Flood Protection Project Targets Vulnerable Area Of Nelson

Flood Protection Project Targets Vulnerable Area Of Nelson

Scoop06-07-2025
A multi-million dollar project that will increase the flood carrying capacity of the Maitai River between Hanby Park and Clouston Terrace will get underway this summer.
The most significant flood resilience project undertaken by Council since the Saxton Creek Upgrade, the work targets an area that saw some of the worst flooding during the August 2022 weather event.
This area of the Maitai is particularly vulnerable to flooding, with the existing stopbank at Clouston Terrace currently only capable of withstanding a 1:50 year flood event.
In August 2022, flooding affected properties between Nile Street, Mill Street and the stopbank.
'I have been involved with Civil Defence responses for 15 years. The flooding in this area in 2022 was some of the worst I have ever seen,' says Group Manager Infrastructure Alec Louverdis.
This project will reduce the risk of future flooding in the area in five ways, including:
New floodwalls
Upgrading the quality of existing stopbanks
Increasing the capacity of the river channel
On Tuesday 24 June, Council held a community meeting with affected residents to present the project plan for the Maitai between Hanby and Clouston.
'This is exciting for us from a technical point of view, but also for the solutions developed by our specialist engineering consultants Tonkin & Taylor,' says Alec.
'We were encouraged by the positive and supportive response from residents and we will keep in close contact throughout the work. All were keen for the work to start as soon as possible.'
Advertisement - scroll to continue reading
Tonkin & Taylor looked out as far as 2130 and modelled solutions for a range of present day and future extreme weather scenarios. Their main focus was to maintain recreational access and the integrity of the river.
'Some solutions looked at potential property purchases but Tonkin and Taylor's innovative and practical design allows us to achieve the required outcomes without going down this avenue. The decision to take land from Hanby Park instead was a practical and compassionate solution and we're really happy with the outcome.'
The summary of the proposed work includes:
Lowering the level of the bank under the east bridge span creating more space under the bridge for pedestrians and cyclists.
A 2m flood wall alongside the new pathway adjacent to Clouston Terrace, that will extend to chest height above the road carriageway.
'We are raising Clouston Terrace,' says Alec. 'Clouston Terrace, which runs alongside this section of the river may be raised by over a metre, as a result we will need to reconfigure several property accessways. We will be working with residents for the best solution for each property.'
Once the project is complete, Council will work closely with residents to discuss options for enhancing the area, including opportunities for planting and artistic detailing of the concrete wall.
These finishing touches are an important way to reflect the character of the neighbourhood and involve the community in shaping the final look and feel of the space.
The project team recognise the importance of protecting the natural ecology both in and around the river.
A lizard survey found the protected northern grass skink inhabits the Maitai River banks within the works area.
Council has sought a Wildlife Act Authority permit from Department of Conservation to salvage the lizards and relocate them to the pest-free Brook Waimārama Sanctuary.
Along with the local lizards, the Maitai is considered as a 'high' value habitat with a diverse native fish community. In-river construction will be timed to avoid the spawning season for bullies and trout, and erosion and sediment control measures will be in place to protect water quality and instream habitat.
Where works in the water cannot be avoided, ecologists will capture and relocate fish away from the construction zone. Once completed the floodways will provide additional habitat for fish and planting will provide shade for fresh water species. For the local birds, works will be undertaken outside of bird breeding season where possible and bird nests will be checked prior to any removal of vegetation.
Notes:
Four individual projects make up the wider Maitai Flood Resilience project. This overall project includes stormwater intake upgrade on Cleveland Terrace, river flood improvements from Hanby Park to Clouston Terrace, a flood wall upgrade and extension on Nile Street and at stormwater improvements at Queens Gardens for a total budget of $9 million, for which we are receiving $5.4 million from Central Government through the Regional Infrastructure Fund. This work will be carried out over the next two financial years and completed by July 2027.
Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Friendly Reminder: New Winter Grazing Rules Now In Effect
Friendly Reminder: New Winter Grazing Rules Now In Effect

Scoop

time23-07-2025

  • Scoop

Friendly Reminder: New Winter Grazing Rules Now In Effect

Marlborough District Council is reminding farmers that new regulations for intensive winter grazing and stock exclusion took effect on 1 July 2025. These changes follow amendments to the National Environmental Standards for Freshwater and are part of a nationwide effort to enhance freshwater health. Between May 1 and September 30, farmers must exclude cattle from all intermittent and permanent waterways (wider than one metre at any point) when grazing winter forage crops. This includes paddocks with rivers, lakes, wetlands, and modified waterways, regardless of whether water is present at the time. The two new standalone regulations for intensive winter grazing include: Maintain a five-metre planting setback from any water body or drain. Avoid cropping and grazing critical source areas with direct connection to waterways. Permanent vegetation must be maintained in these areas to assist in filtering runoff and safeguarding water quality. Council's Regional Catchment Facilitator, Nic Dann, said the regulations help minimise the impact of livestock on water bodies and wetlands. 'The Council's Catchment Care Team is here to support farmers with practical advice and resources to help meet these requirements. We encourage all landowners to review the regulations and ensure their grazing practices align with the new standards. 'Let's work together to protect Marlborough's waterways for future generations.'

Real-Time Flood Alert Sensors Installed On Havelock North Streams
Real-Time Flood Alert Sensors Installed On Havelock North Streams

Scoop

time18-07-2025

  • Scoop

Real-Time Flood Alert Sensors Installed On Havelock North Streams

Residents living near five Havelock North streams will have a real-time view of their water levels. Hastings Havelock North ward councillor Malcolm Dixon described the new water flow sensors as 'wonderful progress'. 'The sensors monitor the level, flow and pressure of the streams and quickly put out alerts on rising water levels, allowing people to be prepared during weather events,' Dixon said. 'The sensors would be advantageous to everyone living in the area,' he said. Thirteen of 15 planned monitors are in place, with the remaining two to be installed after bridge work on Joll Rd has been completed and an appropriate location has been confirmed on the Karituwhenua Stream. Once the project is complete, there will be three monitors on the Herehere, four on the Mangarau, three on Te Kahika, two on School, and three on the Karituwhenua streams. Joll Rd was flooded during Cyclone Gabrielle, due to a huge surge of water flowing through the nearby Mangarau Stream. More than 40 properties near the Mangarau Stream were placed in Category 2C after the cyclone. Earlier this month, the property owners were informed they had been recategorised as Category 1 – the lowest flood risk category, after almost two and a half years in limbo. In May, a report from Chief Ombudsman Peter Boshier chided the council, saying it had not acted for years despite concern from engineering consultants Stantec, which conducted annual checks of the dams, had noted failure of the dams would cause significant damage and could result in fatalities. Hastings Mayor Sandra Hazlehurst said the project was valuable for Havelock North residents, who could now be reassured that in severe weather, timely data would show the water levels on the streams. 'The five streams all run through residential urban areas into the Karamū Stream, so we need near real-time information on what is happening. 'Council will monitor and be able to see trends over time to inform future planning and investment and monitor stream levels during heavy rain,' she said. Council staff are monitoring the sensors and from September, once a process enabling the data to be fed through to the website is complete, residents will be able to access a dashboard to view the information. Council has partnered with Adroit Environmental Intelligence to install the real-time environmental monitoring sensors. Council's programme manager Darren de Klerk said the website dashboard will integrate water level data with local MetService information, and the Havelock North dam monitoring system, to provide a unified view for the council to monitor and residents to check. 'We are excited about releasing this dashboard on our website. It will help build confidence within the community, with residents and other interested people able to keep an eye on stream levels,' de Klerk said. Adroit general manager Guy Macpherson said the new high-tech monitoring system is the most comprehensive example of environmental sensors used for flood detection and emergency response in action in New Zealand, and is 'likely to set the standard for other councils and regions'.

Northbank Road To Open Overnight
Northbank Road To Open Overnight

Scoop

time18-07-2025

  • Scoop

Northbank Road To Open Overnight

Press Release – Marlborough District Council From Monday to Friday the slip will continue to be open overnight and then closed from 9am to 4pm daily. Following requests from the community, there will be an additional opening on Wednesdays from 12pm to 1pm, starting this coming Wednesday 23 July. As crews continue to work across the region following the June-July weather event, there is some good news for Northbank Road residents today with the road now open overnight under stop/go traffic light management from 4pm today. 'Marlborough Roads' crews have continued to work at multiple sites on Northbank Road and its side roads to regain access. The crew at the slip, 2km from the start of the road have made some great progress this week,' Marlborough Roads System Manager Wayne Oldfield said. 'They have managed to establish a catch bench at the base of the slip to collect any uncontrolled rockfalls. This means that we can now open the road overnight under stop/go traffic light management so from 4pm the road will be opened under traffic lights for the weekend.' The slip will be inspected throughout the day and if deemed unsafe the road will be closed and an update sent via Council's Facebook Page and Antenno. Mr Oldfield said the slip was complex and had contained around 25,000 tonnes of rock, was around 40m in height and 60m in length. 'At this stage, we are unable to have a lunchtime opening every day due to the additional time this would add for the overall timeline of works. We want to get as much clearance works completed on the slip as we can while the weather is more stable. 'The openings will continue to be reviewed and if there is an opportunity to increase them safely, this will be done,' Mr Oldfield said. From Monday to Friday the slip will continue to be open overnight and then closed from 9am to 4pm daily. Following requests from the community, there will be an additional opening on Wednesdays from 12pm to 1pm, starting this coming Wednesday 23 July. Mr Oldfield said when people were travelling near or past work sites across the region, they should ensure they keep outside any fences or barriers for their safety and adhere to, and do not move, any traffic or safety management in place. Marlborough Roads' crews have also been working to clear a second major slip 17km from the start of the Northbank Road this week. This section of the road is now open to one lane and will remain under stop/go traffic light management. 'Work continues on Noel's Bridge, further down Northbank Road, to regain access. The bridge will be accessible to residents for essential travel including heavy vehicles from 4pm this afternoon. 'Next week, there will be rock protection work at both Top Valley Bridge and Noel's Bridge, along with other work sites so people should expect multiple delays,' Mr Oldfield said. Flyers have been distributed to the Northbank and Onamalutu community with Council's Facebook page, website, road Alerts and Antenno messages regularly updated.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store