MARYLAND () — The Purple Line in Maryland is one step closer to opening. On Thursday, the Maryland Department of Transportation Maryland Transit Administration announced the start of dynamic testing for all eight light rail vehicles.
The testing will take place on the one-mile test track near the Operations and Maintenance Facility along Veterans Parkway in Prince George's County.
MoCo Minute | Grants available for small businesses along Purple Line
The Purple Line project is about 76% complete, and officials said seeing the light rail vehicles on the track shows its continued progress.
'Moving into the dynamic testing phase is a testament to the extraordinary collaboration of the Maryland Transit Administration, Purple Line Transit Partners, Maryland Transit Solutions and Purple Line Transit Operators along with support from our local and state elected officials,' said Ray Biggs, II, MTA Senior Project Director for the Purple Line
During the testing phase, crews will monitor the light rail vehicles as they go back and forth on the track to evaluate the mechanical system under real-world conditions. While evaluating the 142-foot light rail vehicles, team members will check onboard components such as braking, propulsion, electrical, signaling and communications systems.
The Purple Line Transit Operators will conduct the testing during the day and night. Once this phase is complete, future testings will involve the trains running on longer sections of the mainline track.
Officials noted that dynamic testing is expected to continue throughout 2026 as new light rail vehicles are received. This is a critical step to kickstarting service in late 2027.
Copyright 2025 Nexstar Media, Inc. All rights reserved. This material may not be published, broadcast, rewritten, or redistributed.
Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Report: How permitting requirements slow down California's transit projects
Report: How permitting requirements slow down California's transit projects

Los Angeles Times

time04-08-2025

  • Los Angeles Times

Report: How permitting requirements slow down California's transit projects

California's high-speed rail project has been heavily scrutinized in recent months for its long delays and rising budget. In its decision to pull federal funding from the project, the Trump administration blamed state leadership and the high-speed rail authority. A new report from a San Diego nonprofit points to third-party permitting requirements as another culprit to the project's long delays, and a reason for the slowdown on transit projects across the state. The report from the Circulate San Diego suggests that requirements first imposed decades ago to stop infrastructure projects from ripping up neighborhoods have created new hurdles that have put innovations around transportation years behind schedule. 'The policies meant to restrict highways from separating communities, are now preventing the construction of public transit, meant to stitch communities together,' Colin Parent, the chief executive and general council of Circulate San Diego, wrote in 'The Powerless Brokers: Why California Can't Build Transit.' The report was released Monday. The delays in transit projects aren't isolated to California, Parent said. But because the state's high-speed rail train is one of the most ambitious and widely criticized projects in the nation, the consequences of delays are staggering here. Multiple jurisdictions are often required to sign off on a project, outside of the leading transit agency. In the case of high-speed rail, Parent describes disputes that have occurred between the authority and city officials that have prolonged the timeline for construction. In Wasco, for example, disagreements between the city and the authority over the creation of an underpass and other projects led to years-long delays on construction and increased costs. 'I think a lot of people assume that when you're building transit, the transit agency decides what projects they want to build, they get funding, they do an environmental review, and then they're ready to go and to build things. And that's just not how it works,' Parent told The Times. 'They have to go through a whole new series of processes to receive permits and other agreements in order to actually build the projects that they've approved, and those additional sets of processes can create all sorts of delays, additional costs and other challenges to building the projects that policymakers say that we want to do.' Environmental reviews can take time, as can trying to gain public support. Not every city or county faces the same challenges when it comes to coordination on projects. The Los Angeles and Bay Area area regions each include 27 separate transit operators, Parent said. In the San Diego region, there are only two. In Los Angeles, Metro often has to coordinate with the Los Angeles Department of Transportation, Bureau of Engineering and Street Services. In the report, Parent highlighted the transit agency's extension project underneath Wilshire Boulevard for the D Line, formerly known as the Purple Line. The project saw broad support from city officials, but faced initial permitting challenges over demands by DWP and the Bureau of Engineering. In the early and middle 20th century, U.S. cities' infrastructure projects went unchecked, leading to the destruction of communities that largely displaced disadvantaged and working class residents. Perhaps no one represents the era better than the late urban planner Robert Moses, who shaped the New York City skyline and whose highway and bridge projects razed city blocks and neighborhoods. From his multiple appointed positions in state and local government, he was one of the most powerful and divisive figures in the state from the 1920s to the 1960s. In an effort to decentralize that kind of power with a system of checks and balances, community advocates pushed for laws to establish environmental standards and regulate project approval so that affected communities could be represented in decision-making. While no one has pushed for a return to the days of someone like Moses, Parent and state lawmakers in California believe that today's requirements have created new obstacles. 'A lot of the rules related to permitting that have gotten in the way of building infrastructure, including public transit, have really expanded since the 70s,' Parent said Monday. 'There's been this multi-decade growth in the kinds of barriers and hoops that applicants and public agencies have to jump through in order to get projects.' So, what's the solution? Because the delays in transit projects play out throughout the U.S., Parent believes standards in Quebec and Ontario could present a better model. There, transit agencies are allowed to self-permit if outside parties do not meet specific timeline requirements when it comes to permitting. 'Those local governments are under a timeline, and if they don't review and approve or deny those permits within a period of time, then the transit agency gets to self permit,' Parent said. State Sen. Scott Weiner (D-San Francisco) introduced a bill this year that takes a similar approach. With focus on high-speed rail, the bill would implement time limits on third-party's approvals and denial process. During a recent state assembly hearing, Wiener said that 'any city or water district or special district where some sort of encroachment permit is required' can slow down a project's process by simply doing nothing. 'They can just not respond or drag their feet — sometimes for good reason … sometimes for not good reasons — and there is nothing that, in this case, high speed rail, can do about it,' he said.

Metro D Line reopens Saturday after 70-day closure
Metro D Line reopens Saturday after 70-day closure

Los Angeles Times

time25-07-2025

  • Los Angeles Times

Metro D Line reopens Saturday after 70-day closure

The Metro D line, also known as the Purple Line, reopens Saturday after a 70-day closure for construction on the first phase of a rail expansion project beneath Wilshire Boulevard. The first phase of the extension project is budgeted at $3.7-billion to add three stations at Wilshire/La Brea, Wilshire/Fairfax and Wilshire/La Cienega to connect downtown Los Angeles with the Westside. That phase is 98% complete, Metro said, and is expected to open later in 2025. Station finishes, street restoration and testing remains. During the recent closure, the transit agency worked to connect communication and power systems between the existing line and new sections. Tracks have been laid, lighting has been installed and tunneling has been completed for that section, according to the transit agency. 'Staff and contractors are now working 24/7 to connect the older portions of the subway with the the newest section ... making sure that all power systems, train control, ventilation and signalization all work and function as one common and safe system,' Metro Board Chair Fernando Dutra said during a board meeting Thursday. The route between downtown Los Angeles and Koreatown is one of Metro's most heavily used with more than 65,000 daily boardings on average. The project to add seven stations and expand service on the line to Hancock Park, Century City, Beverly Hills and Westwood broke ground more than a decade ago. Metro's goal is to finish by the 2028 Summer Olympics. 'We're now at the home stretch to opening this game-changing subway extension project, which is going to be on schedule,' Dutra said. The second phase will include the Wilshire/Rodeo and Century City/Constellation stations, which are expected to open in 2026. The final section to add the Westwood/UCLA and Westwood/VA Hospital stations is slotted for a 2027 opening. Metro chief executive Stephanie Wiggins said that the D Line closure contributed to Metro's recent decline in ridership, which dropped 13.5% from May amid ongoing immigration raids throughout Los Angeles County, according to Metro data. The decrease in June boardings was the transit agency's lowest of the year and the lowest June on record since 2022. During the closure, riders relied on expanded B Line service, which shares D Line stops from Union Station to Wilshire/Vermont, and shuttle service from Koreatown.

Maryland transportation chief leaving post, citing upcoming 70th birthday
Maryland transportation chief leaving post, citing upcoming 70th birthday

Washington Post

time09-07-2025

  • Washington Post

Maryland transportation chief leaving post, citing upcoming 70th birthday

Maryland Secretary of Transportation Paul J. Wiedefeld is leaving the administration of Gov. Wes Moore (D) at the end of the month after two and a half years, saying his approaching 70th birthday is the right time to step down as an agency head. He is one of several Cabinet members to leave the Moore administration in recent weeks; the governor recently told state workers to prepare for a hiring freeze and possible buyouts. He will be replaced at least temporarily by Samantha Biddle, his deputy, who started her state government career as a planner for the State Highway Administration. Lt. Gov. Aruna Miller said in a statement that there would be a 'nationwide search' for 'a leader ready to meet the urgent needs of our transportation systems.' Wiedefeld led the department through the catastrophic collapse of the Francis Scott Key Bridge in Baltimore last spring, new costs and delays in building the Purple Line through the D.C. suburbs, a crisis in Metro funding and deep state budget cuts. Last month his office released an ambitious plan for expansion of MARC service. We have a team in place that's going to keep pushing,' he said. 'These are things that take time, but they pay dividends over time.' 'He was a steady hand for several years during difficult times,' said Del. Marc Korman (D-Montgomery). Del. Deni Taveras (D-Prince George's) used the same word, steady, to say why she was disappointed Wiedefeld was leaving before the Purple Line's long-awaited opening. 'I would like to have someone steady at the wheel through the very end,' she said. 'He's been phenomenal.' Along with that project, Wiedefeld leaves with no funding for a promised light-rail project in Baltimore, the American Legion Bridge in need of repair and Virginia looking to expand toll roads up to the state border with no commitment to continue them on the Maryland side. But he rejected the idea, becoming popular among some Democrats, that excessive red tape has made building infrastructure too difficult. 'It's something that we can all improve and it's at every level,' he said. 'But we have to remember that a lot of those process things that do irritate people because they can cost time, they were put in place to protect people. … whether it's a community impact issue, noise issues, environmental issues. At the end of the day we have to do something that the community can support; we're not going to just push through with something. Those days are gone.' Wiedefeld spent four decades in transportation, helming both the Maryland Aviation Administration and the Maryland Transit Administration. He was general manager of the Metro system for six tumultuous years; not long after he started he shut the system down over a fire and he left after pulling dozens of operators from service because of training lapses. Throughout, he struggled to change what an audit described as a 'toxic' and 'chaotic' environment inside the agency. At MDOT, however, Wiedefeld said he was confident he was leaving the system in good shape. 'A lot of our effort has been in rebuilding the culture in the department,' he said. His leadership team is strong enough, he said, that 'in effect, anybody could be secretary.' He said he would likely do some academic or nonprofit work in the future, 'but nothing on this scale.' 'I would spend much more time with my family, I would travel, live a little bit more of a normal life,' Wiedefeld said. 'This life is very demanding.'