
More than half Crown Regional Holdings/Provincial Growth Fund loan book ‘at risk'
'While this increase continues the trend from the previous reporting period, it is not unexpected when factoring the challenging macroeconomic environment,' Rae said.
'It is also important to remind ourselves that the space that the funds are almost universally targeted is into areas that banks and other financiers are either unwilling, or on a very limited basis, prepared to support – which makes our investments inherently more subject to risk.'
CRH's single largest exposure is the expansion and development of Ōpōtiki Harbour, where $110m has been spent to date.
While loans make up the bulk of CRH outgoings, it has also made equity investments in regional businesses – such as the $52m tipped into loss-making Whakatōhea Mussels Ōpōtiki.
Revaluation of CRH's equity portfolio wasn't all one-way in the 2024 financial year.
The 2023 report had impaired a $7m equity investment into lithium and silica extraction startup Geo40 after its main plant suspended production and there were 'material indicators of uncertainty in the going concern of the entity'.
By 2024, however, Geo40 had resumed production and a secondary market share sale had allowed CRH to revalue its equity stake to $6.2m. Geo40 is also the recipient of $10m in loans from CRH.
The release of CRH's 2024 annual report was held up for nearly a year over how to assess its loan and investment portfolio. Audit NZ said it needed to 'ensure that the risks associated with these complexities are addressed appropriately'.
At the end of May, CRH said it was expecting the report to be published in 'mid-June'.
In early July, the Ministry of Business, Innovation and Employment said the report would soon be tabled to Parliament, which finally happened on July 10.
The Audit Note attached to the 2024 report is identical to that filed the previous year, including an emphasis on matters regarding uncertainty in estimating the value of loans and securities and how discount rates and expected credit losses are determined.
The next report is likely to see more write-downs, with CRH flagging a further three loan recipients have entered liquidation since balance date.
In November 2023, CRH approved a loan of up to $5m for Hawke's Bay cherry producer Cherri Global to help the company recover after Cyclone Gabrielle. Less than 18 months later Cherri collapsed into liquidation.
The first report by liquidators PwC showed CRH is among unsecured creditors owed $42m by the Cherri group.
Ashburton-headquartered plant-based food manufacturer Sustainable Foods had been advanced $1.4m by CRH.
Sustainable Foods entered voluntary administration in August. Its proposal to restructure its debts was voted down at the watershed meeting in November and the company had liquidators from PwC appointed.
Despite a general security agreement, the liquidator's second report said the CRH loan was likely to face an $895,616 shortfall.
Overall, Sustainable Foods is expected to leave all creditors more than $2.5m short.
Timber wholesaler Guru NZ was tipped into liquidation in February. CRH is listed as one of six unsecured creditors who are collectively owed $773,085.
Receivers were separately appointed to Guru in March by the China Construction Bank which sought repayment of $3.1m.
The first receivers' report, prepared by McGrathNicol, said Guru owed a total of $14m to creditors and an estimated shortfall of $7.7m would mean unsecured creditors would be left with nothing.
Matt Nippert is an Auckland-based investigations reporter covering white-collar and transnational crimes and the intersection of politics and business. He has won more than a dozen awards for his journalism – including twice being named Reporter of the Year – and joined the Herald in 2014 after having spent the decade prior reporting from business newspapers and national magazines.

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Newsroom
18 hours ago
- Newsroom
Overseas investment changes will undo water bottling safeguard
Special conditions designed to safeguard New Zealand water from foreign-owned bottling operations will be stripped out of the overseas investment regime as part of changes being advanced by the coalition Government. Critics have also raised concerns about the removal of protections for offshore investments in forestry, citing the impact of forestry slash in the wake of Cyclone Gabrielle and other weather events.


NZ Herald
2 days ago
- NZ Herald
Hawke's Bay: New Puketapu Bridge's opening date set
It linked to Puketapu Rd and Dartmoor Rd - the two main routes servicing the farming areas of Patoka, Puketitiri, Puketapu and Rissington. Work began for the rebuild in June 2024. Completion was planned for late June to early July 2025, but was pushed back to August. Six piles at a depth of 41 metres were installed, and the bridge is said to be much larger than a typical bridge. Earlier, Hastings District Council had said the average road bridge pile in Hawke's Bay had a depth of 12 metres, and were 1.2 metres in diameter. Puketapu's piles are 1.8m in diameter. The bridge opening date had been dependent on pavement progress in winter. The Puketapu Hotel owner Mary Danielson inside the iconic pub in March 2023. Puketapu Hotel owner Mary Danielson said two words came to mind with the news a date was set - 'Whoop, whoop'. '(We) are just beside ourselves, so excited for our community and the south side to be back with us.' The family faced a rebuild themselves after the pub and restaurant in the centre of the village was badly flooded during Cyclone Gabrielle. The Danielsons, whose home was not damaged, helped distribute goods and donations during the flood recovery and managed to open their establishment months after the destruction to become a community hub. 'It means so much to our community for the business side... it's massive with the cycle trail, it's for everybody,' Danielson said. 'To join the south and north again is just amazing.' A date of August 23, 2025 has been set for the opening of the Puketapu Bridge. Photo / Michaela Gower Danielson said they were expecting more business at the Puketapu Hotel, including cyclists using the cycle trail. Work on the bridge currently includes preparation for asphalting, pavement works and surfacing of the approaches to the bridge. Tree removal for the viewing area/lookout, and balustrade works are also being undertaken. In December 2024, National Infrastructure Funding and Financing (formerly known as Crown Infrastructure Partners) said the estimated cost for the overall project was $26 million. HDC transportation manager Jag Pannu said work is anticipated to begin on the Rissington Bridge in September 2025, subject to the tender being awarded. The new structure is downstream of the existing temporary bridge, which will remain open to road users. Meanwhile, Pannu said Downer is continuing with work that has closed Waihau Rd from Price Cockburn Rd to Dartmoor Rd. This closure is enabling repairs to be completed at three slip sites along the road, as well as structural repairs to Horgan's Bridge. The work includes road realignments (retreats), drainage improvements, and road surface upgrades. In addition, Berketts Earthmovers Ltd are repairing two slip sites north of Horgans Bridge in a project that also involves road realignment and drainage improvements. Once the full road closure ends, work will continue under a priority give-way traffic system. Michaela Gower joined Hawke's Bay Today in 2023 and is based out of the Hastings newsroom. She covers Dannevirke and Hawke's Bay news and loves sharing stories about farming and rural communities.


NZ Herald
4 days ago
- NZ Herald
Berry Tasty: Cyclone survivor takes over well-known Napier eatery
Berry Tasty workmates (from left) Kimmi Isaac, Mel Gale, Briar Ferguson, and Reese Barraclough. Photo / NZME Cyclone Gabrielle washed away Mel Gale's first business. On Friday, Gale took over her new business and eatery - Berry Tasty in Napier's Bay View - marking a big milestone for her young family. Her family lost their home in Esk Valley during the devastating 2023