taboola
by Taboola
Sponsored Links
Sponsored Links
Promoted Links
Promoted Links
You May Like
Linhas de expressão no rosto? Veja o que está virando febre entre as mulheres.
aartedoherbalismo
Undo
Instead, only stop-gap arrangements were made. Of these, 11 transformers failed before completing their 25-year regulatory lifespan. While five units were temporarily borrowed from other organisations, seven were relocated from other substations.
The document added that DTL's three substations remained non-functional for several days in July–Aug 2024 due to transformer failures, with old and repurposed units being used.
A source familiar with the matter said, "This over-reliance on makeshift fixes underscores a severe lack of planning, inventory, and urgency," adding that poor coordination and ineffective decision-making led to delays in timely and appropriate action.
DTL also highlighted the tenders failing to find contractors willing to take up the works, leading to delays in executing the projects in time. The document stated that a tender to procure a 500 MVA transformer was floated four times between 2020 and 2025 but was cancelled each time.
Similarly, a tender for a 160 MVA transformer was dropped five times since 2019. "This reflects a lackadaisical approach towards the requirement of crucial power transformers that are essential to meet Delhi's future load demand.
It further indicates poor planning, lack of market study, inaccurate estimation, and inclusion of unfavourable terms and conditions in the notice inviting tender," the Delhi Transco Limited said.
To address these inefficiencies, DTL has recommended the formation of a high-level monitoring cell to closely track the progress of ongoing schemes. It also called for organisational restructuring to infuse fresh ideas and strategies for efficient project execution. The utility stressed the need to revisit the schemes under the 14th business plan to ensure realistic, need-based planning aligned with future requirements and supported by achievable timelines.
"IT-enabled platforms may be leveraged to facilitate faceless vendor interactions and streamline various approval processes, ensuring transparency and efficiency. Core projects should be centralised for focused monitoring, while routine and non-critical matters should be decentralised to reduce the excessive burden on higher management and improve overall efficiency," the document stated.
Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

CoinDCX offers 25% bounty to recover stolen crypto in $44-mn hack
CoinDCX offers 25% bounty to recover stolen crypto in $44-mn hack

Indian Express

time6 minutes ago

  • Indian Express

CoinDCX offers 25% bounty to recover stolen crypto in $44-mn hack

CoinDCX, one of India's leading cryptocurrency exchanges, has announced a recovery bounty program after suffering a security breach that led to the loss of approximately $44 million (around Rs 379 crore). The company is offering up to 25 per cent of the recovered funds as a reward to those who help retrieve the stolen crypto and assist in identifying and bringing the attackers to justice. If all lost assets are recovered, the bounty could reach a total value of $11 million (Rs 94.6 crore). In a statement, CoinDCX emphasised that the effort goes beyond just recovering funds — it's about uniting the Web3 community to stand against cybercrime. 'This is not just about us. This is about standing up for what's right, for the safety, transparency, and future of the entire Web3 ecosystem. It's a war against cybercrime,' the company said. Co-founder Neeraj Khandelwal highlighted that the breach was not only an attack on CoinDCX but on trust itself. 'When one of us is targeted, all of us are affected. CoinDCX is committed to using this incident as a turning point—to strengthen our defenses, reinforce transparency, and work with the best minds in the industry to make recovery real and replicable,' he said. He added that the company is actively working with an exchange partner to block and recover the stolen assets and is fully committed to the recovery effort. 'We will emerge from this stronger, together,' Khandelwal said. The company also issued a call to action, inviting ethical hackers, white-hat researchers, and partners across the ecosystem to join the fight against cybercrime.

UltraTech Cement Q1 net profit rises 49% to ₹2,226 crore
UltraTech Cement Q1 net profit rises 49% to ₹2,226 crore

The Hindu

time6 minutes ago

  • The Hindu

UltraTech Cement Q1 net profit rises 49% to ₹2,226 crore

UltraTech Cement Ltd., an Aditya Birla Group company, reported 49% growth in consolidated net profit to ₹2,226 crore for the first quarter ended June 30, 2025 as compared with ₹1,495 crore a year ago. Consolidated net sales stood at ₹21,040 crore as compared with ₹18,626 crore a year ago, up 13%. The company's consolidated sales volumes reached 36.83 million metric tonnes for the quarter, growing 9.7% with the acquisitions of The India Cements Ltd and the cement business of Kesoram Industries Ltd. Energy costs were lower by 12% Year on Year, mainly on account of reduced fuel prices. Raw material costs marginally rose by 2%, the company said in a filing. India Cements, which was acquired by UltraTech last year has successfully turned around. 'Comprehensive efforts on multiple fronts have enabled India Cements generate an EBIDTA of Rs. 92 crore, compared to loss of ₹9 crore last year,' UltraTech Cement said. Through debottlenecking, an additional capacity of 0.3 mtpa has been released from the India Cements assets in the lucrative northern region, it added. UltraTech's expansion program is progressing as scheduled, with the company continuously enhancing its production capabilities to meet the growing demand for cement, it further said.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store